01 8113 Sustainable Design Requirements
1 of 18
SECTION 018113 - SUSTAINABLE DESIGN REQUIREMENTS
PART 1 – GENERAL
1.1 SUMMARY
A. This Section includes administrative requirements and procedures for compliance and documentation for
the Dennis Yarmouth Intermediate Middle School project to obtain minimum LEED Gold for Building
Design and Construction for (LEED-BD+C) certification under the US Green Building Council’s LEED-NC
v4 & LEED NC v4.1 (where indicated) rating system.
B. Related Sections:
1. Section 013300 - SUBMITTAL PROCEDURES
2. Section 017419 - CONSTRUCTION WASTE MANAGEMENT
3. Section 015 100 – CONSTRUCTION INDOOR AIR QUALITY
4. Section 019119 – GENERAL COMMISSIONING REQUIREMENTS
5. Section 312500 – SEDIMENTATION AND EROSION CONTROL
6. Section 017823 – OPERATION AND MAINTENANCE DATA
7. Divisions 03 through 12, 31, and 32 Sections: Specific requirements for materials in those
Sections.
1.2 DEFINITIONS
A. United States Green Building Council (USGBC): A non-profit group of leaders from every sector of the
building industry working to promote buildings that are environmentally responsible, profitable and healthy
places to live and work. The USGBC is administrator of the LEED Green Building Rating Systems.
B. Leadership in Energy & Environmental Design (LEED): A green building rating system that provides
independent third party verification of a project’s sustainability.
C. Indoor Air Quality (IAQ) Management Plan: Plan developed by the contractor to provide a healthy and
safe indoor environment for workers during construction as well as the building’s current and eventual
occupants. The IAQ Management Plan must meet or exceed the recommendations of the Sheet Metal
and Air Conditioning National Contractors Association (SMACNA) IAQ Guidelines for Occupied Buildings
under Construction, 2nd edition, 2007, ANSI/SMACNA 008–2008, Chapter 3.
D. Material Cost: The dollar value of materials being provided to the site, after any contractor mark-ups,
inclusive of all transportation and tax fees but excluding equipment and labor costs.
E. Environmental Product Declaration (EPD): An independently verified report based on life-cycle
assessment studies that have been conducted according to a set of common rules for each product
category and then peer-reviewed.
F. Cradle to Gate Assessment: Analysis of a product’s partial life cycle, from resource extraction (cradle) to
the factory gate (before it is transported for distributi0on and sale). It omits the use and the disposal
phases of the product.
G. Cradle to Grave: Analysis of a product’s full life cycle, from resource extraction (cradle) to the disposal
phase (grave).
H. Life Cycle Assessment: An evaluation of the environmental effects of a product from cradle to grave, as
defined by ISO 14040-2006 and ISO 14044-2006.
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
01 8113 Sustainable Design Requirements
2 of 18
I. Third-party Verified Corporate Sustainability Reports (CSR): A report that outlines the environmental impacts of extraction operations and activities associated with the manufacturer’s product and the product’s supply chain. Corporate sustainability reports must be in line with one of the following: Global
Reporting Initiative (GRI) Sustainability Report, Organization for Economic Co-operation and
Development (OECD) Guidelines for Multinational Enterprises, U.N. Global Compact, and ISO 26000.
J. Extended Producer Responsibility (EPR): Products whose manufacturer has established measures to
reclaim its products at the end of their useful life and to recycle them into the same product.
K. Product Category Rules: A set of rules, requirements, and guidelines for developing Environmental
Product Declarations.
L. Program Operator: An organization that ensures EPDs meet the product category rules (PCRs) for the associated product category. The program operator doesn’t do the actual life-cycle assessments. UL
Environment is the leading program operator in the United States.
M. Product-Specific Environmental Product Declaration (EPD): A product with a publicly available, critically
reviewed life-cycle assessment conforming to ISO 104044 that has at least a cradle to gate scope.
N. Product-Specific Type III Environmental Product Declaration (EPD): A product with a with third-party
certification, including external verification, in which the manufacturer is explicated recognized by the
program operator. The product specific Environmental Product Declaration shall conform to ISO 14025,
ISO 14040, ISO 14044, and EN 15804 or ISO 21930 and have at least a cradle to gate scope.
O. Industry-wide Environmental Product Declaration (EPD): A product with a with third-party certification,
including external verification, in which the manufacturer is explicated recognized by the program
operator. The industry-wide Environmental Product Declaration shall conform to ISO 14025, ISO 14040,
ISO 14044, and EN 15804 or ISO 21930 and have at least a cradle to gate scope. Also referred to as a “generic” Environmental Product Declaration.
P. Bio-based Materials: A product that meets the Sustainable Agriculture Network's Sustainable Agriculture
Standard. Bio-based raw materials shall be tested using ASTM Test Method D6866 and be legally
harvested, as defined by the exporting and receiving country.
Q. Composite Wood and Agrifiber: Products such as particleboard, medium density fiberboard (MDF),
plywood, wheatboard, strawboard, panel substrates, and door cores that are a composite of wood and/or
plant material pressed and adhered together.
R. Chain of Custody (COC): Certificates signed by manufacturers certifying that wood used to make
products was obtained from forests certified by an FSC-accredited certification body to comply with FSC
STD-01-001, "FSC Principles and Criteria for Forest Stewardship." Certificates shall include evidence
that manufacturer and supplier are certified for chain of custody by an FSC-accredited certification body.
S. Recycled Content: The percentage by weight of a material’s constituents that have been recovered or
otherwise diverted from the solid waste stream, either during the manufacturing process (pre-consumer),
or after consumer use (post-consumer).
a. Spills and scraps from the original manufacturing process that are combined with other
constituents after a minimal amount of reprocessing for use in further production of the same
product are not recycled materials.
b. Discarded materials from one manufacturing process that are used as constituents in another
manufacturing process are pre-consumer or post industrial recycled materials.
c. Recycled content of materials shall be defined in accordance with the International Organization
for Standardization document, ISO 14021-1999 – Environmental labels and declarations – self
declared environmental claims (Type II environmental labeling). www.iso.org
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
01 8113 Sustainable Design Requirements
3 of 18
T. Pre-consumer Recycled Content: Matter diverted from the waste stream during the manufacturing
process, determine as the percentage of material, by weight.
U. Post-consumer Recycled Content: Waste generated by households or commercial, industrial, and
institutional facilities in their role as end users of a product that can no longer be used for its intended
purpose.
V. Regionally Extracted, Processed and Manufactured Materials: Materials that are extracted, harvested, or
recovered; processed; and manufactured within a radius of 100 miles (160 km) from the Project location.
Manufacturing refers to the final assembly of components into the building product that is installed at the
Project site.
W. Health Product Declaration: A standard format for reporting product content and associated health
information for building products and materials.
X. GreenScreen® for Safer Chemicals: A method for comparative chemical hazard assessment and their
potential effect on human health and the environment.
Y. Volatile Organic Compound (VOC): Carbon compounds considered indoor air contaminants that are
odorous, irritating, and/or harmful to the comfort and wellbeing of installers and occupants.
Z. Wet Products: Materials and products installed in wet form, including paints, sealants, adhesives, and
special coatings.
1.3 PROJECT GOALS
A. The proposed project is designed to be sustainable, with the intent of incorporating the following qualities:
1. The project will minimize its effect on the environment by selecting environmentally friendly building
materials and utilizing sustainable construction practices.
2. The project will provide a healthy and comfortable space for its occupants by developing and
following an Indoor Air Quality Management Plan during construction, by selecting only non-toxic and
low-emitting materials, and by designing the building’s systems to provide tenants with exceptional
indoor air quality.
3. The finished project will consume significantly less energy and water than a typical code-compliant
building through the use of premium efficiency equipment and designing efficient building systems.
B. The proposed project is targeting a minimum GOLD from the US Green Building Council’s (USGBC)
Leadership in Energy and Environmental Design Building Design and Construction (LEED-BD+C) version
4.0 and version 4.1 (where indicated) Green Building Rating System. The following are expected of all
contractors and sub-contractors:
1. Comply with LEED-NC version 4.0 and 4.1 (where indicated) requirements for those credits being
targeted.
