HomeMy WebLinkAbout110 River Street, SE83-2150 OOCMassachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands
WPA Form 5 — Order of Conditions
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
Town of Yarmouth Wetland By-law, Chapter 143
A. General Information
Please note:
Yarmouth
this form has
been modified
1. From:
Conservation Commissior
with added
2. This issuance is for
space to
accommodate
(check one):
the Registry
of Deeds
3. To: Applicant:
Requirements
Important: ---------
When filling _
out forms on c. Organization
Provided by MassDEP:
eDEP Transaction #
Yarmouth
City/Town
a. ®Order of Conditions b. ❑ Amended Order of Conditions
the
109 River Street
computer,
use only the
d. Mailing Address
tab key to
South Yarmouth
move your
e. City/Town
cursor - do
not use the
4. Property Owner (if different from applicant):
return
nkey.
a. First Name
rafm
c. Organization
d. Mailing Address
e. City/Town
5. Project Location:
110 River Street
a. Street Address
43
c. Assessors Map/Plat Number
Latitude and Longitude, if known:
McCarthy
b. Last Name
MA
f. State
b. Last Name
f. State
South Yarmouth
b. City/Town
45
d. Parcel/Lot Number
41 d39m 13.8594s
d. Latitude
g. Zip Code
70d11 m48.9474s
e. Longitude
wpaform5 doc • rev. 11 12/2014 Page 1 of 12
Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands
i
WPA Form 5 — Order of Conditions
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
Town of Yarmouth Wetland By-law, Chapter 143
A. General Information (cont.)
Provided by MassDEP:
SE83-2150
MassDEP File #
eDEP Transaction #
Yarmouth
City/Town
6. Property recorded at the Registry of Deeds for (attach additional information if more than
one parcel):
Barnstable 194801
a. County f b. Certificate Number (if registered land)
c. Book d. Page
2/14/18 3/1 /18 3/6/18
7. Dates: a. Date Notice of Intent Filed b. Date Public Hearing Closed c. Date of Issuance
s. Final Approved Plans and Other Documents (attach additional plan or document references
as needed):
Sketch Plan Showing Proposed Bulkhead Reconstruction
a. Plan Title
Shorefront Consulting
b. Prepared By c. Signed and Stamped by
12/14/17 1 "=20' (Site Plan)
d. Final Revision Date e. Scale
Plan showing 8Engineered vinyl Bulkhead, Mark McKenzie, P.E.
f. Additional Plan or Document Title
B. Findings
1. Findings pursuant to the Massachusetts Wetlands Protection Act:
12/12/12
g. Date
Following the review of the above -referenced Notice of Intent and based on the information
provided in this application and presented at the public hearing, this Commission finds that
the areas in which work is proposed is significant to the following interests of the Wetlands
Protection Act (the Act). Check all that apply:
a. ® Public Water Supply b. ❑ Land Containing Shellfish c. ® Prevention of
Pollution
d. ® Private Water Supply e. ❑ Fisheries f. ® Protection of
Wildlife Habitat
g. ® Groundwater Supply h. ® Storm Damage Prevention i. ® Flood Control
2. This Commission hereby finds the project, as proposed, is: (check one of the following boxes)
Approved subject to:
a. ® the following conditions which are necessary in accordance with the performance
standards set forth in the wetlands regulations. This Commission orders that all work shall
be performed in accordance with the Notice of Intent referenced above, the following
General Conditions, and any other special conditions attached to this Order. To the extent
that the following conditions modify or differ from the plans, specifications, or other
proposals submitted with the Notice of Intent, these conditions shall control.
wpaform5.doc • rev. 11/12/2014 Page 2 of 12
Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands
WPA Form 5 — Order of Conditions
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 eDEP Transaction #
Town of Yarmouth Wetland By-law, Chapter 143 Yarmouth
City/Town
B. Findings (cont.)
Denied because:
Provided by MassDEP:
SE83-2150
MassDEP File #
b. ❑ the proposed work cannot be conditioned to meet the performance standards set forth
in the wetland regulations. Therefore, work on this project may not go forward unless and
until a new Notice of Intent is submitted which provides measures which are adequate to
protect the interests of the Act, and a final Order of Conditions is issued. A description of
the performance standards which the proposed work cannot meet is attached to this
Order.
c. ❑ the information submitted by the applicant is not sufficient to describe the site, the work,
or the effect of the work on the interests identified in the Wetlands Protection Act.
