HomeMy WebLinkAboutTransmittal_-_00784_PE_Site_Report_20210624Transmittal
Boston, Massachusetts 02110
Page 1 of 2
PROJECT:Mattacheese Middle School: FS-
CA
71010.00.0
DATE:6/25/2021
SUBJECT:6-24 PE field report TRANSMITTAL ID:00784
PURPOSE:For your use and distribution VIA:Info Exchange
FROM
NAME COMPANY EMAIL PHONE
Andrew Hazelton
Boston
MASSACHUSETTS
02110
United States
Perkins Eastman a.hazelton@perkinseastman.
com
TO
NAME COMPANY EMAIL PHONE
Ricky Sughrue
404 Wyman Street
Suite 400
Waltham MA 02451
United States
Commodore Builders rsughrue@commodorebuilder
s.com 617.614.3500
REMARKS:Hi Ricky,
Please download PE's report from the site observation visit of yeserday (6-
24). This includes as attachments the GPI daily reports for 6-21 though 6-
24. Please let me know if you have any problems downloading this file, or
any questions.
Best Regards,
Andy
DESCRIPTION OF CONTENTS
QTY DATED TITLE NOTES
1 6/25/2021 DYIMS PE Site report 20210624.pdf
COPIES:
Jeff Martin (Commodore Builders)
Ryan DiRico (Commodore Builders)
PMA DY Project Email (PMA Consultants)
Daniel Colli (Perkins Eastman)
Robert Bell (Perkins Eastman)
Transmittal
DATE:6/25/2021
TRANSMITTAL ID:00784
Page 2 of 2
Russell Higgins (Perkins Eastman)
Ken Anderson (Girard and Company, LLP)
Leah Schroeder (Perkins Eastman)
Jon Pope (PMA Consultants)
Architect: Perkins Eastman DPC
Distribution: Commodore PMA Consultants Sandra Cashen File
ARCHITECT’S SITE OBSERVATION REPORT
DATE OF VISIT: 06/24/2021 PROJECT: Dennis Yarmouth Intermediate
Middle School
286 Station Avenue
South Yarmouth, MA 02664
DATE OF ISSUE: 06/25/2021 PROJECT NO: 71011
WEATHER
CONDITIONS:
Sunny, high 70’s in AM ARCHITECT: Perkins Eastman, DPC
20 Ashburton Street
8th floor
Boston, MA
The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit.
WORK IN PROGRESS:
1) Stripping of overburden at east access road and west access road extension
2) Stockpiling of topsoil
3) Stockpiling of crushed stone for VSCs and for general site work (utility trenches etc)
4) Layout of VSC locations
5) Installation of vibratory stone columns by CNC and vibration monitoring (see also attached field reports from GPI)
6) Excavation for installation of cul-tec chambers
7) General ground improvements
FIELD OBSERVATIONS:
PE visited the site to review ongoing progress with the site work.
1) RBO is getting underway with stripping of overburden at east access road and west access road extension.
2) Installation of VSCs by CNC: [during architect walk-thru, Installation of vibratory stone columns was paused
during walk through due to equipment issues].GPI/Commodore reported that 90 VSCs were installed on
Wednesday and that proof tests indicated +/- ¼” movement which is good (see also attached field reports from
GPI).
3) New subgrade for the new access drive that will run between SAE and the new building area B has been installed
(up to the existing SAE service area)--see photo below.
4) Ryan DiRico reviewed with PE the specific location of existing-to-remain light poles in the area in front of SEA, 6
or 8 of which are going to need to be re-circuited due to the fact that the existing curcuits will be disconnected
associated with light poles that are being removed (how to recircuit this will be an RFI for GGD).
5) Modulus testing will be performed early next week.
6) Excavation for foundations is due to commence at the end of next week per Commodore.
7) PE reviewed and approved new proposed mockup location at future field C adjacent to east access road (NE
zone of field C).
Note: CNC resumed VSC installation in the PM, and installed 68 piers on 6/24. GPI’s attached 6/24 field report
indicates that CNC was encountering refusal at about 10% of the 68 piers installed, and GPI believes that that
either indicates a dense gravel layer that was not identified in GPI’s borings, or a potential problem with the
equipment.