2. Refer to LEED Scorecard that follows this Section.
3. Refer to individual Specification Sections for additional requirements.
1.4 MEETINGS
A. Prime Contractor shall conduct LEED Certification meetings at 25%, 50% and 100% construction
completion, in addition to those meetings outlined in Section 013100 Project Management and
Coordination.
1. The meetings shall include, at a minimum:
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
01 8113 Sustainable Design Requirements
4 of 18
a. Prime Contractor’s Project Manager
b. Owner’s Representative
c. Prime Contractor’s LEED Representative
d. All other attendees designated by Owner’s Representative
e. Sub-Contractor Representatives as appropriate to stage of work
2. At a minimum, LEED certification goals and issues shall be discussed at the following meetings:
a. Preconstruction Meetings
b. Progress Meetings
c. Subcontractor Meetings
d. LEED Certification Meetings (outlined above). Meeting should be scheduled as a part of
regularly scheduled job meetings on site.
1.5 SUBMITTAL REQUIREMENTS
A. Coordination of Submittals: Coordinate LEED submittals with general submittal requirements as indicated
in Section 013300 – SUBMITTAL PROCEDURES.
B. LEED Action Plans: Provide preliminary hard copy submittals within 14 days of date established for
commencement of the Work indicating how the following requirements will be met.
1. Materials & Resources Prerequisite and Credit: Construction and Demolition Waste Management
complying with Division 01 Section "Construction Waste Management."
2. Materials & Resources Credit: Building product disclosure and optimization – sourcing of raw
materials: list of proposed materials with recycled content, proposed regionally extracted, processed
and manufactured materials, and proposed FSC-certified wood products
3. Indoor Environmental Quality Credit: Construction Indoor Air Quality Management Plan: submit a
draft copy of the plan for review, complying with Section 015100 – Construction Indoor Air Quality
C. Contractor is responsible for completion and transmittal of ALL construction-related tracking required for
LEED certification including:
1. LEED Submittal Coversheets: All project submittals must be accompanied by a completed LEED
coversheet. Submittal packages must also include documentation in support of the sustainability
claims made on the LEED coversheet, including:
2. Cost of each material or product, excluding labor and equipment
3. From manufacturer, for each product‘s environmental attributes. The team’s sustainability consultant
will be responsible for obtaining a report describing raw materials suppliers, complete content
inventory for the product, and/or environmental product declaration.
4. Highlight compliance with all requirements for low-emitting materials as noted in Section 2 (Products)
5. Providing and following an Erosion and Sedimentation Control Plan. See Section 312500 – Erosion
and Sedimentation Control Plan.
6. Providing and following a Construction Waste Management Plan and ongoing documentation of
construction and demolition waste recycling / salvage rates for all categories of waste. See Section
017419 - Construction Waste Management.
7. During construction, meet or exceed all applicable recommended control measures of the Sheet
Metal and Air Conditioning National Contractors Association (SMACNA) IAQ Guidelines for Occupied
Buildings under Construction, 2nd edition, 2007, ANSI/SMACNA 008–2008, Chapter See Section
015100 – Construction Indoor Air Quality
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
01 8113 Sustainable Design Requirements
5 of 18
8. Providing monthly tracking and progress updates on the following credits. The sustainability
consultant will be responsible for final documentation for submission to the Green Business
Certification Inc (GBCI).
1. Materials & Resources Prerequisite and Credit: Construction and Demolition Waste Management
2. Materials & Resources Credit: Building Product Disclosure and Optimization – Sourcing of Raw
Materials
3. Indoor Environmental Quality Credit: Low Emitting Interiors
4. Indoor Environmental Quality Credit: Construction IAQ Management Plan
5. Indoor Environmental Quality Credit: Indoor Air Quality Assessment
9. Contractor to maintain Materials Credit Tracking Sheet monitoring the project’s progress towards
targeted LEED Materials and Resources Credits. Tracking Sheet to be presented at construction
meetings.
10. Contractor to maintain a Low Emitting Materials Tracking Sheet monitoring the project’s progress
towards targeted LEED Indoor Environmental Quality Credits. Tracking Sheet to be presented at
construction meetings.
11. Contractor to package each submittal individually using a LEED Transmittal Cover Sheet verifying
that submittals comply with LEED Requirements and that appropriate documentation is included. See
sample provided.
12. Project Materials Cost Data: Provide itemized and total cost for ALL building materials under
Divisions 2-10, 12, 31, and 32 used for Project, excluding labor and equipment.
13. Contractor to provide Commissioning Authority with a copy of approved submittals for all equipment
to be commissioned as well as documentation requested by the Commissioning Authority which is
necessary for the commissioning process. This may include: detailed manufacturer installation and
start-up, operating, troubleshooting and maintenance procedures, full details of any owner-contracted
tests, fan and pump curves, full factory testing reports, if any, and full warranty information including
all responsibilities of the Owner to keep the warranty in force clearly identified. The actual field
checkout sheet forms to be used by the factory or field technicians shall be provided to the
Commissioning Authority.
1.6 SPECIAL PRODUCTS AND SUBSTITUTION PROCEDURES
A. In addition to the requirements of Section 012500 – Substitution Procedures, the special substitution
requirements described here apply only to the LEED certification related materials and requirements and
environmental products and procedures identified in this Section.
B. Notify Owner and Architect when contractor wishes to substitute materials, equipment, or products that
meet the aesthetic and programmatic intent of the Construction Documents and offer equivalent or
increased environmental sensitivity to materials, equipment, or products specified to meet LEED
requirements as indicated in the Construction Documents.
C. Substitutions that may affect LEED certification must be clearly stated as such.
D. Comply with the requirements of Section 012500 – Substitution Procedures, except as follows:
1. Prior to submitting detailed information required under Section 012500 – Substitution Procedures,
submit the following for initial review by the architect.
a. Product data including manufacturer’s names, address, and phone number.
b. Include copy of Material Safety Data Sheet (MSDS) if applicable.
c. Description of the differences of the proposed substitution from specified product related
to LEED requirements. Include description of environmental advantages of proposed
substitution over specified product.
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
01 8113 Sustainable Design Requirements
6 of 18
d. The contractor is responsible for re-submittal of all calculations, and documentation of
products or material substitutions that affect LEED prerequisites and credits referenced in this Section, and any credits previously submitted as part of the project’s LEED Design
Application Submittal, and all credits included in the LEED Construction Submittal.
Products that do not meet these requirements should not be submitted for substitution.
e. Substitutions of materials and products specified as part of the Contract documents in the
following areas (but not necessarily limited to these items) will require review and
potential re-submittal of LEED Design Credit Application Pre-requisites and Credits:
i. Irrigation System
ii. Rainwater Management System
iii. Roofing products and materials
iv. Plumbing fixtures and controls
v. Interior and Exterior Lighting systems and controls
vi. HVAC equipment, systems and controls
vii. CO2 monitoring system
viii. Acoustical Performance
f. Substituted products shall not be ordered or installed without written acceptance by the
owner.
2. Requests for Substitutions
a. Submit a Submit a separate request for each LEED related product substitution.
b. Identify product by Specification Section and LEED credit or credits, if applicable.
c. List similar projects using product, dates of installation, and names of Contractor and
Owner.
d. Give itemized comparison of proposed substitution with specified product, listing
variations, and reference Specification section and Article number.
e. Include copy of Material Safety Data Sheet (MSDS) if applicable.
f. Give cost data comparing proposed substitution with specified product and amount of net
change to Contract Sum. The cost data should be based on life cycle analysis for each
affected product including annual energy consumption and maintenance costs.
g. State effect of substitution on construction schedule and changes required in other work
of products.
1.7 LEED DOCUMENTATION SUBMITTALS
A. For all credits: LEED documentation submittals must be prepared and submitted using the LEED-
Online Credit web based application (https://www.usgbc.org/leedonline/) and minimum system
requirements.