Therefore, work on this project may not go forward unless and until a revised Notice of
Intent is submitted which provides sufficient information and includes measures which are
adequate to protect the Act's interests, and a final Order of Conditions is issued. A
description of the specific information which is lacking and why it is necessary is
attached to this Order as per 310 CMR 10.05(6)(c).
3. ❑ Buffer Zone Impacts: Shortest distance between limit of project
disturbance and the wetland resource area specified in 310 CMR 10.02(1)(a) a. linear feet
Inland Resource Area Impacts: Check all that apply below. (For Approvals Only)
Resource Area Proposed Permitted Proposed Permitted
Alteration Alteration Replacement Replacement
4. ❑ Bank
a. linear feet
b. linear feet
c. linear feet
d. linear feet
5. ❑ Bordering
Vegetated Wetland
a. square feet
_
b. square feet
c. square feet
d. square feet
s. ❑ Land Under
Waterbodies and
a. square feet
b. square feet
c. square feet
d. square feet
Waterways
e. c/y dredged
f. c/y dredged
7. ❑ Bordering Land
Subject to Flooding
a. square feet
b. square feet
c. square feet
d. square feet
Cubic Feet Flood Storage
e. cubic feet
f. cubic feet
g. cubic feet
h. cubic feet
8. ❑ Isolated Land
Subject to Flooding
a. square feet
b. square feet
Cubic Feet Flood Storage
c. cubic feet
d. cubic feet
e. cubic feet
f. cubic feet
s. ❑ Riverfront Area
a. total sq. feet
b. total sq. feet
Sq ft within 100 ft
c. square feet
d. square feet
e. square feet
f. square feet
Sq ft between 100-
200 ft
g. square feet
h. square feet
i. square feet
j. square feet
wpaform5.doc • rev. 11/12/2014 Page 3 of 12
Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands
WPA Form 5 — Order of Conditions
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
Town of Yarmouth Wetland By-law, Chapter 143
B. Findings (cont.)
Provided by MassDEP:
eDEP Transaction #
Yarmouth
city/Town
Coastal Resource Area Impacts: Check all that apply below. (For Approvals Only)
Proposed Permitted Proposed Permitted
Alteration Alteration Replacement Replacement
10. ❑ Designated Port Indicate size under Land Under the Ocean, below
Areas
11. ❑ Land Under the
Ocean
12.
❑
Barrier Beaches
13.
❑
Coastal Beaches
14.
❑
Coastal Dunes
15.
®
Coastal Banks
16.
❑
Rocky Intertidal
Shores
17.
❑
Salt Marshes
18.
❑
Land Under Salt
Ponds
19. ❑ Land Containing
Shellfish
20. ❑ Fish Runs
21. ® Land Subject to
Coastal Storm
Flowage
a. square feet b. square feet
Indicate size under Coastal Beaches and/or Coastal Dunes
below
cu yd
cu yd
a. square feet
b. square feet
c. nourishment
d. nourishment
cu yd
cu yd
a. square feet
b. square feet
c. nourishment
d. nourishment
126
126
a. linear feet
b. linear feet
a. square feet
b. square feet
a. square feet
b. square feet
c. square feet
d. square feet
c. c/y dredged d. c/y dredged
a. square feet b. square feet c. square feet d. square feet
Indicate size under Coastal Banks, Inland Bank, Land Under
the Ocean, and/or inland Land Under Waterbodies and
Waterways, above
a. c/y dredged b. c/y dredged
1260 1260
a. square feet b. square feet
wpaform5.doc • rev. 11/12/2014 Page 4 of 12
LlMassachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands
WPA Form 5 — Order of Conditions
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
Town of Yarmouth Wetland By-law, Chapter 143
B. Findings (cont.)
* #22. If the 22 ❑ Restoration/Enhancement *:
project is for
the purpose of
restoring or
enhancing a
a. square feet of BVW
wetland
resource area 23. ❑ Stream Crossing(s):
b. square feet of salt marsh
Provided by MassDEP:
SE83-2150
MassDEP File #
eDEP Transaction #
Yarmouth
City/Town
in addition to
the square
footage that a. number of new stream crossings b. number of replacement stream crossings
has been entered in C. General Conditions Under Massachusetts Wetlands Protection Act
Section B.5.c
aBV c) or The following conditions are only applicable to Approved projects.
