HomeMy WebLinkAbout36.106.1 - Design for Sewage Disposal SystemSOIL TEST PIT DATA: APRIL 25, 2007 TEST PIT #1_- TEST PIT #2_ TEST PIT #3 TEST PIT -#A GRD. EL. 21.2 GRD. EL. 21.8 GRD. EL. 22.5 GRD. EL 22.7 EST. HIGH GW. N/A EST. HIGH GW. 11.2 EST. HIGH GW. N/A EST. HIGH GW. N A FILL LOAMY SAND 10YR 3/4 LOAMY SAND 10 EL = 11.7 MEDIUM SAND 1OYR 7/4 MEDIUM 7/4 D 127 NO G.WATER „ NO G.WATER „ EL = 77 162 EL = 9 5 = 147 EL = 10.0 150 90" 96" 114" FILL A LOAMY SAND 1OYR 3/4 LOAMY S ND 10YR 8 EL = 13.8 MEDIUM SAND 10YR 7/4 - DAMP SOIL 60" 72" LOAMY SI�ND 10YR 6 8 72" EL = 14.0 102" 96" t. SEPTIC TANK DETAIL: 3,500 GALLON H-20 NOT TO SCALE 2 COMPARTMENT I/A SYSYEM NOTES: 1. SEPTIC TANK SHALL BE STEEL 5. INLET AND OUTLET TEES TO BE CAST IRON, REINFORCED CONCRETE. SCHED. 40 PVC OR CAST -IN-PLACE CONCRETE. 2. SEPTIC TANK TO WITHSTAND H-10 LOADING TEES TO BE CENTERED UNDER MANHOLE COVER. UNLESS UNDER PAVEMENT, DRIVES OR TRAVELED WAYS, WHEREIN H-20 LOADING SHALL APPLY. 3. ALL PIPE CONNECTIONS AND CONCRETE 2-24" DIA CONCRETE MANHOLES CONSTRUCTION SHALL BE WATERTIGHT. W/ METAL HANDLES BROUGHT 4. FILL ALL UNUSED KNOCKOUTS WITH TO 6" OF FINISH GRADE MORTAR. TEE TO BE UNDER 12" MIN. M.H. OPENING -1 COVER DISTRIBUTION BOX DETAIL: NOT TO SCALE 1-3, �pab � $gyp �a� $a�$aV,�a L IN PUMPED SYSTEM. 2' 3. FIRST TWO FEET OF PIPE OUT OF DIST. RAISE M.H W 4" BOTTOM ON LEVEL 6" MIN. 3 4" TO STABLE BASE / BOX TO BE LAID LEVEL. 10'-6" SEWER BRICK p - - p_ �_•: 1 1/2" CRUSHED & MORTAR p- p p p 4. ALL PIPE CONNECTIONS AND CONCRETE CROSS-SECTION STONE BASE �.o.; NORMAL WATER LEVEL 12" CONSTRUCTION SHALL BE WATERTIGHT. e: 3" _ PRECAST SEPTIC TANK � 110" 14• T w INLET TEE 5•-1" O - 5-2" 4'-6" p 4'-0" MIN. so mm oM p 5-8• 15 1/2' ? LIQUID DEPTH �ws e p x/ x 1 PRECAST DIST. Box m m 5. FILL ALL UNUSED KNOCKOUTS WITH MORTAR. LEACHING FIELD DETAIL: NOT TO SCALE 36" MAX .COVER FINISHED GRADE F\ eCAP ENDS 4" PVC' ..� . i_, �4 P�F S��i eU g� SSo4.005'('a e s i'e e $.411_ Po$a�b�'���b$a°or e+ea sa ea ea ea ea oa ete s+oa ea IirWTM �a a4Pa° 9P 4°Pe9� ' uDfc4p+ e e ` ' LEVEL BOTTOM \ I 50' PROFILE /- 36" MAX. - 12" MIN. COVER 2% MIN. FINISH GRADE 4" MIN. LOAM & SEED LOAM do SEED DISTURBED AREAS 311 MAXIMUM i 15' MIN _ _ .. ,-c..