A. Once the Contractor has joined the project through LEED-Online, the LEED Project Administrator
will assign the LEED credits that the contractor is responsible for completing.
a. NOTE: LEED Online is only accessible through Safari, Internet Explorer and Firefox at this
time.
b. NOTE: Each “Credit Form” is an editable Adobe pdf document. It may be completed or
updated at any time prior to the LEED Construction Submittal. After you have completed
documenting the credit, use the ‘Save’ button at the lower right hand corner of the Form to
save the data online.
c. Additional submittal documentation and back-up requirements should be uploaded to the “File Uploads” section of LEED-Online following the required documentation support for each
credit.
B. Sustainable Sites Prerequisite Construction Activity Pollution Prevention. Using the LEED Online
Credit form, provide:
a. A narrative describing the implemented erosion and sedimentation control measures and how
these were maintained
b. Photographic evidence of the implemented measures from various stages throughout
construction.
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
01 8113 Sustainable Design Requirements
7 of 18
C. Water Efficiency Prerequisite and Credit Water Metering and Energy & Atmosphere Prerequisite and
Credit Energy Metering: Product Data and wiring diagrams for sensors and data collection system
used to provide continuous metering of building energy and water consumption performance over
time.
D. Materials & Resources Prerequisite and Credit: Construction and Demolition Waste Management:
Comply with Division 01 Section "Construction Waste Management." Using the LEED Construction
and Demolition Waste Calculator and the LEED Credit Form:
a. Complete the construction waste calculation tables including: General description of each
type/category of waste generated; location of receiving agent (recycler/landfill) for waste; quantity
of waste diverted (by category) in tons or cubic yards.
b. Provide a narrative describing the project’s construction waste management approach including a copy of the project’s construction waste management plan. Please provide any additional comments or notes to describe special circumstances or considerations regarding the project’s
credit approach.
c. Provide the Construction Waste Management Plan.
d. Provide the hauling/recycling tags/tickets or receipts from the project
e. Provide project-specific documentation of recycling rate for commingled facilities
E. Materials & Resources Credit: Building Product Disclosure and Optimization –Environmental Product
Declaration- EPDs - Environmental Product Declarations Using the LEED Building Product Disclosure
and Optimization Calculator and the LEED Online Credit Form:
a. Provide a list of manufactures providing EPDs.
b. Provide a list of each separate product holding an EPD.
c. Provide copy of each EPD including statement type for each EPD.
F. Materials & Resources Credit: Building Product Disclosure and Optimization – Sourcing of Raw
Materials, Leadership Extraction Practices - Recycled Content Using the LEED Building Product
Disclosure and Optimization Calculator and the LEED Online Credit Form:
a. Provide the total project materials cost per “Project Materials Cost Data” in the Submittals section
above.
b. Provide a tabulation of each material used on the project that is being tracked for recycled
content. The tabulation must include a description of the material, the manufacturer of the
material, the product cost, the pre-consumer and/or post-consumer recycled content percentage,
and the source of the recycled content data.
c. Provide a tabulation of each material used on the project that is being tracked for regional
content. The tabulation must include a description of the material; the manufacturer of the
material; the product cost; the percentage of the product by weight that meets both the extraction
and manufacturer location criteria; distance between the project site and
extraction/harvest/recovery site; and distance between the project site and final manufacturing
location.
d. Provide Manufacturer cut sheets, literature, or letters highlighting the overall post-consumer
and/or post-industrial recycled content percentages (by weight) of each listed product
e. Provide Manufacturer cut sheets, literature, or letters highlighting address location of each material’s extraction/harvest/recovery and manufacturing / processing sites AND a map (Yahoo
Maps, Google Maps or equivalent) indicating distances from each location to the project site.
G. Materials & Resources Credit: Building Product Disclosure and Optimization – Sourcing of Raw
Materials, Leadership Extraction Practices - FSC Certified Wood Products. Using the LEED Building
Product Disclosure and Optimization Calculator and the LEED Online Credit Form:
a. Provide total of all new, permanently installed wood-based construction materials cost per “Project Materials Cost Data” in the Submittals section above.
b. Provide a list of items (and/or components of products) claimed as FSC-certified, including product type, manufacturer, and the entity’s Chain of Custody (COC) certification number. (Each
product name can then be cross-referenced with the manufacturer or vendor COC number during
the LEED certification review.) Visit www.fscus.org/green_building for more information.
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
01 8113 Sustainable Design Requirements
8 of 18
c. Provide official proof of FSC Chain of Custody certification of all fabricators including, but not
limited to, millworkers and cabinet-makers, who modify or alter the FSC wood products before
they are installed in the project.
d. Provide materials invoices (showing costs) for each listed product
H. Materials & Resources Credit: Building Product Disclosure and Optimization – Material Ingredients-
Material Ingredient Reporting- Material Ingredient Reporting Using the LEED Building Product
Disclosure and Optimization Calculator and the LEED Online Credit Form:
a. Provide a list of manufactures providing material ingredient reporting.
b. Provide a list of each separate product providing material ingredient reporting.
c. Provide copy of each material reporting statement including: Health Product Declaration, Cradle
to Cradle Declare, ANSI/BIFMA e3 Furniture Sustainability Standard, Cradle to Cradle Material
Health Certificate, or other USGBC approved program.
I. Indoor Environmental Quality Credit low-Emitting Materials. Using the LEED Low Emitting Calculator
and LEED Online Credit Form, provide the following:
a. A listing of each interior applied paints and coating. Include the manufacture’s name, product
name, specific VOC data (in g/L less water) for each product, and the corresponding allowable
VOC from the referenced standard: California Department of Public Health (CDPH) Standard
Method v1.2-2017, using the applicable exposure scenario, VOC limits of the California Air
Resources Board (CARB) 2007, Suggested Control Measure (SCM) for Architectural Coatings, or
the South Coast Air Quality Management District (SCAQMD) Rule 1113, effective February 5,
2016. Include cut sheets, MSDS, or other manufacturer’s data confirming compliance with the
VOC limits.
b. A listing of each indoor adhesive, sealant and sealant primer product used on the project. Include the manufacture’s name, product name, specific VOC data (in g/L less water) for each product,
and the corresponding allowable VOC from the referenced standard, California Department of
Public Health (CDPH) Standard Method v1.2-2017, using the applicable exposure scenario, or
SCAQMD Rule 1168, October 6, 2017. Include cut sheets, MSDS, or other manufacturer’s data
confirming compliance with the VOC limits.
c. A listing of each composite wood and agrifiber product installed in the building interior, including
those manufactured off-site, such as toilet partitions, backer board, door cores and engineered
wood, including manufacture’s name and product name. Confirm that the product meets the low
formaldehyde emissions that meet the EPA TSCA Title VI or California Air Resources Board
ATCM for formaldehyde requirements for ultra-low-emitting formaldehyde (ULEF) resins or no
added formaldehyde resins. Include cut sheets or manufacturer literature or letters indicating the
bonding agents for each composite wood and agrifiber material used in the project, showing that
no added urea-formaldehyde resins were used in these products or meets ULEF criteria.
d. A listing of each structural composite wood installed in the building interior, such as plywood,
oriented-strand board, structural composite lumber, glued laminated timber, i-joists, cross-
laminated timber, and finger-jointed lumber, including manufacture’s name and product name.