Marsh) above, 1. Failure to comply with all conditions stated herein, and with all related statutes and other
please enter regulatory measures
the additional 9 Y ,shall be deemed cause to revoke or modify this Order.
amount here. 2. The Order does not grant any property rights or any exclusive privileges; it does not
authorize any injury to private property or invasion of private rights.
3. This Order does not relieve the permittee or any other person of the necessity of complying
with all other applicable federal, state, or local statutes, ordinances, bylaws, or regulations.
4. The work authorized hereunder shall be completed within three years from the date of this
Order unless either of the following apply:
a. The work is a maintenance dredging project as provided for in the Act; or
b. The time for completion has been extended to a specified date more than three years,
but less than five years, from the date of issuance. If this Order is intended to be valid
for more than three years, the extension date and the special circumstances warranting
the extended time period are set forth as a special condition in this Order.
c. If the work is for a Test Project, this Order of Conditions shall be valid for no more than
one year.
5. This Order may be extended by the issuing authority for one or more periods of up to three
years each upon application to the issuing authority at least 30 days prior to the expiration
date of the Order. An Order of Conditions for a Test Project may be extended for one
additional year only upon written application by the applicant, subject to the provisions of 310
CMR 10.05(11)(f).
6. If this Order constitutes an Amended Order of Conditions, this Amended Order of
Conditions does not extend the issuance date of the original Final Order of Conditions and
the Order will expire on 3/6/21 unless extended in writing by the Department.
7. Any fill used in connection with this project shall be clean fill. Any fill shall contain no trash,
refuse, rubbish, or debris, including but not limited to lumber, bricks, plaster, wire, lath,
paper, cardboard, pipe, tires, ashes, refrigerators, motor vehicles, or parts of any of the
foregoing.
wpaform5.doc • rev. 11/12/2014 Page 5 of 12
Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands
WPA Form 5 — Order of Conditions
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
Town of Yarmouth Wetland By-law, Chapter 143
Provided by MassDEP:
S E83-2150
MassDEP File #
eDEP Transaction #
Yarmouth
City/Town
C. General Conditions Under Massachusetts Wetlands Protection Act
8. This Order is not final until all administrative appeal periods from this Order have elapsed,
or if such an appeal has been taken, until all proceedings before the Department have been
completed.
9. No work shall be undertaken until the Order has become final and then has been recorded
in the Registry of Deeds or the Land Court for the district in which the land is located, within
the chain of title of the affected property. In the case of recorded land, the Final Order shall
also be noted in the Registry's Grantor Index under the name of the owner of the land upon
which the proposed work is to be done. In the case of the registered land, the Final Order
shall also be noted on the Land Court Certificate of Title of the owner of the land upon
which the proposed work is done. The recording information shall be submitted to the
Conservation Commission on the form at the end of this Order, which form must be
stamped by the Registry of Deeds, prior to the commencement of work.
10. A sign shall be displayed at the site not less then two square feet or more than three
square feet in size bearing the words,
"Massachusetts Department of Environmental Protection" [or, "MassDEP"]
"File Number SE83-2150 "
11. Where the Department of Environmental Protection is requested to issue a Superseding
Order, the Conservation Commission shall be a party to all agency proceedings and
hearings before MassDEP.
12. Upon completion of the work described herein, the applicant shall submit a Request for
Certificate of Compliance (WPA Form 8A) to the Conservation Commission.
13. The work shall conform to the plans and special conditions referenced in this order.
14. Any change to the plans identified in Condition #13 above shall require the applicant to
inquire of the Conservation Commission in writing whether the change is significant enough
to require the filing of a new Notice of Intent.