--i-^x�••..._.,__ map era 6'B'P`f9°T2" MIN. OF 1/8• TO 8`d re o a p°lv e e e� "ewe L1/2" WASHED STONE 162 I__ 3/4" TO 1-1/2" DOUBLE e 3" WASHED STONE (NO FINES) �I-�� q I 9Pa BOTTOM ON LEVEL STABLE BASE_*6 PLAN VIEW y, TYP DATE: 6" MIN. 3/4" TO �4 "4- � CROSS-SECTION VIEW PLA VIEW I ( 32 4/25/07 1 1/2" STONE CROSS-SECTION TEST BY: INDICATES #f_ THE BSC GROUP, INC. �_ ESTIMATED WF '41 �� / WITNESSED BY: SEASONAL HIGH / It '/ ' f - f // � \ ' , , T3P� GROUND \ DESIGN CRITERIA: PHIL RENAULD HIGH GROUNDWATER COMPUTATION INDICATES �T3(' \ PERC. RATE: BASED ON TP#2 Ji, � OBSERVED DESIGN FLOW: ASSUME 2 MIN./INCH DEPTH TO DAMP SOIL 12.3 GROUND WATER / // �� - - j O ✓ \ \ ' SOIL EVALUATOR INDEX WELL Miw-zs 6920 S.F. @ 75 GALLONS / 1000 S.F. // / - - / WF 6 \ MARK DIBB WATER LEVEL RANGE ZONE C INDICATES o T2P1 -1106V�/ // / - - / N78 4 ` \ \ \ \ 1 \ = 520 G.P.D. CURRENT DEPTHOINDEX WELL(4/07) 7.0 PERC. SOIL CLASS: WATER LEVEL ADJUSTMENT 1.7 TEST �A \ / / / / _ \ \ ,' /T2P2 2 � ( \ \ 5 BEDROOMS @ 110 GPD PER BEDROOM 1 DEPTH TO ADJUSTED HIGH WATER 10.6 VHF INDICATES 550 G.P.D. L.T.A.R. ® UNSUITABLE tlt, / / / \ \ 0.74 G.P.D./SQ.FT. MATERIAL ' -' , \ \ \ TOTAL DAILY FLOW = 1,070 GPD 7r U 1 1 WF#5 +I , REQUIRED SEPTIC TANK: DATUM: �' WF#3 / ' 'f' I i ,I `°� 1,070 X 300% = 3,210 GAL. VERTICAL DATUM: N.G.V.D. 1929 tII // // // // / / S / �\ �i,, N I I , \ F SEPTIC TANK PROVIDED: = 3.500 GAL. BENCH MARK USED: RM- fli /// // // // / / \ I ' 1 ` \ \ WF#58 BENCH MARK SET: TOP OF CONCRETE BOUND = 23.12 \ /�/ // // // / / + I / �� 1 , \ \ 8.39'40"C -� SIZE OF LEACHING FACILITY REQUIRED: I�DRAINAGE \ ` t \ \N7�g1, CONCRETE DESIGN PER <2 / / / AREA 1 , \ \ \ 201 BOUND \ C. RATE: MIN./ INCH 1 \ WF / / // / / / I I FOUND LONG TERM APPL. RATE 0,74 G.P.D/S.F. PROFILE: NOT TO SCALE y� 1,070 GPD = 0,74 GPD/SF = 1,446 S.F. WF1�5 El.= A I t11 / / / / / / / / # TOP FOUNDATION FIRST PIPE LENGTH ! CONCRETE COVERS TO WITHIN TO BE SET LEVEL EL.= 22.0 6' OF FINISHED GRADE. WF#37 ,� j // / / / // / / \ 11 `I I ; I tl�J WF#6b SIZE OF LEACHING FACILITY PROVIDED: 4' PVC SCH 40 �/ 1 USE ONE 50'x32' 5 OUTLET DIST. BOX SEPTIC TANK INVERT ELEVATIONS: TOP OF FOUNDATION 22.50 4" INVERT AT BUILDING 20.50 NO. OF OUTLETS 5 20.00 FINISHED GRADE 19.75 4" INVERT AT DIST. BOX (IN) 19.50 EMOVABLE -� I-- 2" WALLS NOTES: OVER ANY KNOWN WELLS PROPOSED WITHIN OF LEACHING FIELD 19.00 4" INVERT AT END IMPERVIOUS MATERIAL- ATERIAL6. OF LEACHING FIELD j• ELEVATION AT BOTTOM 1. DIST. BOX TO WITHSTAND H-10 LOADING ,Q:•4.