Confirm that the product meets. Confirm that wood products are made with moisture resistant
adhesives meeting ASTM 2559, have no surface treatments with added urea-formaldehyde
resins or coatings, and are certified according to the applicable industry standard. Include cut
sheets or manufacturer literature or letters indicating the bonding agents for each composite
wood and agrifiber material used in the project, showing compliance with the applicable industry
standard:
i. Plywood: compliant in accordance with Voluntary Product Standard ‐ Structural Plywood
(PS 1‐09), Voluntary Product Standard – Performance Standard for Wood‐Based
Structural‐Use Panels (PS 2‐10), or one of the standards considered by CARB to be
equivalent to PS 1 or PS 2: (AS/NZS 2269, EN 636 3S (including CE label), Canadian
ii. Standards Association CSA O121 for Douglas fir plywood, CSA O151 for Canadian
softwood plywood, for CSA O153 Poplar plywood, or CSAO325 for Construction
sheathing)
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
01 8113 Sustainable Design Requirements
9 of 18
iii. Oriented strand board: specified with the Exposure 1 or Exterior bond classification in
accordance with Voluntary Product Standard – Performance Standard for Wood‐Based
Structural‐Use Panels (PS 2‐10)
iv. Structural composite lumber: compliant in accordance with Standard Specification for
Evaluation of Structural Composite Lumber Products (ASTM D 5456‐13)
v. Glued laminated timber: compliant in accordance with Structural Glued Laminated Timber
(ANSI A190.1‐2012)
vi. I‐joists compliant in accordance with Standard Specification for Establishing and
Monitoring Structural Capacities of Prefabricated Wood I‐Joists (ASTM D 5055‐13)
vii. Cross‐laminated timber: compliant in accordance with Standard for Performance‐Rated
Cross‐Laminated Timber (PRG 320‐15)
viii. Finger‐jointed lumber labeled “Heat Resistant Adhesive (HRA)” in accordance with the
American Softwood Lumber Standard (DOC PS‐20 2015)
e. A listing of flooring installed in the project. Include manufacturer’s documentation confirming that
the product has been tested and determined compliant in accordance with California Department
of Public Health (CDPH) Standard Method v1.2-2017, using the applicable exposure scenario.
f. A listing of ceiling products, including ceiling panels, ceiling tile, surface ceiling structures such as
gypsum or plaster, suspended systems, and glazed skylights, installed in the project. Include manufacturer’s documentation confirming that the product has been tested and determined
compliant in accordance with California Department of Public Health (CDPH) Standard Method
v1.2-2017, using the applicable exposure scenario.
g. A listing of insulation, including thermal and acoustic boards, batts, rolls, blankets, sound
attention fire blankets, foamed-in place, loose-fill, blown, and sprayed insulation, installed in the
project. Include manufacturer’s documentation confirming that the product has been tested and
determined compliant in accordance with California Department of Public Health (CDPH)
Standard Method v1.2-2017, using the applicable exposure scenario.
J. Indoor Environmental Quality Credit Construction IAQ Management Plan. Provide the following:
a. A copy of the project’s Indoor Air Quality Management Plan, highlighting the no-smoking policy
b. Confirm if the permanently installed air handling equipment was used during construction.
c. Six photographs at each of three different times during the construction period to highlight the
implemented construction IAQ practices.
d. List all filtration media (manufacturer, model number, MERV rating, location of installed filter)
installed during construction and confirm that each unit was replaced prior to occupancy.
e. A narrative describing protection measures for absorbent materials
K. Indoor Air Quality Assessment: Provide the following:
a. A Flush-out Report documenting the required volume and duration of the flush-out and describing the project’s specific flush-out procedures, with product data for filtration media used
during flush-out and during occupancy.
OR
b. A copy of the Air Testing Report documenting the procedures for air testing, the locations, dates
and results of each test.
PART 2 PRODUCTS
2.1 SUSTAINABLE MATERIALS
A. Environmental Product Declarations: Provide at least 20 (after weighting) separate permanently installed
products from at least five different manufacturers that met one of the criteria below.
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
01 8113 Sustainable Design Requirements
10 of 18
a. Products with a publicly available, critically reviewed life-cycle assessment conforming to ISO
14044 that have at least a cradle to gate scope are valued as one whole product for the purposes
of credit achievement calculation.
b. Product-specific Type III EPD -- Internally Reviewed. Products with an internally critically
reviewed LCA in accordance with ISO 14071. Products with product-specific internal EPDs which
conform to ISO 14025, and EN 15804 or ISO 21930 and have at least a cradle to gate scope are
valued as one whole product for the purposes of credit achievement calculation.
c. Industry-wide Type III EPD -- Products with third-party certification (Type III), including external
verification, in which the manufacturer is explicitly recognized as a participant by the program
operator. Products with industry-wide EPDs, which conform to ISO 14025, and EN 15804 or ISO
21930 and have at least a cradle to gate scope are valued as one whole product for purposes of
credit achievement calculation.
d. Environmental Product Declarations which conform to ISO 14025 and EN 15804 or ISO 21930
and have at least a cradle to gate scope.
i. Product-specific Type III EPD -- Products with third-party certification (Type III), including
external verification and external critical review in which the manufacturer is explicitly
recognized as the participant by the program operator are valued as 1.5 products for the
purposes of credit achievement calculation.
B. Environmental Product Declarations - Multi-Attribute Optimization: Use products that comply with one of
the criteria below for 10%, by cost, of the total value of permanently installed products in the project, or
use at least 10 permanently installed products sourced from at least three different manufacturers.
Products will be valued as below.
a. Life Cycle Impact Reduction Action Plan (value at 50% by cost or ½ product)
i. The manufacturer has produced a product specific LCA using EN 15804 or ISO 21930 for
the product and has provided a publicly available action plan to mitigate or reduce life
cycle impacts. The action plan must be product-specific using the specified PCR
functional unit, be critically reviewed, and must include the following information:
1. Description of the LCA conducted including the dataset, software or platform
used by manufacturer to complete the analysis.
2. Identification of the largest life cycle impact areas identified in the analysis and a
narrative description of the impact areas targeted for reduction in the action plan.
3. Description of specific steps anticipated in implementation of the action plan.
Include proposed changes in formulation or manufacturing processes that are
planned as part of impact reduction strategy.
4. Specific dates and a full timeline for completion of all the steps described in the
action plan.
b. Life Cycle Impact Reductions in Embodied Carbon.
i. Products that have demonstrated environmental impact reductions for the specified
functional unit based on a current third-party EPD or verified LCA that conforms to the
comparability requirements of ISO 14025 and ISO 21930.
1. The comparative analysis must show impact reduction in the global warming
potential (GWP) impact category and must include a narrative describing how
reductions in impacts were achieved. The published comparisons must be third-
party verified (value at 100% by cost or 1 product).
2. The comparative analysis must show impact reduction(s) of at least 10% in the
global warming potential (GWP) impact category and must include a narrative
describing how the impact reductions were achieved. The published comparisons
must be third-party verified (value at 150% by cost or 1.5 products).
3. The comparative analysis must show impact reduction(s) of at least 20% in the
global warming potential (GWP) impact category, and demonstrate at least 5%
reduction in two additional impact categories. A narrative describing how the
impact reductions were achieved is required. The published comparisons must
be third-party verified (value at 200% by cost or 2 products).
c.
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
01 8113 Sustainable Design Requirements
11 of 18
C. Leadership extraction practices: Provide products which meet at least one of the responsible extraction
criteria below for at least 20%, by cost, of the total value of permanently installed building products in the
project. Products sourced (extracted, harvested, manufactured, and purchased) within 100 miles (160
km) of the project site are valued at 200% of their cost.
a. Bio-based materials. Bio-based products shall meet the Sustainable Agriculture Network’s
Sustainable Agriculture Standard. Bio-based raw materials shall be tested using ASTM Test
Method D6866 and be legally harvested, as defined by the exporting and receiving country.
Exclude hide products, such as leather and other animal skin material.
b. New wood products. Wood products shall be certified by the Forest Stewardship Council or
USGBC-approved equivalent.
c. Materials reuse. Reuse includes salvaged, refurbished, or reused products.
d. Recycled content. Recycled content is the sum of postconsumer recycled content plus one-half
the pre-consumer recycled content, based on cost.
e. Extended producer responsibility (ie Cradle to Cradle Certified Products) Products purchased
from a manufacturer (producer) that participates in an extended producer responsibility program
or is directly responsible for extended producer responsibility. Products meeting extended
producer responsibility criteria are valued at 50% of their cost for the purposes of credit
achievement calculation.