15. The Agent or members of the Conservation Commission and the Department of
Environmental Protection shall have the right to enter and inspect the area subject to this
Order at reasonable hours to evaluate compliance with the conditions stated in this Order,
and may require the submittal of any data deemed necessary by the Conservation
Commission or Department for that evaluation.
16. This Order of Conditions shall apply to any successor in interest or successor in control of
the property subject to this Order and to any contractor or other person performing work
conditioned by this Order.
wpaform5.doc • rev. 11/12/2014 Page 6 of 12
ILlMassachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands
WPA Form 5 —Order of Conditions
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
Town of Yarmouth Wetland By-law, Chapter 143
Provided by MassDEP:
SE83-2150
MassDEP File #
eDEP Transaction #
Yarmouth
City/Town
C. General Conditions Under Massachusetts Wetlands Protection Act (cont.)
17. Prior to the start of work, and if the project involves work adjacent to a Bordering Vegetated
Wetland, the boundary of the wetland in the vicinity of the proposed work area shall be
marked by wooden stakes or flagging. Once in place, the wetland boundary markers shall
be maintained until a Certificate of Compliance has been issued by the Conservation
Commission.
18. All sedimentation barriers shall be maintained in good repair until all disturbed areas have
been fully stabilized with vegetation or other means. At no time shall sediments be
deposited in a wetland or water body. During construction, the applicant or his/her designee
shall inspect the erosion controls on a daily basis and shall remove accumulated sediments
as needed. The applicant shall immediately control any erosion problems that occur at the
site and shall also immediately notify the Conservation Commission, which reserves the
right to require additional erosion and/or damage prevention controls it may deem
necessary. Sedimentation barriers shall serve as the limit of work unless another limit of
work line has been approved by this Order.
19. The work associated with this Order (the "Project')
(1) ❑ is subject to the Massachusetts Stormwater Standards
(2) ® is NOT subject to the Massachusetts Stormwater Standards
If the work is subject to the Stormwater Standards, then the project is subject to the
following conditions:
a) All work, including site preparation, land disturbance, construction and redevelopment,
shall be implemented in accordance with the construction period pollution prevention and
erosion and sedimentation control plan and, if applicable, the Stormwater Pollution
Prevention Plan required by the National Pollution Discharge Elimination System
Construction General Permit as required by Stormwater Condition 8. Construction period
erosion, sedimentation and pollution control measures and best management practices
(BMPs) shall remain in place until the site is fully stabilized.
b) No stormwater runoff may be discharged to the post -construction stormwater BMPs
unless and until a Registered Professional Engineer provides a Certification that:
i. all construction period BMPs have been removed or will be removed by a date certain
specified in the Certification. For any construction period BMPs intended to be converted
to post construction operation for stormwater attenuation, recharge, and/or treatment, the
conversion is allowed by the MassDEP Stormwater Handbook BMP specifications and that
the BMP has been properly cleaned or prepared for post construction operation, including
removal of all construction period sediment trapped in inlet and outlet control structures;
ii. as -built final construction BMP plans are included, signed and stamped by a Registered
Professional Engineer, certifying the site is fully stabilized;
iii. any illicit discharges to the stormwater management system have been removed, as per
the requirements of Stormwater Standard 10;
wpaform5.doc • rev. 11/12/2014 Page 7 of 12
Massachusetts Department of Environmental Protection Provided by MassDEP:
Bureau of Resource Protection - Wetlands SE83-2150
Ll#
WPA Form 5 — Order of Conditions MassDEP File#
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 eDEP Transaction #
Town of Yarmouth Wetland By-law, Chapter 143 Yarmouth
cityrrown
C. General Conditions Under Massachusetts Wetlands Protection Act (cont.)
iv. all post -construction stormwater BMPs are installed in accordance with the plans
(including all planting plans) approved by the issuing authority, and have been inspected to
ensure that they are not damaged and that they are in proper working condition;
v. any vegetation associated with post -construction BMPs is suitably established to
withstand erosion.
