HomeMy WebLinkAbout19.41.1.1 - Sewage Disposal System Design (2)4 UNITS
REVISIONS
NO. DATE DESCRIPTION
1. 8/16/00 B.O.H.:.ISSUE
2. 12/11/00 B.O.H. CO".IMENTS
3. 6/3/02: ' REVISE HSE. LOC.
4. 6/19/02 ADD. POOL
GENERAL NOTES:
L THIS PLAN IS FOR DESIGN AND ,
CONSTRUCTION OF THE SEWAGE
DISPOSAL • FACfUTY ONLY.
2. ALL CONSTRUCTION METHODS AND
MATERIALS SHALL CONFORM TO MASS.
D.E.P TITLE 5 AND LOCAL BOARD
OF HEALTH REGULATIONS.
3. ALL PIPES LOCATED UNDER PAVEMENT '
OR TRAVELED WAY SHALL BE SCHEDULE
40 OR EQUAL.. -
4. THERE ARE NO KNOWN PRIVATE WELLS
LOCATED WITHIN '150 FT. OF THE
PROPOSED LEACHING FACILITY NOR
ANY KNOWN WELLS PROPOSED WITHIN
150' OF ANY KNOWN .LEACHING FACILITY.
5. WITHIN LIMIT OF EXCAVATION REMOVE
ALL TOPSOIL, SUBSOIL AND OTHER
IMPERMOUS MATERIAL
6. REPLACE WITH CLEAN WASHED SAND
OR OTHER CLEAN GRANULAR SOILS
CONFORMING TO THE FOLLOWING
SIEVE'ANALYSIS:
10% (MAX) BY WT.SHALL
PASS No. 50 STEVE
<10 % OF No. 4 SIEVE SHALL
PASS No. 100 - -
<5 9. OF No. 4 SIEVE SHALL
PASS No. 200
UNIFORMITY COEFFICIENT ® No. 4
SIEVE </=6.0
7. EXISTING UTILITIES WHERE SHOWN
IN THE DRAWINGS ARE APPROXIMATE.
THE CONTRACTOR SHALL BE RESPON—
SIBLE FOR PROPERLY LOCATING -AND
COORDINATING THE PROPOSED CON—
STRUCTION ACTIMTY 141TH DIG—SAFE
AND THE APPLICABLE UTILITY
COMPANY AND MAINTAINING THE
EXISTING'UTIUTY SYSTEM IN SERVICE-
ERVICEDIG—SAFE
DIG—SAFESHALL BE NOTIFIED PER
THE STATE OF MASSACHUSETTS
STATUTE CHAPTER 82, SECTION 409
AT TEL 1-888-344-7233. THE
ENGINEER DOES NOT GUARANTEE
THEIR ACCURACY OR THAT ALL
UTILITIES AND SUBSURFACE STRUCTURES
ARE SHOWN. LOCATIONS AND
ELEVATIONS OF UNDERGROUND UTTLITIES
TAKEN FROM RECORD PLANS. THE
CONTRACTOR SHALL VERIFY SIZE,
LOCATION AND INVERTS OF UTILITIES
AND STRUCTURES AS REQUIRED PRIOR
TO THE START OF CONSTRUCTION.
8.' THIS SYSTEM iS NOT DESIGNED FOR
THE USE OF A GARBAGE GRINDER.
A GARBAGE GRINDER IS NOT
RECOMMENDED DUE TO RECOGNIZED
:.ADVERSE IMPACTS TO THE .LEACHING
FACILITY. - ..
1 #.
l
The BSC Group Inc. u
^ 1
�
I
657, ROUTE '28, (UNIT 6) LL« W
WEST YARMOUTH, MA: 02673
(508) 778-8919 "
PROJECT TITLE:
SEk AGE -DISPOSAL
SYSTEM DESIGN
LOT 1
PARKERS
li-19
NECK ROAD
S., YARMOU TH '
.
1
Pik
Ll FOR:
BARRY DUNN
AND
BOSWORTH ASSOCIATES
P.O. BOX 685
1645 FALMOUTH ROAD,'` UNIT, C
CENTERVILLE, MA
02632
DATE: JULY 12, 2000
COMP. DESIGN:' K. HEALY
CHECK: D. CRISPIN/L. MACDONALD
DRAWN: K. HEALY
FIELD; P.H. / A.D.
FILE NO. 8188-SEP.DWG
DWG N0. 5179-13;
:SHEET - 1 OF I
JOB N0, 4-8188.00
t