D. Heath Product Declarations: Provide at least 20 (after weighting) separate permanently installed products
from at least five different manufacturers that met one of the criteria below and demonstrate the chemical
inventory of the product to at least 0.1% (1000 ppm).
a. Manufacturer Inventory. The manufacturer has published complete content inventory for the
product following these guidelines:
i. A publicly available inventory of all ingredients identified by name and Chemical Abstract
Service Registration Number (CASRN) and/or European Community Number (EC
Number).
ii. Materials defined as trade secret or intellectual property may withhold the name and/or
CASRN/EC Number but must disclose ingredient/chemical role, amount and hazard
score/class using either:
1. Greenscreen List Translator (LT) score and/or Full GreenScreen Benchmark
(BM)
2. The Globally Harmonized System of Classification and Labeling of Chemicals
rev.6 (2015) (GHS)
a. The hazard screen must be applied to each trade secret ingredient and
the inventory lists the hazard category for each of the health hazards included in Part 3 of GHS (e.g. “GHS Category 2 Carcinogen”).
b. Health Product Declaration. The end use product has a published and complete Health Product
Declaration with full disclosure of known hazards in compliance with the Health Product
Declaration open Standard.
c. Cradle to Cradle. Product has Material Health Certificate or is Cradle to Cradle Certified™ under
standard version 3 or later with a Material Health achievement level at the Bronze level or higher.
d. Declare. The Declare product label meet the following requirements:
i. Declare labels designated as Red List Free or Declared.
ii. Declare labels designated as LBC Compliant that demonstrate content inventory to 0.1%
(1000 ppm).
e. ANSI/BIFMA e3 Furniture Sustainability Standard. The documentation from the assessor or
scorecard from BIFMA must demonstrate the product earned at least 3 points under 7.5.1.3
Advanced Level in e3-2014 or 3 points under 7.4.1.3 Advanced Level in e3-2012.
f. USGBC approved program. Other USGBC approved programs meeting the material ingredient
reporting criteria.
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
01 8113 Sustainable Design Requirements
12 of 18
E. Health Product Declaration - Material Ingredient Optimization: Use permanently installed products from at
least three different manufacturers that document their material ingredient optimization using the paths
below. Choose either 10 compliant products, or select products that constitute at least 10%, by cost, of
the total value of permanently installed products in the project.
a. Material Ingredient Screening and Optimization Action Plan (value at 50% by cost or ½ product)
i. The manufacturer has screened the product to at least 1,000 ppm and has provided a
publicly available inventory meeting the requirements of Option 1 and completed a
detailed action plan to mitigate or reduce known hazards using the principles of green
chemistry. The action plan must be product-specific (not company, manufacturer or
brand), and must include the following information:
1. Description of the screening or assessment platform used by manufacturer to
complete the material ingredient screening and analysis.
2. Identification of the specific green chemistry principles targeted for
implementation in the action plan.
3. Description of specific steps anticipated in implementation of the action plan.
Include proposed changes in formulation or manufacturing processes that are
planned as part of green chemistry optimization strategy.
4. Specific dates and a full timeline for completion of all the steps described in the
action plan.
b. Advanced Inventory & Assessment (value at 100% by cost or 1 product):
i. The end use product meets the requirements of any of the following:
1. Manufacturer Inventory or Health Product Declaration: The product has
demonstrated a chemical inventory to at least 0.01% by weight (100 ppm) with
no GreenScreen LT-1 hazards or GHS Category 1 hazards. The HPD or
Manufacturer Inventory must be third party verified.
2. Manufacturer Inventory or HPD: The product has demonstrated a chemical
inventory to at least 0.01% by weight (100ppm) and at least 75% by weight of
product is assessed using GreenScreen Benchmark assessment. The remaining
25% by weight of product has been inventoried. The GreenScreen assessment
must be publicly available. The HPD or Manufacturer Inventory must be third-
party verified.
3. Declare labels designated as Red List Free that are third-party verified.
4. Cradle to Cradle. Product has Material Health Certificate or is Cradle to Cradle
Certified™ under standard version 3 or later with a Material Health achievement
level at the Bronze level or higher.
c. Material Ingredient Optimization (value at 150% by cost or 1.5 products)
i. The end use product has demonstrated a product inventory and assessment of
ingredients using any of the following programs:
ii. Manufacturer Inventory or HPD: The product has demonstrated a chemical inventory to
at least 0.01% by weight (100ppm) and at least 95% by weight of product is assessed
using GreenScreen Benchmark assessment. No Benchmark 1 hazards (BM-1) are
present in the end use product. The remaining 5% by weight of product not assessed has
been inventoried and screened using GreenScreen List Translator and no GreenScreen
LT-1 hazards are present in the end use product. The documents must be third party
verified.
iii. Cradle to Cradle. Product has Material Health Certificate or is Cradle to Cradle Certified™ under standard version 3 or later with a Material Health achievement level at
the Silver level or higher.
d. USGBC approved program.
i. Products that comply with USGBC approved building product optimization criteria for
material ingredient optimization and/or advanced inventory & assessment pathways.
ii. For credit achievement calculation, products sourced (extracted, manufactured,
purchased) within 100 miles (160 km) of the project site are valued at twice their base
contributing cost (or number of products), up to a maximum of 200% of cost, or 2
products.
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
01 8113 Sustainable Design Requirements
13 of 18
2.2 LOW-EMITTING MATERIALS
Building products shall be in accordance with California Department of Public Health (CDPH) Standard
Method v1.2–2017, and comply with the VOC limits in Table 4-1 of the method. Additionally, the range of
total VOCs after 14 days (336 hours) was measured as specified in the CDPH Standard Method v1.2 and
is reported (TVOC ranges: 0.5 mg/m3 or less, between 0.5 and 5 mg/m3, or 5 mg/m3 or more).
Laboratories that conduct the tests must be accredited under ISO/IEC 17025 for the test methods they
use. Products used in school classrooms must be evaluated using the classroom scenario, products
used in other spaces must be evaluated using the default private office scenario
A. All paints and coatings wet-applied on site shall meet the applicable VOC limits of the California Air
Resources Board (CARB) 2007, Suggested Control Measure (SCM) for Architectural Coatings, or the
South Coast Air Quality Management District (SCAQMD) Rule 1113, effective February 5, 2016.
i. Interior Flat Coating or Primer – 50 g/L
ii. Interior Non-Flat Coating or Primer – 50 g/L
iii. Anti-corrosive/Anti-rust coating – 100 g/L
iv. Primers/Sealers/ and Undercoaters – 100 g/L
v. Clear Wood Finish: Lacquer- 275 g/L
vi. Clear Wood Finish: Sanding Sealer -275 g/L
vii. Clear Wood Finish: Varnish – 275 g/L
viii. Clear Wood Finish: Brushing Lacquer- 275 g/L
ix. Floor Coatings – 50 g/L
x. Fire Protective Coatings – 150 g/L
xi. Sealers and Under coaters – 100 g/L
xii. Shellac: Clear – 730 g/L
xiii. Shellac: Pigmented – 550 g/L
xiv. Stain: 100 g/L
xv. Concrete Curing Compounds: 100 g/L
xvi. Japans/Faux Finishing Coatings: 350 g/L
xvii. Magnesite Cement Coatings: 450 g/L
xviii. Waterproofing Sealers – 100 g/L
xix. Waterproofing Concrete/Masonry Sealers – 100 g/L
xx. Wood Preservatives – 350 g/L
xxi. Low-Solids Coatings – 120 g/L
xxii. Colorant – Architectural coatings – 50 g/L
B. All adhesives and sealants wet-applied on site shall meet the applicable chemical content requirements of
SCAQMD Rule 1168, October 6, 2017, Adhesive and Sealant Applications, as analyzed by the methods
specified in Rule 1168. The provisions of SCAQMD Rule 1168 do not apply to adhesives and sealants
subject to state or federal consumer product VOC regulations.
