HomeMy WebLinkAboutEngineering letter DWD ENGINEERING, INC.
5 MICHAEL ROAD EAST BRIDGEWATER,MA 02333
(508)378-9602
domdean@aol.com
December 27, 2019
Mr. Timothy Sears-Building Inspector
Yarmouth Building Department
1146 Route 28
Yarmouth, MA 02664
RE: Framing Conditions ygf,Mov'h„
191 Diane Avenue-South Falmeeth, MA
Dear Mr. Sears,
On Thursday, December 26, I visited the above referenced site to review the roof framing conditions for the
addition being built. Due to the existing layout, the roof(and supporting posts and beams in the attic) was not able to be
framed as shown on the design sketch that I stamped. The framer reached out to Mid-Cape Lumber to provide an
alternate scheme. Based on the existing conditions I am in agreement with the proposed framing changes and no further
remedial work is required. If you have any questions concerning this letter or if I can be of further assistance, please do
not hesitate to contact me.
Si rely,