REPORT BY: ABH Page 2 of 3
PROGRESS PHOTOS
GRADING ONGOING - OVERALL CRUSHED STONE STOCKPILING FOR RBO
STRIPPING OF OVERBURDEN – EAST DRIVE STRIPPING OF OVERBURDEN – WEST DRIVE
STORED CULTEC AND MANHOLE STRUCTURES EXCAVATION FOR STORM WATER RETENTION STRUCTURES
REPORT BY: ABH Page 3 of 3
COMPLETED VSCS CNC VSC RIG
STOCKPILING OF STRIPPED TOP SOIL NEW DRIVE SUBGRADE NEAR SAE NW CORNER
EXISTING MANHOLE COVER EXISTING LIGHT POLE BASE NEAR ETR SAE PARKING
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 6/21/21 Caseyville, Il 62232
__________________________________________________________________________________________________
This Report is a summary installation list of installed vibratory stone columns, (VSC), in accordance with Submittal #31
3400-02.0 31 3400 – Aggregate Piers, prepared by CMC Professional Services LLC, 335 E. Geneva Rd #3116, Carol
Stream, Il 60188.
Activity for Monday, June 21st, 2021:
VSC Pier # Installed Depth (ft.) Stone Take (Cu. Yds.) COMMENTS
3114 9.0 0.75 Routine
3118 9.0 0.75 Routine
3115 6.0 0.5 Routine
3095 6.0 0.5 Routine
3045 9.0 0.75 Routine
3046 9.0 0.75 Routine
3047 9.0 0.75 Routine
3116 6.0 0.5 Routine
3096 6.0 0.5 Routine
3048 9.0 0.75 Routine
3117 6.0 0.5 Routine
3097 6.0 0.5 Routine
3049 9.0 0.75 Routine
3050 11.0 1.0 Routine
3051 11.0 1.0 Routine
3052 9.0 0.75 Refusal
3113 9.0 0.75 Routine
3053 9.0 0.75 Routine
3119 6.0 0.5 Routine
3098 6.0 0.5 Routine
3054 9.0 0.75 Routine
3120 6.0 0.5 Routine
3099 6.0 0.5 Routine
3055 9.0 0.75 Routine
3056 14.0 1.0 Routine
3057 14.0 1.0 Routine
3058 14.0 1.0 Routine
3059 14.0 1.0 Routine
Test Pier #1 16.0 1.25 12’ East of Pier 3460
Test Pier #2 16.0 1.25 12’ South of pier 3460
4007 14,0 1.0 Routine
4078 14.0 1.0 Routine
4079 14.0 1.0 Routine
4056 9.0 0.75 Routine
4077 6.0 0.5 Routine
4055 9.0 0.75 Routine
4076 6.0 0.5 Routine
4054 9.0 0.75 Routine
4075 6.0 0.5 Routine
4053 11.0 1.0 Routine
4051 11.0 1.0 Routine
4052 11.0 1.0 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 6/21/21 Caseyville, Il 62232
__________________________________________________________________________________________________
VSC Pier # Installed Depth (ft.) Stone Take (Cu. Yds.) COMMENTS
4050 9.0 0.75 Routine
4074 6.0 0.5 Routine
4049 9.0 0.75 Routine
4048 9.0 0.75 Routine
4073 6.0 0.5 Routine
4046 14.0 1.25 Routine
4047 14.0 1.50 Routine
Total production Piers this day = 47, Total Test Piers = 2
Total production Piers to date = 47
See Photos:
Rig on Location, Area “D” Northeast
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 6/21/21 Caseyville, Il 62232
__________________________________________________________________________________________________
Loading Crushed Stone into Hopper
Hopper loading mandrel chute
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 6/22/21, OVERCAST – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
This Report is a summary installation list of installed vibratory stone columns, (VSC), in accordance with Submittal #31
3400-02.0 31 3400 – Aggregate Piers, prepared by CMC Professional Services LLC, 335 E. Geneva Rd #3116, Carol
Stream, Il 60188.
Glossary of Header Terms:
VSC Pier #: Each pier is identified by number according to location plan included in the above referenced
Submittal.
Installed Depth: The as-built length of pier as constructed from working grade to termination in suitable native,
(bearing) soil.
Stone Take: The amount of Crushed Stone used in constructing a given Pier, (expressed in volume), one cubic
yard weighs approximately 1.2 Ton.
Comments: Note any deviation from standard installation procedures, proposed depths or changes in location of
said Pier.