i. Indoor Carpet Adhesives - 50 g/L
ii. Carpet Pad Adhesives - 50 g/L
iii. Wood Flooring Adhesive – 100 g/L
iv. Rubber Floor Adhesives - 60 g/L
v. Sub floor Adhesives - 50 g/L
vi. Ceramic Tile Adhesives - 65 g/L
vii. VCT and Asphalt Tile Adhesives - 50 g/L
viii. Dry Wall and Panel Adhesives - 50 g/L
ix. Cove Base Adhesives - 50 g/L
x. Multipurpose Construction Adhesives - 70 g/L
xi. Structural Glazing Adhesives - 100 g/L
xii. PVC Welding - 510 g/L
xiii. CPVC Welding - 490 g/L
xiv. ABS Welding – 325 g/L
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
01 8113 Sustainable Design Requirements
14 of 18
xv. Plastic Cement Welding - 250 g/L
xvi. Adhesive Primer for Plastic - 550 g/L
xvii. Contact Adhesive - 80 g/L
xviii. Special Purpose Contact Adhesive - 250 g/L
xix. Structural Wood Member Adhesive - 140 g/L
xx. Top and Trim Adhesive - 250 g/L
xxi. Metal to Metal - 30 g/L
xxii. Plastic Foams substrate specific - 50 g/L
xxiii. Porous Material (except wood) substrate specific - 50 g/L
xxiv. Wood substrate specific - 30 g/L
xxv. Fiberglass substrate specific - 80 g/L
xxvi. Architectural Sealant - 250 g/L
xxvii. Roadway Sealant - 250 g/L
xxviii. Other Sealant - 420 g/L
xxix. Architectural, Non-Porous – Sealant Primer – 250 g/L
xxx. Architectural, Non-Porous– Sealant Primer – 775 g/L
xxxi. Other– Sealant Primer 750 g/L
C. If the applicable regulation requires subtraction of exempt compounds, any content of intentionally added
exempt compounds larger than 1% weight by mass (total exempt compounds) shall be disclosed.
D. Methylene chloride and perchloroethylene shall not be intentionally added in paints, coatings, adhesives,
or sealants.
E. Composite Wood Evaluation. Product meets one of the following:
a. EPA TSCA Title VI or California Air Resources Board (CARB) ATCM for formaldehyde
requirements for ultra-low-emitting formaldehyde (ULEF) resins or
b. EPA TSCA Title VI or CARB ATCM formaldehyde requirements for no added formaldehyde
resins (NAF).
c. Tested per EN 717-1:2014 for formaldehyde emissions and complies with emissions class E1.
d. Structural composite wood product made with moisture resistant adhesives meeting ASTM 2559,
no surface treatments with added urea-formaldehyde resins or coatings, and certified according
to one of the following industry standards:
i. Plywood: compliant in accordance with Voluntary Product Standard ‐ Structural Plywood
(PS 1‐09), Voluntary Product Standard – Performance Standard for Wood‐Based
Structural‐Use Panels (PS 2‐10), or one of the standards considered by CARB to be
equivalent to PS 1 or PS 2: (AS/NZS 2269, EN 636 3S (including CE label), Canadian
ii. Standards Association CSA O121 for Douglas fir plywood, CSA O151 for Canadian
softwood plywood, for CSA O153 Poplar plywood, or CSAO325 for Construction
sheathing)
iii. Oriented strand board: specified with the Exposure 1 or Exterior bond classification in
accordance with Voluntary Product Standard – Performance Standard for Wood‐Based
Structural‐Use Panels (PS 2‐10)
iv. Structural composite lumber: compliant in accordance with Standard Specification for
Evaluation of Structural Composite Lumber Products (ASTM D 5456‐13) o Glued
laminated timber: compliant in accordance with Structural Glued Laminated Timber (ANSI
A190.1‐2012)
v. ‐joists compliant in accordance with Standard Specification for Establishing and
Monitoring Structural Capacities of Prefabricated Wood I‐Joists (ASTM D 5055‐13)
vi. Cross‐laminated timber: compliant in accordance with Standard for Performance‐Rated
Cross‐Laminated Timber (PRG 320‐15)
vii. Finger‐jointed lumber labeled “Heat Resistant Adhesive (HRA)” in accordance with the
American Softwood Lumber Standard (DOC PS‐20 2015)
2.3 INDOOR AIR QUALITY
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
01 8113 Sustainable Design Requirements
15 of 18
A. Air filters treating outdoor air installed in the air handling unit shall have a MERV rating of 13 or higher.
2.4 WATER EFFICIENCY
A. Install only EPA WaterSense Labeled water closets, showerheads, and urinals. Refer to Section 220000
- Plumbing.
B. Install only ENERGY STAR clothes washers, dishwashers, and ice machines.
No equipment or appliances that reject heat may use once through cooling with potable water.
PART 3 EXECUTION
3.1 CONSTRUCTION ACTIVITY POLLUTION PREVENTION
A. SS prerequisite: Comply with Division 31 Section "Erosion and Sedimentation Control Plan"
3.2 CONSTRUCTION WASTE MANAGEMENT
A. MR prerequisite and MR credit: Comply with Division 1 Section "Construction Waste Management."
Divert at least 75% of construction and demolition waste from landfill from at least 4 material streams.
3.3 INDOOR AIR QUALITY CONSTRUCTION MANAGEMENT PLAN – DURING CONSTRUCTION
A. LEED IEQ credit Construction IAQ Management Plan: Comply with Division 1 Section “Indoor Air Quality Management”
B. During construction Trade Contractor shall meet or exceed the minimum requirements of the SMACNA
IAQ Guideline for Occupied Buildings under Construction, 2nd Edition, 2007, ANSI/SMACNA 008-2008
(Chapter 3).
C. Temporary Construction Ventilation: Prime Trade Contractor shall Maintain sufficient temporary
ventilation of areas where materials are being used that emit VOC’s, and maintain ventilation
continuously during installation, and until emissions dissipate after installation. If continuous ventilation is not possible via the building’s HVAC system(s) then ventilation shall be supplied via open windows and
temporary fans, sufficient to provide no less than three air changes per hour. Prime Trade Contractor
shall ensure that:
a. The period after installation shall be sufficient to dissipate odors and elevated concentrations of
VOCs. Where no specific period is stated in these Specifications, a time period of 72 hours shall
be used.
b. All areas shall be vented directly to outside. Areas shall not be vented to other enclosed areas.
D. During dust producing activities (e.g. drywall installation and finishing) ventilation system shall be off, and
openings in supply and return HVAC system shall be protected from dust infiltration. Provide temporary
ventilation as required.
E. Preconditioning: Prior to installation, Prime Trade Contractor shall allow products which have odors and
VOC emissions to off-gas in dry, well-ventilated space outside of building for 14 calendar days, in order to
allow for reasonable dissipation of odors and emissions.
F. Prime Trade Contractor shall complete all interior finish material installation prior to Substantial Completion to allow time for building flush out as described below. Submit notification to Owner’s
Representative when all interior finish material installation is complete, highlighting the date of
completion.
3.4 INDOOR AIR QUALITY CONSTRUCTION MANAGEMENT PLAN – POST CONSTRUCTION
A. Building Flush Out: Select one of the following two options (prior to occupancy or during occupancy), to
be implemented after construction ends and the building been completely cleaned. All interior finishes,
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
01 8113 Sustainable Design Requirements
16 of 18
such as millwork, doors, paint, carpet, acoustic tiles, and movable furnishing, must be installed, and major
VOC punch list items must be finished.
a. Prior to Building Occupancy: Prime Trade Contractor shall install new filtration media and
perform a building flush-out by supplying a total air volume of 14,000 cubic feet f outdoor air
per square foot of gross floor area while maintaining an internal temperature of at least 60ºF
(15ºC) and no higher than 80ºF (27ºC) and relative humidity no higher than 60%. The
duration of the flush-out must be calculated as follows:
Cubic feet of outdoor air needed prior to occupancy = Area (ft2) X 14,000 cfm
Duration (Days) = Cubic Feet needed/(air handler capacity/1440 minutes/day)
i. Replace all outside air filtration media prior to occupancy. Filtration media shall have
a MERV of 13 as determined by ASHRAE 52.2.
b. During Occupancy: if occupancy is desired before the flush-out is completed, the space may
be occupied only after delivery of a minimum of 3,500 cubic feet of outdoor air per square
foot of gross floor area while maintaining an internal temperature of at least 60ºF (15ºC) and
no higher than 80ºF (27ºC) and relative humidity no higher than 60%.
