RE: SE 83-1663 Certificate of Compliance — Sailing Village Way, South Yarmouth
Map 51 Parcel 81— Sheathing Repair
To the Conservation Commission,
Attached please find Form 8A for the Request for Certificate of Compliance for SE 83-
1663 and a check in the amount of $75.
The project to install vinyl sheathing along the lower segment of the entire bulkhead was
completed. The work was necessary because of the unfortunate poor quality of treated
lumber available in the early 1990's used in the marina rehabilitation. The vinyl sheet
work was completed shortly after the Order was issued. Recent inspections showed it is
in good condition and installed consistently with the plan.
I hereby certify that the project component was installed according to the plan and the
Order of Conditions and the completed project warrants issuance of a Certificate of
Compliance.
Please contact me directly should you have any questions.
Sincerely,
Cape Cod Engineeriq, Inc.
Robert M. Pe
Important:
When filling out
forms on the
computer, use
only the tab
key to move
your cursor -
do not use the
return key.
_ I�
Int
Upon completion
of the work
authorized in
an Order of
Conditions, the
property owner
must request a
Certificate of
Compliance
from the issuing
authority stating
that the work or
portion of the
work has been
satisfactorily
completed.
Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands
DEP File Number:
VVPA Form 8A — Request for Certificate of Compliance SE 83-1663
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 Provided by DEP
Town of Yarmouth Wetland By-law, Chapter 143
A. Project Information
This request is being made by:
Cape Cod Engineering, Inc.
Name
PO Box 1517
Mailing Address
East Dennis
508-385-1445
Phone Number
MA
State
2. This request is in reference to work regulated by a final Order of Conditions issued to:
Ship Shops, Inc.
Applicant
5/04/2004 SE 83-1663
Dated DEP File Number
3. The project site is located at
Sailing Village Way
Street Address
51
Assessors Map/Plat Number
South Yarmouth
City/Town
81
Parcel/Lot Number
4. The final Order of Conditions was recorded at the Registry of Deeds for:
Alyson Taubert
Property Owner (if different)
Barnstable
Certificate (if registered land)
5. This request is for certification that (check one):
02641
Zip Code
18769 176
Book Page
® the work regulated by the above -referenced Order of Conditions has been satisfactorily completed.
❑ the following portions of the work regulated by the above -referenced Order of Conditions have
been satisfactorily completed (use additional paper if necessary).
❑ the above -referenced Order of Conditions has lapsed and is therefore no longer valid, and the
work regulated by it was never started.
wpaform8a.doc -- rev. 5/29/114 Page 1 of 2
Massachusetts Department of Environmental Protection
DEP File Number:
Bureau of Resource Protection - Wetlands
L11
WPA Form 8A — Request for Certificate of Compliance SE 83-1663
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 Provided by DEP
Town of Yarmouth Wetland By-law, Chapter 143
A. Project Information (cont.)
6. Did the Order of Conditions for this project, or the portion of the project subject to this request, contain
an approval of any plans stamped by a registered professional engineer, architect, landscape
architect, or land surveyor?
® Yes If yes, attach a written statement by such a professional certifying substantial
compliance with the plans and describing what deviation, if any, exists from the plans
approved in the Order.
B. Submittal Requirements
Requests for Certificates of Compliance should be directed to the issuing authority that issued the final
Order of Conditions (OOC). If the project received an OOC from the Conservation Commission, submit
this request to that Commission. If the project was issued a Superseding Order of Conditions or was the
subject of an Adjudicatory Hearing Final Decision, submit this request to the appropriate DEP Regional
Office (see htti)://www.mass.gov/eea/agencies/massdep/about/contacts/find-the-massdep-regional-office-
for-your-city_or-town.html).
wpaformSa.doc -- rev. 5/29/14 Page 2 of 2