Activity for Tuesday, June 22nd, 2021:
VSC Pier # Installed Depth (ft.) Stone Take (Cu. Yds.) COMMENTS
4372 9.0 .75 Routine
4373 9.0 .75 Routine
4374 9.0 1.0 Routine
4345 6.0 .75 Routine
4375 9.0 1.0 Routine
4346 6.0 .75 Routine
4376 9.0 1.0 Routine
4377 11.0 1.0 Routine
4378 11.0 1.0 Routine
4379 8.0 1.0 REFUSAL
4347 6.0 .75 Routine
4380 9.0 1.0 Routine
4348 6.0 .70 Routine
4381 9.0 1.0 Routine
4349 6.0 .70 Routine
4382 9.0 1.0 Routine
4350 6.0 .70 Routine
4351 7.3 1.0 Routine
4352 6.0 .70 Routine
4390 9.0 1.0 Routine
4391 9.4 1.0 Routine
4392 9.0 1.0 Routine
4393 9.0 1.0 Routine
4353 6.0 .75 Routine
4354 6.0 .75 Routine
4394 9.0 1.0 Routine
4395 9.0 1.0 Routine
4355 6.0 .75 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 6/22/21, OVERCAST – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
4396 9.0 1.0 Routine
4356 6.0 .75 Routine
4397 9.0 1.0 Routine
4398 9.0 1.25 Routine
4357 6.0 .75 Routine
4399 11.0 1.25 Routine
4401 11.0 1.25 Routine
4400 11.0 1.25 Routine
4358 6.0 .75 Routine
4402 9.0 1.0 Routine
4359 9.0 1.0 Routine
4403 9.0 1.0 Routine
4404 9.0 1.0 Routine
4360 6.0 .75 Routine
4405 11.0 1.25 Routine
4406 11.0 1.25 Routine
4407 11.0 1.25 Routine
4361 6.0 .75 Routine
4408 9.0 1.0 Routine
4409 9.0 1.0 Routine
4362 6.0 .75 Routine
4363 6.0 .75 Routine
4410 6.0 .75 Routine
4412 9.0 1.0 Routine
4413 9.0 1.0 Routine
4411 6.0 .42 Routine
4364 6.0 .5 Routine
3005 9.0 1.0 Routine
4365 6.0 .75 Routine
4419 9.0 1.0 Routine
4366 6.0 .75 Routine
4420 9.0 1.0 Routine
4367 6.0 .75 Routine
4421 9.0 1.0 Routine
4422 9.5 1.0 REFUSAL
4424 8.5 1.0 REFUSAL
4423 11.0 1.25 Routine
4368 6.0 .75 Routine
4425* 9.0 1.0 Routine
4369 6.0 .70 Routine
4426 9.0 1.0 Routine
4370 6.0 .75 Routine
4427 9.0 1.0 Routine
* Proof Test – Movement 3/8” – Acceptable
Total Production Piers this day = 71
Total Production Piers to date = 118
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 6/22/21, OVERCAST – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
v
Long view of Installation Rig – Area D
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 6/22/21, OVERCAST – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
Stockpile of ¾” Crushed Stone
Loading
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 6/23/21, Partly Cloudy Mid 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
This Report is a summary installation list of installed vibratory stone columns, (VSC), in accordance with Submittal #31
3400-02.0 31 3400 – Aggregate Piers, prepared by CMC Professional Services LLC, 335 E. Geneva Rd #3116, Carol
Stream, Il 60188.
Glossary of Header Terms:
VSC Pier #: Each pier is identified by number according to location plan included in the above referenced
Submittal.
Installed Depth: The as-built length of pier as constructed from working grade to termination in suitable native,
(bearing) soil.
Stone Take: The amount of Crushed Stone used in constructing a given Pier, (expressed in volume), one cubic
yard weighs approximately 1.2 Ton.
Comments: Note any deviation from standard installation procedures, proposed depths or changes in location of
said Pier.