c) The landowner is responsible for BMP maintenance until the issuing authority is notified
that another party has legally assumed responsibility for BMP maintenance. Prior to
requesting a Certificate of Compliance, or Partial Certificate of Compliance, the responsible
party (defined in General Condition 18(e)) shall execute and submit to the issuing authority
an Operation and Maintenance Compliance Statement ("O&M Statement) for the
Stormwater BMPs identifying the party responsible for implementing the stormwater BMP
Operation and Maintenance Plan ("O&M Plan") and certifying the following:
i.) the O&M Plan is complete and will be implemented upon receipt of the Certificate of
Compliance, and
ii.) the future responsible parties shall be notified in writing of their ongoing legal
responsibility to operate and maintain the stormwater management BMPs and
implement the Stormwater Pollution Prevention Plan.
d) Post -construction pollution prevention and source control shall be implemented in
accordance with the long-term pollution prevention plan section of the approved
Stormwater Report and, if applicable, the Stormwater Pollution Prevention Plan required by
the National Pollution Discharge Elimination System Multi -Sector General Permit.
e) Unless and until another party accepts responsibility, the landowner, or owner of any
drainage easement, assumes responsibility for maintaining each BMP. To overcome this
presumption, the landowner of the property must submit to the issuing authority a legally
binding agreement of record, acceptable to the issuing authority, evidencing that another
entity has accepted responsibility for maintaining the BMP, and that the proposed
responsible party shall be treated as a permittee for purposes of implementing the
requirements of Conditions 18(f) through 18(k) with respect to that BMP. Any failure of the
proposed responsible party to implement the requirements of Conditions 18(f) through
18(k) with respect to that BMP shall be a violation of the Order of Conditions or Certificate
of Compliance. In the case of stormwater BMPs that are serving more than one lot, the
legally binding agreement shall also identify the lots that will be serviced by the stormwater
BMPs. A plan and easement deed that grants the responsible party access to perform the
required operation and maintenance must be submitted along with the legally binding
agreement.
f) The responsible party shall operate and maintain all stormwater BMPs in accordance
with the design plans, the O&M Plan, and the requirements of the Massachusetts
Stormwater Handbook.
wpaform5.doc • rev. 11/12/2014 Page 8 of 12
Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands
WPA Form 5 — Order of Conditions
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
Town of Yarmouth Wetland By-law, Chapter 143
Provided by MassDEP:
SE83-2150
MassDEP File #
eDEP Transaction #
Yarmouth
City/Town
C. General Conditions Under Massachusetts Wetlands Protection Act (cont.)
g) The responsible party shall:
1. Maintain an operation and maintenance log for the last three (3) consecutive
calendar years of inspections, repairs, maintenance and/or replacement of the
stormwater management system or any part thereof, and disposal (for disposal the
log shall indicate the type of material and the disposal location);
2. Make the maintenance log available to MassDEP and the Conservation
Commission ("Commission") upon request; and
3. Allow members and agents of the MassDEP and the Commission to enter and
inspect the site to evaluate and ensure that the responsible party is in compliance
with the requirements for each BMP established in the O&M Plan approved by the
issuing authority.
h) All sediment or other contaminants removed from stormwater BMPs shall be disposed
of in accordance with all applicable federal, state, and local laws and regulations.
i) Illicit discharges to the stormwater management system as defined in 310 CMR 10.04
are prohibited.
j) The stormwater management system approved in the Order of Conditions shall not be
changed without the prior written approval of the issuing authority.
k) Areas designated as qualifying pervious areas for the purpose of the Low Impact Site
Design Credit (as defined in the MassDEP Stormwater Handbook, Volume 3, Chapter 1,
Low Impact Development Site Design Credits) shall not be altered without the prior written
approval of the issuing authority.
1) Access for maintenance, repair, and/or replacement of BMPs shall not be withheld.
Any fencing constructed around stormwater BMPs shall include access gates and shall be
at least six inches above grade to allow for wildlife passage.
