UNIT PRICES
01 2200 - 1
SECTION 01 2200
UNIT PRICES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for unit prices.
B. Related Requirements:
1. Document 00 4322 "Unit Prices Form" for proposed unit price amounts.
2. Section 01 2600 "Contract Modification Procedures" for procedures for submitting and
handling Change Orders.
1.3 DEFINITIONS
A. Unit price is an amount incorporated into the Agreement, applicable during the duration of the
Work as a price per unit of measurement for materials, equipment, or services, or a portion of
the Work, added to or deducted from the Contract Sum by appropriate modification, if the scope
of Work or estimated quantities of Work required by the Contract Documents are increased or
decreased.
1.4 PROCEDURES
A. Unit prices include all necessary material, plus cost for delivery, installation, insurance,
overhead, and profit.
B. Measurement and Payment: See individual Specification Sections for work that requires
establishment of unit prices. Methods of measurement and payment for unit prices are
specified in those Sections.
C. Owner reserves the right to reject Contractor's measurement of work-in-place that involves use
of established unit prices and to have this work measured, at Owner's expense, by an
independent surveyor acceptable to Contractor.
D. List of Unit Prices: A schedule of unit prices is included in Part 3. Specification Sections
referenced in the Part 3 "Schedule of Unit Prices" Article contain requirements for materials
described under each unit price.
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011 Addendum #5, Dated 2/23/2021
UNIT PRICES
01 2200 - 2
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 SCHEDULE OF UNIT PRICES
A. Unit Price No. 1: Rock excavation and replacement with satisfactory soil material.
1. Description: Classified rock excavation and disposal off-site and replacement with
satisfactory fill material or engineered fill from off-site, as required, in accordance with
Section 31 0000 "Earth Moving."
2. Unit of Measurement: Per cubic yard of rock excavated, based on in-place surveys of
volume before and after removal.
3. Quantity Allowance: Include 200 cu. yd. of mass rock removal and replacement with
satisfactory soil material, as specified in Section 31 0000 "Earth Moving."
B. Unit Price No. 2: Removal of unsatisfactory soil and replacement with satisfactory soil material.
1. Description: Unsatisfactory soil excavation and disposal off-site and replacement with
satisfactory fill material or engineered fill from off-site, as required, in accordance with
Section 31 0000 "Earth Moving."
2. Unit of Measurement: Per cubic yard of soil excavated, based on in-place surveys of
volume before and after removal.
3. Quantity Allowance: Include 5,000 cu. yd. of unsatisfactory soil excavation and disposal
off-site and replacement with satisfactory soil material from off-site, as specified in
Section 31 0000 "Earth Moving."
C. Unit Price No. 3: Moisture vapor emission control without cementitious underlayment.
1. Description: Provide moisture vapor emission control for existing concrete floor slabs in
accordance with Section 09 0561.13 “Moisture Vapor Emission Control” except without
cementitious underlayment. Cementitious underlayment is already included in the Work
for linoleum flooring and resilient athletic flooring as Specified in Section 03 5416
“Hydraulic Cement Underlayment” and shall not be included as part of this unit price.
2. Unit of Measurement: Per square foot.
3. Quantity Allowance: Include 20,000 SF
D. Unit Price No. 4: Moisture vapor emission control including cementitious underlayment.
1. Description: Provide moisture vapor emission control system including cementitious
underlayment for existing concrete floor slabs in accordance with Section 09 0561.13
“Moisture Vapor Emission Control.”
2. Unit of Measurement: Per square foot.
3. Quantity Allowance: Include 10,000 SF
END OF SECTION