Activity for Wednesday, June 23rd, 2021
VSC Pier # Installed Depth (ft.) Stone Take (Cu. Yds.) COMMENTS
4344 9.4 1.0 Routine
4315 9.5 1.0 Routine
4316 6.0 .75 Routine
4317 6.0 .75 Routine
4318 6.2 .75 Routine
4319 6.2 .75 Routine
4320 6.4 .75 Routine
4321 6.9 .75 Routine
4322 6.0 .75 Routine
4323 6.0 .75 Routine
4324 6.0 .75 Routine
4325 6.0 .75 Routine
4326 6.0 .75 Routine
4327 6.0 .75 Routine
4328 6.0 .75 Routine
4329 6.0 .75 Routine
4330 6.0 .75 Routine
4331 6.0 .75 Routine
4332 6.0 .75 Routine
4333 6.0 .75 Routine
4334 6.0 .75 Routine
4335 6.4 .75 Routine
4336 6.0 .75 Routine
4337 6.0 .75 Routine
4338 6.0 .75 Routine
4339 6.0 .75 Routine
4340 6.0 .75 Routine
4341 6.0 .75 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 6/23/21, Partly Cloudy Mid 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
4342 6.0 .75 Routine
4428 9.0 1.0 Routine
4429 9.0 1.0 Routine
4371 9.5 1.25 Routine
4343 9.0 1.0 Routine
4231 9.0 1.0 Routine
4232 9.0 1.0 Routine
4233 9.0 1.0 Routine
4286 9.0 1.0 Routine
4287 6.0 .80 Routine
4288 7.2 .80 Routine
4234 7.6 .80 Routine
4289 6.0 .75 Routine
4235 6.82 .75 Routine
4290 6.0 .75 Routine
4236 14.0 1.5 Routine
4237 14.0 1.5 Routine
4239* 14.0 1.5 Routine
4238 14.0 1.5 REFUSAL
4291 6.0 .75 Routine
4240 6.0 .75 Routine
4292 6.0 .75 Routine
4241 6.0 .75 Routine
4293 6.0 .75 Routine
4242 14.0 1.20 Routine
4243 13.0 1.25 REFUSAL
4244 12.0 1.25 REFUSAL
4245 12.0 1.25 REFUSAL
4246 12.0 1.25 REFUSAL
4294 6.0 .75 Routine
4247 6.0 .75 Routine
4248 9.0 1.0 Routine
4295 6.0 .75 Routine
4249 9.0 1.0 Routine
4296 6.0 .75 Routine
4250 6.0 ..75 Routine
4297 6.0 .75 Routine
4251 11.0 .75 Routine
4252 11.0 .75 Routine
4253 11.0 .75 Routine
4298 6.0 .75 Routine
4254 6.4 .75 Routine
4299 6.0 .75 Routine
4255 6.0 .75 Routine
4300 6.0 .75 Routine
4257 14.0 1.25 Routine
4256 14.0 1.25 Routine
4259 14.0 1.25 Routine
4258 14.0 1.25 Routine
4260 6.0 .75 Routine
4301 6.0 .75 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 6/23/21, Partly Cloudy Mid 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
4302 6.0 .75 Routine
4261 6.0 .75 Routine
4303** 6.0 .75 Routine
4262 6.0 .75 Routine
4263 11.0 1.0 Routine
4264 11.0 1.0 Routine
4265 11.0 1.0 Routine
4304 6.0 .75 Routine
4266 6.0 .75 Routine
4305 6.0 .75 Routine
4267 6.0 .75 Routine
* Proof Test – Movement ¼” – Acceptable
** Proof Test – Movement < ¼” – Acceptable
Total Production Piers this day = 90
Total Production Piers to date = 208
Photos: Typical Installation Procedure in four steps
1. Tip of mandrel prior to insertion
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 6/23/21, Partly Cloudy Mid 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
2. Mandrel advanced to design depth
3. Crushed Stone being dispensed through mandrel as it is withdrawn in increments
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 6/23/21, Partly Cloudy Mid 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
4. Ramming vibratory action is then applied to the Crushed Stone, (aggregate) that results in the formation of the
VSC, (Vibratory Stone Column).
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 6/24/21, CLEAR LOW 80’S Caseyville, Il 62232
_________________________________________________________________________________________________
This Report is a summary installation list of installed vibratory stone columns, (VSC), in accordance with Submittal #31
3400-02.0 31 3400 – Aggregate Piers, prepared by CMC Professional Services LLC, 335 E. Geneva Rd #3116, Carol
Stream, Il 60188.
Glossary of Header Terms:
VSC Pier #: Each pier is identified by number according to location plan included in the above referenced
Submittal.
Proposed Depth: Total VSC depth from working grade to proposed bottom elevation as put forth in design
criteria.
Installed Depth: The as-built length of pier as constructed from working grade to termination in suitable native,
(bearing) soil.
Stone Take: The amount of Crushed Stone used in constructing a given Pier, (expressed in volume), one cubic
yard weighs approximately 1.2 Ton.
Comments: Note any deviation from standard installation procedures, proposed depths or changes in location of
said Pier.