Once the space is occupied, it must be ventilated at a minimum rate of 0.30 cubic foot per
minute (CFM) per square foot of outdoor air or the design minimum outdoor air rate
determined by the ASHRAE 62.1-2010 calculations determined in IEQ Prerequisite Minimum
indoor Air Quality performance, whichever is greater. During each day of the flush-out period,
ventilation must begin at least three hours before occupancy and continue during occupancy.
These conditions must be maintained until a total of 14,000 cubic feet per square foot of
outdoor air has been delivered to the space. The duration of the flush-out must be calculated
as follows:
Cubic feet of outdoor air needed prior to occupancy = Area (ft2) X 3,500 cfm
Cubic feet of outdoor air needed during occupancy = Area (ft2) X 10,500 cfm
Duration (Days) = (Area (ft2) X 14,00 cfm)/(air handler capacity/1440 minutes/day)
B. IAQ Testing: After construction ends and before occupancy, but under ventilation conditions typical for
occupancy, conduct IAQ testing using protocols consistent with the methods in the table below for all
occupied spaces.
a. Use current versions of ASTM standard methods, EPA compendium methods, or ISO
methods, as indicated.
b. Conduct all measurements before occupancy during normal occupied hours, with the building
ventilation system started at the normal daily start time and operated at the minimum outdoor
airflow rate for the occupied mode throughout the test.
c. For each sampling point where the concentrations exceed the limit, take corrective action
and retest for the noncompliant contaminants ate the same sample points. Repeat until all
requirements are met.
Test for the particulate matter (PM) and inorganic gases listed in Table 1, using an allowed test method,
and demonstrate the contaminants do not exceed the concentration limits listed in the table.
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
01 8113 Sustainable Design Requirements
17 of 18
Table 1.
Contaminant (CAS#) Concentration Limit (µg/m3) Allowed Test Methods
Carbon monoxide (CO) 9 ppm; no more than 2 ppm
above outdoor levels
ISO 4224
EPA Compendium Method IP-3
GB/T 18883-2002 for projects in
China
Direct calibrated electrochemical
instrument with
accuracy of (+/- 2% ppm <50 ppm
minimum accuracy).
PM 10 ISO 14644-1:2015,
cleanroom class of 8 or lower 50 μg/m3 Healthcare only: 20 μg/m3
Particulate monitoring device with
accuracy greater of 5
micrograms/m3 or 20% of reading
and resolution (5 min
average data) +/- 5 µg/m
3
PM 2.5 12 μg/m3 or 35 µg/m3**
Ozone 0.07 ppm Monitoring device with accuracy
greater of 5 ppb or 20%
of reading and resolution (5 min
average data) +/- 5 ppb
ISO 13964
ASTM D5149 -– 02
EPA designated methods for Ozone
Perform a screening test for Total Volatile Organic Compounds (TVOC). Use ISO 16000-6, EPA TO-17,or EPA
TO-15 to collect and analyze the air sample. Calculate the TVOC value per EN 16516:2017, CDPH Standard
Method v1.2 2017 section 3.9.4, or alternative calculation method as long as full method description is included in
test report. If the TVOC levels exceed 500 µg/m3, investigate for potential issues by comparing the individual
VOC levels from the GC/MS results to associated cognizant authority health-basedlimits. Correct any identified
issues and re-test if necessary.
Additionally, test for the individual volatile organic compounds listed in Table 2 using an allowed test method and
demonstrate the contaminants do not exceed the concentration limits listed in the table.
Table 2.
Contaminant (CAS#) Concentration Limit (µg/m3) Allowed Test Methods
Formaldehyde 50-00-0 20 µg/m3 (16 ppb) ISO 16000-3, 4;
EPA TO-11a,
EPA comp. IP-6A
ASTM D5197-16
Acetaldehyde 75-07-0 140 µg/m3
Benzene 71-43-2 3 µg/m3 ISO 16000-6
EPA IP-1,
EPA TO-17,
EPA TO-15
ISO 16017-1, 2;
ASTM D6196-15
Hexane (n-) 110-54-3 7000 µg/m3
Naphthalene 91-20-3 9 µg/m3
Phenol 108-95-2 200 µg/m3
Styrene 100-42-5 900 µg/m3
Tetrachloroethylene 127-18-4 35 µg/m3
Toluene 108-88-3 300 µg/m3
Vinyl acetate 108-05-4 200 µg/m3
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
01 8113 Sustainable Design Requirements
18 of 18
Dichlorobenzene (1,4-) 106-46-7 800 µg/m3
Xylenes-total 108-38-3, 95-47-6,
and 106-42-3
700 µg/m3
3.5 COMMISSOINING
A. EA prerequisite and EA credit: Comply with Division 1 Section "General Commissioning Requirements"
LEED SCORECARD – follows
LEED SUBMITTAL COVER SHEET – follows
END OF SECTION
LEED v4 for BD+C: Schools Project Name: DYIMS
Project Checklist
Y ?+ ?- N
1 Credit 1 TT / PE / GGD
1 0 0 14 15 Role 8 0 3 2 13 Role
15 Credit 15 - Y Prereq Required TT / PE/PMA
1 Credit 1 - / - Y Prereq Required CM
2 Credit 2 - 3 2 Credit 5 TT / PE
5 Credit 5 - 1 1 Credit 2 CM / TT
4 Credit 4 - 1 1 Credit 2 CM / TT
1 Credit 1 - / - 1 1 Credit Building Product Disclosure and Optimization - Material Ingredients 2 CM / TT
1 Credit 1 - / - 2 Credit 2 CM / TT
1 Credit Green Vehicles 1 TR / PE
10 1 2 4 16 Role
3 0 0 9 12 Role Y Prereq Required GGD
Y Prereq Required CDW / CM Y Prereq Required TT / PMA
Y Prereq Required PMA / CDW Y Prereq Required CTA / PE
1 Credit 1 CDW / TR / PE 2 Credit 2 GGD / PE
2 Credit 2 - / - 2 1 1 Credit 3 CM / TT
1 Credit 1 - / - 1 Credit 1 CM / PMA
3 Credit 3 - / - 2 Credit 2 CM / PMA
2 Credit 2 - / - 1 Credit 1 GGD
1 Credit 1 GGD / TT 1 1 Credit 2 TT / GGD / PE
1 Credit 1 - 1 2 Credit 3 PE / TT
1 Credit Joint Use of Facilities 1 PE / PMA 1 Credit 1 TT / PE
1 Credit 1 CTA
8 0 0 4 12 Role
Y Prereq Required TR / CDW / TR 6 0 0 0 6 Role
Y Prereq Required TT / VAV / CMA 1 Credit 1 PE / TT
Y Prereq Building-Level Water Metering Required TT / VAV 1 Credit 1 PE / TT
2 Credit 2 TR / CDW 1 Credit 1 GGD / TT
3 4 Credit 7 TT / VAV / CMA 1 Credit 1 PE / TT
2 Credit 2 - 1 Credit 1 PE / TT
1 Credit Water Metering 1 GGD / TT 1 Credit 1 TT
24 3 5 0 31 Role 3 0 0 3 4 Role
Y Prereq Required SMMA / PMA 1 Credit Regional Priority: Renewable Energy Production (2 pt threshold) 1 TT / GGD
Y Prereq Required TT / - 1 Credit Regional Priority: Optimize Energy Performance (8 pt threshold) 1 TT / GGD
Y Prereq Required PMA / GGD / TT 1 Credit Regional Priority: Building Life-Cycle Impact Reduction (2 pt threshold) 1 TT / PE
Y Prereq Required GGD 1 Credit Regional Priority: Open Space (1 pt threshold)1 TT / CDW
5 1 Credit 6 SMMA / RJK / PMA / GGD 1 Credit Regional Priority: Outdoor Water Use Reduction (2 pt threshold) 1 TR / CDW
14 2 Credit 16 TT / GGD 1 Credit Regional Priority: Indoor Water Use Reduction (4 pt threshold) 1 TT / GGD
1 Credit 1 GGD / TT
2 Credit 2 PMA / GGD / TT 63 5 10 36 TOTALS Possible Points: 110
4 Credit 0 - / -Certified: 40 to 49 points, Silver: 50 to 59 points, Gold: 60 to 79 points, Platinum: 80 to 110
1 Credit 1 GGD
2 Credit 5 TT / PMA
Construction and Demolition Waste Management Planning
Building Product Disclosure and Optimization - Sourcing of Raw Materials
Minimum Indoor Air Quality Performance
Indoor Environmental Quality
Building Product Disclosure and Optimization - Environmental ProductDeclarations
Building Life-Cycle Impact Reduction
Enhanced Indoor Air Quality Strategies
Minimum Acoustic Performance
Environmental Tobacco Smoke Control
Date: Nov 18, 2020
Site Master Plan