Special Conditions (if you need more space for additional conditions, please attach a text
document):
20. For Test Projects subject to 310 CMR 10.05(11), the applicant shall also implement the
monitoring plan and the restoration plan submitted with the Notice of Intent. If the
conservation commission or Department determines that the Test Project threatens the
public health, safety or the environment, the applicant shall implement the removal plan
submitted with the Notice of Intent or modify the project as directed by the conservation
commission or the Department.
wpaform5.doc • rev. 11/12/2014 Page 9 of 12
LlMassachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands
WPA Form 5 — Order of Conditions
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
Town of Yarmouth Wetland By-law, Chapter 143
Provided by MassDEP:
SE83-2150
MassDEP File #
eDEP Transaction #
Yarmouth
City/Town
D. Findings Under Municipal Wetlands Bylaw or Ordinance
1. Is a municipal wetlands bylaw or ordinance applicable? ® Yes ❑ No
2. The Yarmouth hereby finds (check one that applies):
Conservation Commission
a. ❑ that the proposed work cannot be conditioned to meet the standards set forth in a
municipal ordinance or bylaw, specifically:
1. Municipal Ordinance or Bylaw 2. Citation
Therefore, work on this project may not go forward unless and until a revised Notice of
Intent is submitted which provides measures which are adequate to meet these
standards, and a final Order of Conditions is issued.
b. ® that the following additional conditions are necessary to comply with a municipal
ordinance or bylaw:
Yarmouth Wetland By -Law, Chapter 143
1. Municipal Ordinance or Bylaw 2. Citation
3. The Commission orders that all work shall be performed in accordance with the following
conditions and with the Notice of Intent referenced above. To the extent that the following
conditions modify or differ from the plans, specifications, or other proposals submitted with
the Notice of Intent, the conditions shall control.
The special conditions relating to municipal ordinance or bylaw are as follows (if you need
more space for additional conditions, attach a text document):
See attached text pa e fs10A and 10B of 12
wpaform5.doc • rev. 11/12/2014 Page 10 of 12
WPA FORM 5-ORDER OF CONDITIONS
SPECIAL CONDITIONS -PAGE 10A OF 12
SE83-2150, David McCarthy
110 River Street, Yarmouth, MA
1. The applicant/owner shall be responsible for having a copy of the "Order of Conditions" on the job site at all
times and shall be responsible for insuring that all persons performing the permitted activity are fully aware of its
terms and conditions. Failure to do so may result in the revocation of these "Orders", a fine or both.
2. The Conservation Commission, its agent(s) or assigned(s) shall have the express right of entry upon the job
site at all reasonable times for the purposes of establishing compliance with the "Order of Conditions", "By -Laws"
and 'Regulations". Commission members and the Conservation Administrator may acquire any information,
measurements, photographs, observations and/or materials or may require the submittal of any data/information
deemed necessary by this Commission for that evaluation.
3. A preconstruction review shall be arranged by the contractor with the Conservation Administrator and shall
occur prior to the commencement of any work.
4. Any change in the approved plan(s) shall require the Applicant to file, in writing, a notice of project change with
this Commission. The Commission will determine the significance of the change and determine whether
administrative approval or an "Amended Order of Conditions" is required. Should the project be changed without
permission, or found by the Yarmouth Conservation Commission to be altered in any way from the approved
plan(s), all work will immediately cease until the project is reapproved by the Commission.
5. The "Order of Conditions" is valid for three years from the date of issuance unless otherwise specifically noted
in the "Orders". Extension Permit requests must be applied for at least 30 calendar days prior to the expiration
date of the original Orders". Failure to do so will result in a new "Notice of Intent' filing.
6. Noncompliance with these conditions shall constitute grounds for an Enforcement Order and possible fines.
Fines shall not exceed $300.00 per day/per violation.
7. All imported fill shall be clean and not contain any foreign debris such as cement, bituminous concrete, rubber,
metal, trash, boulders, etc. Boulders will be allowed in specific instances if part of the project design.
8. Debris, including litter, shall be picked up immediately. Any excess material that is excavated from the job site
shall be disposed of at a location approved by the Conservation Administrator or in a covered dumpster. No
debris shall be allowed in a Wetland or Waterway.
9. Washing of equipment/tools shall be done OFF -SITE or handled in a manner appropriate by the Conservation
Administrator.
10. No equipment shall be refueled, nor shall fuel be stored within 100 feet of a resource area
11. Grading shall be accomplished so that runoff shall not be directed to the property of others. The project shall
not increase runoff, nor cause flooding or storm damage to abutters other property owners or wetland Resource
Areas.
12. Any area that is disturbed during construction shall be revegetated immediately or as soon after as the
growing season commences, with appropriate native plantings. Permanent stabilization shall be carried out in
order to minimize erosion.