••,p:•9..�,d::V .... j: ry.:: 17.80 ADJUSTED TT GROUNDWATER UNLES UNDER S OR TRAVELED WAYS PWHERENTH-20L LOADING OBSERVED GROUNDWATER 9.50 T 15" SHALL APPLY. 6" •. 5,5" OUTLETS' 8" 10%-100% MUST PASS #50 SIEVE 1 2. PROVIDE INLET TEE OR BAFFLE WHERE (0.15 mm EFFECTIVE PARTICLE SIZE) 0%-5% MUST PASS #200 SIEVE (0.075 mm EFFECTIVE PARTICLE SIZE) 7. EXISTING UTILITIES WHERE SHOWN SLOPE OF PIPE EXCEEDS 0.08 FT./FT OR 1-3, �pab � $gyp �a� $a�$aV,�a L IN PUMPED SYSTEM. 2' 3. FIRST TWO FEET OF PIPE OUT OF DIST. RAISE M.H W 4" BOTTOM ON LEVEL 6" MIN. 3 4" TO STABLE BASE / BOX TO BE LAID LEVEL. 10'-6" SEWER BRICK p - - p_ �_•: 1 1/2" CRUSHED & MORTAR p- p p p 4. ALL PIPE CONNECTIONS AND CONCRETE CROSS-SECTION STONE BASE �.o.; NORMAL WATER LEVEL 12" CONSTRUCTION SHALL BE WATERTIGHT. e: 3" _ PRECAST SEPTIC TANK � 110" 14• T w INLET TEE 5•-1" O - 5-2" 4'-6" p 4'-0" MIN. so mm oM p 5-8• 15 1/2' ? LIQUID DEPTH �ws e p x/ x 1 PRECAST DIST. Box m m 5. FILL ALL UNUSED KNOCKOUTS WITH MORTAR. LEACHING FIELD DETAIL: NOT TO SCALE 36" MAX .COVER FINISHED GRADE F\ eCAP ENDS 4" PVC' ..� . i_, �4 P�F S��i eU g� SSo4.005'('a e s i'e e $.411_ Po$a�b�'���b$a°or e+ea sa ea ea ea ea oa ete s+oa ea IirWTM �a a4Pa° 9P 4°Pe9� ' uDfc4p+ e e ` ' LEVEL BOTTOM \ I 50' PROFILE /- 36" MAX. - 12" MIN. COVER 2% MIN. FINISH GRADE 4" MIN. LOAM & SEED LOAM do SEED DISTURBED AREAS 311 MAXIMUM i 15' MIN _ _ .. ,-c..--i-^x�••..._.,__ map era 6'B'P`f9°T2" MIN. OF 1/8• TO 8`d re o a p°lv e e e� "ewe L1/2" WASHED STONE 162 I__ 3/4" TO 1-1/2" DOUBLE e 3" WASHED STONE (NO FINES) �I-�� q I 9Pa BOTTOM ON LEVEL STABLE BASE_*6 PLAN VIEW y, TYP DATE: 6" MIN. 3/4" TO �4 "4- � CROSS-SECTION VIEW PLA VIEW I ( 32 4/25/07 1 1/2" STONE CROSS-SECTION TEST BY: INDICATES #f_ THE BSC GROUP, INC. �_ ESTIMATED WF '41 �� / WITNESSED BY: SEASONAL HIGH / It '/ ' f - f // � \ ' , , T3P� GROUND \ DESIGN CRITERIA: PHIL RENAULD HIGH GROUNDWATER COMPUTATION INDICATES �T3(' \ PERC. RATE: BASED ON TP#2 Ji, � OBSERVED DESIGN FLOW: ASSUME 2 MIN./INCH DEPTH TO DAMP SOIL 12.3 GROUND WATER / // �� - - j O ✓ \ \ ' SOIL EVALUATOR INDEX WELL Miw-zs 6920 S.F. @ 