Activity for Thursday, June 24th, 2021
VSC Pier # Proposed Depth Installed Depth Stone Take (Cu. Yds.) COMMENTS
4306 6.0 6.0 0.7 Routine
4268 9.0 9.0 1.0 Routine
4269 9.0 9.0 1.0 Routine
4307 6.0 6.0 0.7 Routine
4270 6.0 7.2 1.0 Routine
4271 14.0 14.0 1.25 Routine
4272 14.0 14.0 1.25 Routine
4273 14.0 13.0 1.25 REFUSAL
4274 14.0 13.0 1.25 REFUSAL
4275 14.0 14.0 1.5 Routine
4308 6.0 6.0 0.75 Routine
4276 6.0 6.0 0.75 Routine
4309 6.0 6.0 0.75 Routine
4277* 6.0 6.0 0.75 Routine
4310 6.0 6.0 0.75 Routine
4278 14.0 14.0 1.25 REFUSAL
4279 14.0 12.1 1.25 Routine
4311 6.0 6.0 0.75 Routine
4281 14.0 13.0 1.25 REFUSAL
4280 14.0 12.6 1.25 Routine
4282 6.0 6.0 0.75 Routine
4312 6.0 6.0 0.75 Routine
4313 6.0 6.0 0.75 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 6/24/21, CLEAR LOW 80’S Caseyville, Il 62232
_________________________________________________________________________________________________
4283 6.0 6.0 0.75 Routine
4314 9.0 9.0 1.0 Routine
4285 9.0 9.0 1.0 Routine
4284 9.0 6.0 0.75 REFUSAL
4201 9.0 9.0 1.0 Routine
4202 9.0 9.0 1.0 Routine
4203 6.0 6.0 0.75 Routine
4204 6.0 6.5 0.75 Routine
4205 6.0 6.0 0.75 Routine
4206 6.0 6.0 0.75 Routine
4207 6.0 6.0 0.75 Routine
4208 6.0 6.0 0.75 Routine
4209 6.0 6.0 0.75 Routine
4210 6.0 6.0 0.75 Routine
4211 6.0 6.0 0.75 Routine
4212 6.0 6.0 0.75 Routine
4213 6.0 6.0 0.75 Routine
4214 6.0 6.0 0.75 Routine
4215 6.0 6.0 0.75 Routine
4216 6.0 6.0 0.75 Routine
4217 6.0 6.0 0.75 Routine
4218 6.0 6.0 0.75 Routine
4219 6.0 6.0 0.75 Routine
4220 6.0 6.0 0.75 Routine
4221 6.0 6.0 0.75 Routine
4222 6.0 6.0 0.75 Routine
4223 6.0 6.0 0.75 Routine
4224 6.0 6.0 0.75 Routine
4225 6.0 6.0 0.75 Routine
4226 6.0 6.0 0.75 Routine
4227 6.0 6.0 0.75 Routine
4228 6.0 6.0 0.75 Routine
4229 9.0 9.0 1.0 Routine
4230** 9.0 9.0 1.0 Routine
4147 14.0 14.0 1.5 Routine
4148 14.0 14.0 1.5 Routine
4146 14.0 11.0 1.5 REFUSAL
4149 6.0 6.0 0.75 Routine
4150 6.0 6.0 0.75 Routine
4151 6.0 6.0 0.75 Routine
4156 6.0 6.0 0.75 Routine
4157 6.0 6.0 0.75 Routine
4158 11.0 11.0 1.0 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 6/24/21, CLEAR LOW 80’S Caseyville, Il 62232
_________________________________________________________________________________________________
4159 11.0 11.0 1.0 Routine
4160 11.0 9.75 1.0 REFUSAL
* Proof Test – Movement < ¼” – Acceptable
** Proof Test – Movement 5/16” – Acceptable
Total Production Piers this day = 68
Total Production Piers to date = 276
NOTE: although item 12 in the ground improvement submittal allows for stoppage of installation “at refusal” in
native soil, based on all test borings drilled for this project there is no reason a “refusal” would occur in native soil on
this site at the planned installation depths. Ways a “refusal” could occur may either be an issue with the installation
rig itself or buried man‐made structures (sewers, drains, septic system etc.). Although it is possible a dense gravel
layer could be found at depth, it is unlikely based upon the multiple test borings drilled. Installer should review his
installation methodology and if necessary a test pit be excavated near refusal piers to the depth of refusal.
Topping off Pier with side feed hopper, (typical)
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 6/24/21, CLEAR LOW 80’S Caseyville, Il 62232
_________________________________________________________________________________________________
Pier # 4147 mandrel @ 14’ depth
Withdrawing mandrel Pier # 4147