WPA FORM 5-ORDER OF CONDITIONS
SPECIAL CONDITIONS -PAGE 10B OF 12
SE83-2150, David McCarthy
110 River Street, Yarmouth, MA
13. There shall be no dredging in connection with this project.
14. No pipes, drains, or outlets of any kind shall be placed in or through the bulkhead
15. The project shall consist of using only non -leaching types of treated lumber. CCA or creosote lumber is
prohibited.
16. During the non -boating season any pier components including but not limited to floats and ramps, dinghies,
kayaks etc... shall be stored above the mean high water lines. There shall be no items stored upon salt marsh
areas under any circumstances.
17. The vegetative buffer shall be restored behind the bulkhead as described on on the approved plan. This is an
on -going condition, in -perpetuity, that does not expire with the issuance of a Certificate of Compliance.
18. Landscape Debris, including leaves, grass clippings, brush, or other shall not be allowed within the wetland
resource area. This is an on -going condition that does not expire with the issuance of a Certificate of Compliance
19. A stamped "As Built Plan" shall be certified by the Design Engineer (Massachusetts registered Professional
Engineer or land Surveyor) and will certify that this project has been completed in accordance with the "Order of
Conditions" before a Certificate of Compliance will be issued. The as -built plan shall indicate the structure
location, gradients, distances to the resource areas, and other pertinent information described in the application
and approved plans. Any deviation from the approved plan shall be identified.
20. Upon completion of the project, a 'Request for a "Certificate of Compliance" shall be submitted by the
applicant to the Conservation Commission for review. The "Order of Conditions" shall be considered incomplete
until the "Certificate of Compliance" is issued by the Conservation Commission and recorded at the Registry of
Deeds.
Additional conditions:
21. Adequate returns shall be provided at each end of the bulkhead.
22. Appropriate erosion control measures should be employed to minimize runoff from the property in the
resource area during construction.
23. Gutters and downspouts directed into adequately sized drywells shall be provided for roof drainage. The
Commission may also allow "drip trenches" instead of gutter systems. At no time shall roof run off be directed to a
wetland resource area or abutting properties.
Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands
WPA Form 5 — Order of Conditions
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
Town of Yarmouth Wetland By-law, Chapter 143
E. Signatures
This Order is valid for three years, unless otherwise specified as a special
condition pursuant to General Conditions #4, from the date of issuance.
Please indicate the number of members who will sign this form.
This Order must be signed by a majority of the Conservation Commission.
Provided by MassDEP:
SE83-21$O
MassDEP File #
eDEP Transaction #
Yarmouth
City/Town
3/64019
1. Date of Issuance
`/
2. Number of Signers
The Order must be mailed by certified mail (return receipt requested) or hand delivered to the applicant. A
❑ by hand delivery on
Date
F. Appeals
❑ by certified mail, return receipt
requested, on
Date
The applicant, the owner, any person aggrieved by this Order, any owner of land abutting the
land subject to this Order, or any ten residents of the city or town in which such land is located,
are hereby notified of their right to request the appropriate MassDEP Regional Office to issue a
Superseding Order of Conditions. The request must be made by certified mail or hand delivery
to the Department, with the appropriate filing fee and a completed Request for Departmental
Action Fee Transmittal Form, as provided in 310 CMR 10.03(7) within ten business days from
the date of issuance of this Order. A copy of the request shall at the same time be sent by
certified mail or hand delivery to the Conservation Commission and to the applicant, if he/she is
not the appellant.
Any appellants seeking to appeal the Department's Superseding Order associated with this
appeal will be required to demonstrate prior participation in the review of this project. Previous
participation in the permit proceeding means the submission of written information to the
Conservation Commission prior to the close of the public hearing, requesting a Superseding
Order, or providing written information to the Department prior to issuance of a Superseding
Order.