75 GALLONS / 1000 S.F. // / - - / WF 6 \ MARK DIBB WATER LEVEL RANGE ZONE C INDICATES o T2P1 -1106V�/ // / - - / N78 4 ` \ \ \ \ 1 \ = 520 G.P.D. CURRENT DEPTHOINDEX WELL(4/07) 7.0 PERC. SOIL CLASS: WATER LEVEL ADJUSTMENT 1.7 TEST �A \ / / / / _ \ \ ,' /T2P2 2 � ( \ \ 5 BEDROOMS @ 110 GPD PER BEDROOM 1 DEPTH TO ADJUSTED HIGH WATER 10.6 VHF INDICATES 550 G.P.D. L.T.A.R. ® UNSUITABLE tlt, / / / \ \ 0.74 G.P.D./SQ.FT. MATERIAL ' -' , \ \ \ TOTAL DAILY FLOW = 1,070 GPD 7r U 1 1 WF#5 +I , REQUIRED SEPTIC TANK: DATUM: �' WF#3 / ' 'f' I i ,I `°� 1,070 X 300% = 3,210 GAL. VERTICAL DATUM: N.G.V.D. 1929 tII // // // // / / S / �\ �i,, N I I , \ F SEPTIC TANK PROVIDED: = 3.500 GAL. BENCH MARK USED: RM- fli /// // // // / / \ I ' 1 ` \ \ WF#58 BENCH MARK SET: TOP OF CONCRETE BOUND = 23.12 \ /�/ // // // / / + I / �� 1 , \ \ 8.39'40"C -� SIZE OF LEACHING FACILITY REQUIRED: I�DRAINAGE \ ` t \ \N7�g1, CONCRETE DESIGN PER <2 / / / AREA 1 , \ \ \ 201 BOUND \ C. RATE: MIN./ INCH 1 \ WF / / // / / / I I FOUND LONG TERM APPL. RATE 0,74 G.P.D/S.F. PROFILE: NOT TO SCALE y� 1,070 GPD = 0,74 GPD/SF = 1,446 S.F. WF1�5 El.= A I t11 / / / / / / / / # TOP FOUNDATION FIRST PIPE LENGTH ! CONCRETE COVERS TO WITHIN TO BE SET LEVEL EL.= 22.0 6' OF FINISHED GRADE. WF#37 ,� j // / / / // / / \ 11 `I I ; I tl�J WF#6b SIZE OF LEACHING FACILITY PROVIDED: 4' PVC SCH 40 �/ 1 USE ONE 50'x32' 5 OUTLET DIST. BOX SEPTIC TANK INVERT ELEVATIONS: TOP OF FOUNDATION 22.50 4" INVERT AT BUILDING 20.50 4" INVERT AT SEPTIC TANK (IN) 20.00 4" INVERT AT SEPTIC TANK (OUT) 19.75 4" INVERT AT DIST. BOX (IN) 19.50 4" INVERT AT DIST. BOX (OUT) 19.33 40 OR EQUAL. INVERTS AT LEACHING FACILITY: LOCATED WITHIN 150 FT. OF THE 4" INVERT AT BEGINNING ANY KNOWN WELLS PROPOSED WITHIN OF LEACHING FIELD 19.00 4" INVERT AT END IMPERVIOUS MATERIAL- ATERIAL6. OF LEACHING FIELD 18.80 ELEVATION AT BOTTOM MIXTURES AND LAYERS OF DIFFERENT CLASSES OF LEACHING FIELD 17.80 ADJUSTED SIEVE, SHALL BE PERFORMED ON A GROUNDWATER 11.20 OBSERVED GROUNDWATER 9.50 VARIANCES REQUESTED: SEE ATTACHED ARCHITECTURAL PLANS -LEACHING FIELD- - - H VERFRONT - -� \ ,, t, •� j // / / j / ` I I I I I 1 LEACHING FIELD I=Gw // �/ F# 61 •fig / / / / _ / _ i I I I I BOTTOM = 50' X 32' = 1600 6.6 SEPARATION �� tij / ' \�/ / / / / / / `O _ J I