HomeMy WebLinkAbout2019-03-27 Letter to Con Com.pdfGRADY CONSULTING, L.L.C.
Civil Engineers . Land Surveyors • Landscape Architects
March 27, 2019
Kelly Grant
Conservation Commission
Town of Yarmouth
1146 Route 28
Yarmouth, MA 02664-4492 EMAIL KGrant gyarmouth.ma.us & MAIL
RE: 2 Channel Point Drive, Yarmouth — SE83-2029
Applicant: Jacob Simmons CIO Channel Point LLC
Dear Kelly & Commission Members;
We are providing this letter in response to our conversation this morning and your March 25,
2019 e-mail where you informed us that the Commission "requested a six-foot buffer zone of
native plantings be added along the bank and suggested the applicant address bank erosion issues
by managing invasive vegetation."
• As we discussed, Mr. Simmons is not interested in constructing the previously approved
garage or septic system at this time so he is amenable to requesting a Certificate of
Compliance and reapplying to the Commission if or when he would like to proceed with
those items.
• He is working with a landscape designer and will submit a planting plan to you upon
completion for your review and approval.
• He would like to complete this planting at the end of summer, ideally beginning of
September and will notify your office prior to the start of planting.
• Per conversation no other site work other than the planting, invasive species management and
erosion control is proposed.
• Per our conversation we will not request a Certificate of Compliance until after the planting
is completed.
If you have any questions please do not hesitate to contact us.
Sincerely,
GRADY CON ULTING, L.L.C.
Richard Grad , P.E.
Principal Engineer
JA2014114-105TON COAConCom.doox
71 Evergreen Street, Suite 1 + Kingston, MA 02364 + Tel (781) 585-2300 . Fax (781) 585-2378