Here is a list of corrections from yesterday's inspection;
• Firestopping in attic above rooms, 201, 202, 203, 204,207, 208,211, 235, 252, 254, 258, is either not complete
or done incorrectly
• Room 234 light fixture hanging, and hole in ceiling
• Second floor mechanical room firestopping not done,and remove top storage shelves
• First floor sprinkler room has hole in ceiling and missing electrical box cover
• First floor ice machine alcove needs ceiling, and exit sign is too close to sprinkler head in hallway
• Rooms 102, 137 need door closers
• Room 124 carpet lifted
• Rooms 111, 113, 115, 122 sprinkler head covered with plaster
• Basement electrical room has holes in ceiling,firestopping not done correctly,sprinkler head under stairs needs
to be moved out, and label for exterior door
• Mikes office needs sprinkler head trim
• Storage in kitchen &cafe areas needs to be min 18" from ceiling
• Lobby bathroom sprinkler head missing trim
• Panic hardware for doors in assembly area on second floor&closer needed for storage closet, paint on sprinkler
head
• Light covers in offices at main entrance
• Mechanical room second floor over lobby needs door for attic access, sprinkler head trim, and firestopping
• Pool area has sprinkler trim missing in front window& hole in ceiling
• Main basement holes in ceiling in sprinkler&elevator room, dryer vents need to be replaced,firestopping needs
to be done correctly
• Exterior front of building fan exhaust missing cover, back of building has hole around gas pipe
• Street number for building needed
• Final affidavit from architect
The following items need to be addressed by the architect in writing;
1. Correct firestopping systems are being used in the above areas mentioned?
2. Door needed at service area entrance hallway?
3. Railings for café entrance steps needed?
1
4. Insulation for all attic access doors?
The items listed above all need to be repaired and re-inspected before a temp CO will be issued.
Timothy Sears CBO
Building Inspector
Town of Yarmouth
508-398-2231 Ext. 1259
mailto:tsears@yarmouth.ma.us
From:Jigar Patel [mailto:jpatel29@gmail.com]
Sent: Friday,June 28, 2019 7:01 AM
To:Sears,Tim <tsears@yarmouth.ma.us>
Cc: mikenadzeika@outlook.com
Subject: Hilti fire stopping cape point
Attention!T.hiemail5o . s outside of ,or tion. Do not pe ft chm
are sur-e.his ai; s from a ,own nder d you� o� a contents, fe Ca the finer too eri nsi ..
Otherwise.delete thi erg l
On site getting this fixed in the morning ASAP.
Please let's get temp CO today please!!
We are all about life safety as well and I promise I will get all this done. I need to open doors today I'm in pain.
Jigar Patel