The request shall state clearly and concisely the objections to the Order which is being
appealed and how the Order does not contribute to the protection of the interests identified in
the Massachusetts Wetlands Protection Act (M.G.L. c. 131, § 40), and is inconsistent with the
wetlands regulations (310 CMR 10.00). To the extent that the Order is based on a municipal
ordinance or bylaw, and not on the Massachusetts Wetlands Protection Act or regulations, the
Department has no appellate jurisdiction.
wpaform5.doc • rev 11.12/2014 Page 11 of 12
Massachusetts Department of Environmental Protection Provided by MassDEP:
Bureau of Resource Protection - Wetlands SE83-2150
WPA Form 5 — Order of Conditions MassDEP File#
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 eDEP Transaction #
Town of Yarmouth Wetland By-law, Chapter 143 Yarmouth
Cityrrown
G. Recording Information
Prior to commencement of work, this Order of Conditions must be recorded in the Registry of
Deeds or the Land Court for the district in which the land is located, within the chain of title of
the affected property. In the case of recorded land, the Final Order shall also be noted in the
Registry's Grantor Index under the name of the owner of the land subject to the Order. In the
case of registered land, this Order shall also be noted on the Land Court Certificate of Title of
the owner of the land subject to the Order of Conditions. The recording information on this page
shall be submitted to the Conservation Commission listed below.
Yarmouth
Conservation Commission
Detach on dotted line, have stamped by the Registry of Deeds and submit to the Conservation
Commission.
--------------------------------------------------------------------------------------------------------------
To:
Yarmouth
Conservation Commission
Please be advised that the Order of Conditions for the Project at:
110 River Street
Project Location
Has been recorded at the Registry of Deeds of:
SE83-2150
MassDEP File Number
Barnstable _
County Book
for: Property Owner
and has been noted in the chain of title of the affected property in:
Book
Page
In accordance with the Order of Conditions issued on:
Date
If recorded land, the instrument number identifying this transaction is:
Instrument Number
If registered land, the document number identifying this transaction is:
Document Number
Signature of Applicant
Page
wpaform5.doc • rev. 1111212014 Page 12 of 12
L1Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands DEP File Number:
1 Request for Departmental Action Fee
Transmittal Form Provided by DEP
Massachusetts Wetlands Protection Act M_ .G.L. c. 131, §40
A. Request Information
Important:
When filling
out forms on
the computer,
use only the
tab key to
move your
cursor - do
not use the
return key.
- I�
1. Location of Project
a. Street Address
b. Cityrrown, Zip
c. Check number d. Fee amount
2. Person or party making request (if appropriate, name the citizen group's representative):
Name
Mailing Address
City/Town
Phone Number
State
Fax Number (if applicable)
3. Applicant (as shown on Determination of Applicability (Form 2), Order of Resource Area Delineation
(Form 46), Order of Conditions (Form 5), Restoration Order of Conditions (Form 5A), or Notice of
Non -Significance (Form 6)):
Name
Mailing Address
City/Town
Phone Number
4. DEP File Number:
B. Instructions
State
Fax Number (if applicable)
1. When the Departmental action request is for (check one):
❑ Superseding Order of Conditions — Fee: $120.00 (single family house projects) or $245 (all other
projects)
❑ Superseding Determination of Applicability — Fee: $120
❑ Superseding Order of Resource Area Delineation — Fee: $120
wpaform5.doc • rev. 11 12/2014 Page 13 of 1
ILIMassachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands
Request for Departmental Action Fee
Transmittal Form
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
B. Instructions (cont.)
DEP File Number:
Provided by DEP
Send this form and check or money order, payable to the Commonwealth of Massachusetts, to:
Department of Environmental Protection
Box 4062
Boston, MA 02211
2. On a separate sheet attached to this form, state clearly and concisely the objections to the
Determination or Order which is being appealed. To the extent that the Determination or Order is
based on a municipal bylaw, and not on the Massachusetts Wetlands Protection Act or regulations,
the Department has no appellate jurisdiction.
3. Send a copy of this form and a copy of the check or money order with the Request for a
Superseding Determination or Order by certified mail or hand delivery to the appropriate DEP
Regional Office (see http://www.mass.qov/eea/agencies/massdep/about/contacts/).
4. A copy of the request shall at the same time be sent by certified mail or hand delivery to the
Conservation Commission and to the applicant, if he/she is not the appellant.
wpaform5.doc • rev. 11/1212014 Page 14 of 12