EST. HIGH GROUNDWATER �� /' // /� / / / / \ J ( O I� I,LfLc 1,600 S,F x 0,74 GPD/SF = 1,184GPD WF#3 GRAVEL _ I- I I I I I WF#62 PARKING ARE 1 �d i LOCUS INFORMATION PROPOSED _ I Q0 1 DRAI GE d i , I , CURRENT OWNER: CODE REALTY, LLC AQ\ ' I \ \ t ` I -AL TITLE REFERENCE: DEED BOOK 20644, PAGE 94 UP 1 \ \ , ` 1 B // /�/ / // ��/ 1 P#1 /_ J � \ \ \ ` 1 , \ � PLAN REFERENCE: PLAN BOOK 459, PAGE 28 C / / / j/ / 1 �f� (Q� o \ , \ , , WF#63 PLAN BOOK 381, PAGE 99 D ASSESSORS MAP: 36 E y W PARCEL' 104, 105, 106 O `` 1 \ \ t t F#68 ZONING DISTRICT- FRONT 30' SIDE 25' / 1 WF#6 REAR 20' \ y O \ WF#67 MINIMUM LOT SIZE: 20,000 S.F. / \\ \ \ G 25.4 X \ \ \ 9 1 1 \ \ \\ \\ \ �\ \ 66 3 EXISTING LOT AREA: 209,514± S.F. (4.8± AC.) / 1 \ \ \\ \ \ \ p \ OVERLAY DISTRICT: APD OR NITROGEN SENSITIVE -01 \ 1 +T p\\ \ \ \ \ N ZONE: YES - ZONE II 0FEMA FLOOD ZONE DISTRICT: ZONE "B & C" 7/2/1992 28 K /p \ \\ \ \\ PANEL #250015 0005 D c>;c / / .1 m � s. � J 1 ➢ \ i , 9��\ � ` \ \ \ \\\ , X . /o /J Z o 19 \ \� , LOCUS PLAN: NO SCALE LP LnX / ym 26.7 I / ! I \ \_' ¢ _ r� ( „WILD ANIMAL r / TP#4_ ' _ _ ate° y` LAGOON # PARKING AREA o ` o 1 U, o N O No. 4W7 / MINIATURE x 27. / / �_ TOP Of - 18 `� '1 ¢ } HOLE 0CONCRETE ` \ �\ \ ' ` 0 3a �. \ \ \1 \ 1 z z L❑GLIB V) GOLF COURSE BOUND (INTERIOR LP 27. X F�CE� EL=23.12 \\\ \\\� _i D: -� _ FENCE \ �\ _ 28 � NOT SURVEYED) ,�� CB \ •L -• S�I�ZcO - OF AVEF.Ir_------- PLAN VIEW / / � � - 'EOG -' ,-- � �. S86.17'00'W � - � � S'(• MAIN ST, £ � / CONCRETE' z 242.84 CONCRETE / BOUND' �`P v < JSCALE: 1' = 20 FEET o \ l / / / PAD / / / FOUND moo: <v 0 10 20 40 FT. /23� Q �7777777 \ / / �\ REVISIONS NO. DATE DESCRIPTION GENERAL NOTES: 1. THIS PLAN IS FOR DESIGN AND CONSTRUCTION OF THE SEWAGE DISPOSAL FACILITY ONLY. 2. ALL CONSTRUCTION METHODS AND MATERIALS SHALL CONFORM TO MASS. D.E.P TITLE 5 AND LOCAL BOARD OF HEALTH REGULATIONS. 3. ALL PIPES LOCATED UNDER PAVEMENT OR TRAVELED WAY SHALL BE SCHEDULE 40 OR EQUAL. 4. THERE ARE NO KNOWN PRIVATE WELLS LOCATED WITHIN 150 FT. OF THE PROPOSED LEACHING FACILITY NOR ANY KNOWN WELLS PROPOSED WITHIN 150' OF ANY KNOWN LEACHING FACILITY. 5. WITHIN LIMIT OF EXCAVATION REMOVE ALL TOPSOIL, SUBSOIL AND OTHER IMPERVIOUS MATERIAL- ATERIAL6. 