HomeMy WebLinkAboutEngineer Certification Letter •
iT tel.(508)362-4541
.939 main street rt 6a fax(508)362-9880
yarmouth port
mass 02675 down cape engineering
civil engineers& land surveyors
structural design
Arne H.Ojala P.E.,P.LS.
Timothy H.Covell,P.LS.
land court David C.Thulin,P.E.
surveys N 0 V 0 5 1998
November 2, 1998
site planning
Bruce Murphy, R.3. , CHO
sewage system Yarmouth Board of Health
designs 1146 Route 28
So. Yarmouth, Mei 02664
inspections
446• L .: Port
permits
Dear Bruce:
On 10/29/98, Down Cape Engineering, Inc. performed an
inspection of the removal of unsuitable soils at the
above-referenced location as required.
Due to the proximity of the hedge on the easterly property
line, the 5' removal as called for on the plan was not
I performed completely. Since the design of the leach
v facility is based on bottom area only, it is felt that the
•
full 5' removal is not critical to the functioning of the
leach facility.
This is to certify that the soils removal was performed in
substantial compliance with the approved plan.
If you have any questions, please do not hesitate to call
me.
Yours truly,
Arne H. Ojala, PE, PLS
Down Cape Engineering, Inc.
cc: Mary Frances Baker