6.REPLACE ALL EXCAVATED MATERIAL WITH CLEAN GRANULAR SAND, FREE FROM ORGANIC MATERIAL AND DELETERIOUS SUBSTANCES. MIXTURES AND LAYERS OF DIFFERENT CLASSES OF SOIL SHALL NOT BE USED. THE FILL SHALL NOT CONTAIN ANY MATERIAL LARGER THAN TWO INCHES. A SIEVE ANALYSIS, USING A #4 SIEVE, SHALL BE PERFORMED ON A REPRESENTATIVE SAMPLE OF FILL UP TO 45% BY WEIGHT OF THE FILL SAMPLE MAY BE RETAINED ON THE #4 SIEVE. SIEVE ANALYSES ALSO SHALL BE PERFORMED ON THE FRACTION OF FILL SAMPLE PASSING THE #4 SIEVE, SUCH ANALYSES MUST DEMONSTRATE THAT THE MATERIAL MEETS EACH OF THE FOLLOWING SPECIFICATIONS: 100% MUST PASS #4 SIEVE (4.75 mm EFFECTIVE PARTICLE SIZE) 10%-100% MUST PASS #50 SIEVE (0.30 mm EFFECTIVE PARTICLE SIZE) 09-20% MUST PASS #100 SIEVE (0.15 mm EFFECTIVE PARTICLE SIZE) 0%-5% MUST PASS #200 SIEVE (0.075 mm EFFECTIVE PARTICLE SIZE) 7. EXISTING UTILITIES WHERE SHOWN IN THE DRAWINGS ARE APPROXIMATE. THE CONTRACTOR SHALL BE RESPON- SIBLE FOR PROPERLY LOCATING AND COORDINATING THE PROPOSED CON- STRUCTION ACTIVITY WITH DIG -SAFE AND THE APPLICABLE UTILITY COMPANY AND MAINTAINING THE EXISTING UTILITY SYSTEM IN SERVICE. DIG -SAFE SHALL BE NOTIFIED PER THE STATE OF MASSACHUSETTS STATUTE CHAPTER 82, SECTION 409 AT TEL, 1-888-344-7233. THE ENGINEER DOES NOT GUARANTEE THEIR ACCURACY OR THAT ALL UTILITIES AND SUBSURFACE STRUCTURES ARE SHOWN. LOCATIONS AND ELEVATIONS OF UNDERGROUND UTILITIES TAKEN FROM RECORD PLANS. THE CONTRACTOR SHALL VERIFY SIZE, LOCATION AND INVERTS OF UTILITIES AND STRUCTURES AS REQUIRED PRIOR TO THE START OF CONSTRUCTION. B. THIS SYSTEM IS NOT DESIGNED FOR THE USE OF A GARBAGE GRINDER. A GARBAGE GRINDER IS NOT RECOMMENDED DUE TO RECOGNIZED ADVERSE IMPACTS TO THE LEACHING FACILITY. 9. EXITING INVERTS ARE TO BE CHECKED BY THE CONTRACTOR PRIOR TO CONSTRUCTION. CONFIRM LOCATION & NUMBER OF INVERTS. 0. THE ENGINEER IS TO BE NOTIFIED OF ANY FIELD CHANGES THAT MAY BE REQUIRED. BS URDUP 349 Main Street, (RT. 28) Unit D W. Yarmouth Massachusetts 02673 508 778 8919 PROJECT TITLE: DESIGN FOR SEWAGE DISPOSAL SYSTEM "SYSTEM 4" #68 ROUTE 28 WEST YARMOUTH MASSACHUSETTS PREPARED FOR: CODE REALTY, LLC 52 SHIPS EAGLE LANE OSTERVILLE MA 02655 DATE: MAY 11, 2007 COMP. DESIGN: K. HEALY CHECK: M. DIBB DRAWN: P. HAGIST FIELD: D. GAZZOLO / J. McCARTIN FILE NO. 9178SITE.DWG DWG NO. 5766-05 SHEET 1 OF 1 JOB NO. 4-9178.00