Site Development - Protect or Restore Habitat
Construction Indoor Air Quality Management Plan
Storage and Collection of Recyclables
Location and Transportation
Construction and Demolition Waste Management
Access to Quality Transit
Reduced Parking Footprint
Environmental Site Assessment
Site Assessment
Construction Activity Pollution Prevention
Light Pollution Reduction
LEED for Neighborhood Development Location
Materials and Resources
Demand Response
Renewable Energy Production
Heat Island Reduction
Regional Priority
ID Credit 1.2: Innovation in Design: Pilot Credit for Design with Nature
ID Credit 1.3: Innovation in Design: Low Mercury Lighting
ID Credit 1.4: Innovation in Design: Green Building Education
ID Credit 1.5: Innovation in Design: WELL Features: Beauty and Design I (celebration of culture, spirit, place, art)
Indoor Air Quality Assessment
LEED Accredited Professional
Low-Emitting Materials
Thermal Comfort
ID Credit 1.1: School as a teaching tool
Water Efficiency
Advanced Energy Metering
Minimum Energy Performance
Optimize Energy Performance
Fundamental Refrigerant Management
Enhanced Commissioning
Indoor Water Use Reduction
Building-Level Energy Metering
Green Power and Carbon Offsets
Integrative Process
Indoor Water Use Reduction
Energy and Atmosphere
Fundamental Commissioning and Verification
Sensitive Land Protection
Open Space
Outdoor Water Use Reduction
Cooling Tower Water Use
High Priority Site
Surrounding Density and Diverse Uses
Outdoor Water Use Reduction
Bicycle Facilities
Sustainable Sites
Rainwater Management
Enhanced Refrigerant Management
Quality Views
Daylight
Acoustic Performance
Interior Lighting
Innovation
PRODUCT DATA REPORTING FORM for LEED v4 Projects
THIS FORM IS REQUIRED TO BE SUBMITTED WITH Product Data Submittals
You must include backup documentation such as SPECIFIC Product Data Sheets, Cut Sheets, Product Specific Letter from Manufacturer, etc. DO NOT INCLUDE GENERIC MARKETING MATERIAL
LEED PROJECT NAME:
SUBCONTRACTOR:
Specification Section: Submittal Number:
Product Manufacturer
Product Costs1
(only exclude
install labor)
($)
Product Specific (PS)
or Industry Wide (IW)
Env. Product
Declaration (EPD)3?
FSC Certified7
Wood
Products?
(%)
Post-Consumer
Recycled
Content8
(%)
Pre-Consumer
Recycled
Content9
(%)
Extended
Producer
Responsibility5
Program Name?
Delclare Label
with ingredient
disclosure
greater than 1000
ppm?
Fully Declared
HPD to 1000
ppm
Declaration4
included?
C2C version
(2.1.1 or 3.0)
Level of
Certification
Extracted,
Manufactured,
& Purchased
within2 100
miles?
CDPH
Emissions10
testing
compliant?
VOC
Content11
(g/L)
Wet-Applied
Products
Volume Used
(L)
Wood
Products
are low
emitting12?
Ex. ABC Product ABC. Inc. $ XX,XXX PS / IW % % % Yes / No Yes / No Yes / No Yes / No Yes / No Yes / No ## ## Yes / No
1
2
3
4
5
6
7
8
9
NOTES / DEFINITIONS:
1. Furnish Costs include all expenses to deliver the material to the project site, including taxes, transport, fabrication and profit. Do not include site labor or installation.
2. Within 100 miles distance is defined as travel by air to the project site, not travel distance by road.
3. Environmental Product Declarations which conform to ISO 14025, 14040, 14044, and EN 15804 or ISO 21930 and have at least a cradle to gate scope.http://productguide.ulenvironment.com/QuickSearch.aspx
4. The end use product has a published, complete Health Product Declaration with full disclosure of known hazards in compliance with the Health Product Declaration open Standard.
5. Extended producer responsibility. Products purchased from a manufacturer (producer) that participates in an extended producer responsibility program or is directly responsible for extended producer responsibility. (e.g. Closed Loop or Take Back Program)
http://info.fsc.org/certificate.php
8. Post-Consumer Recycled Content: Sourced from recovered Consumer Waste and used as a raw material (e.g. plastic bottles, newspaper, etc).
10. TVOC Emissions for Building products must be tested and determined compliant in accordance with California Department of Public Health (CDPH) Standard Method v1.2–2017 http://www.usgbc.org/resources/low-emitting-materials-third-party-certification-table
EMAIL CONTACT FOR AUTHORIZED REPRESENTATIVE: _____________________________________________ Direct Phone: ____________________
SIGNATURE OF AUTHORIZED REPRESENTATIVE: ___________________________________________________ DATE: ________________________
12. Composite Wood Evaluation as defined by the California Air Resources Board (CARB), Airborne Toxic Measure to Reduce Formaldehyde Emissions from Composite Wood Products Regulation, must be documented to have low formaldehyde emissions that meet the CARB ATCM for formaldehyde
requirements for ultra-low-emitting formaldehyde (ULEF) resins or no added formaldehyde (NAUF) resins. In additional structural composite wood shall meet requirements listed in specifications.
I, __________________________________________ a duly authorized representative of_____________________________________________ hereby certify that the material information submitted here is an accurate representation of the
material to be provided under our contract.
Low-Emitting Materials LEED Credits (See note 13)
http://www.distancefromto.net/
Project Product Data Materials and Resources LEED Credits
11. All paints and coatings wet-applied on site must meet applicable VOC limits of the California Air Resources Board (CARB) 2007, Suggested Control Measure (SCM) for Architectural Coatings, or the South Coast Air Quality Management District (SCAQMD) Rule 1113, effective June 3, 2011. All
adhesives and sealants wet-applied on site must meet the applicable chemical content requirements of SCAQMD Rule 1168, October 6, 2017, Adhesive and Sealant Applications, as analyzed by the methods specified in Rule 1168.
9. Pre-Consumer Recycled Content: Recovered Industrial Materials diverted from municipal solid waste for use in a different mfg. process, prior to use by a consumer. Note: "home scrap" from the original mfg. process that are reused / reprocessed do not qualify.
Some Qualifying VOC Standards (More in Note 10):
CDPH Standard Method v1.1 or v1.2
FloorScore: Hard Surfaces & Adhesives
Green Label Plus: Carpet, Adhesive, Cushion
UL Greengaurd Gold: When Meeting CDPH Std. v1.1(2)
ONLY if
product
has FSC or
recycled
content,
then fill
Regional
Data
7. Wood products must be certified by the Forest Stewardship Council (FSC) and must be provide proof of vendor FSC Chain-of-Custody with this Product Data Submittal.
Invoices listing COC numbers are required.
13. CDPH (California Department of Public Health (CDPH) Standard Method v1.2–2017) is required for each of the following product categories at the following thresholds:Interior Paints & Coatings (75% by volume); Interior Adhesives & Sealants (75% by volume); Flooring (90% by area); Insulation
(75% by value); Ceilings (90% by area); and Composite Wood (75% by value or area.)
LEED v4 for BD+C: Schools Project Name: DYIMS
Project Checklist
Y ?+ ?- N
1 Credit 1 TT / PE / GGD
1 0 0 14 15 Role 8 0 3 2 13 Role
15 Credit 15 - Y Prereq Required TT / PE/PMA
1 Credit 1 - / - Y Prereq Required CM
2 Credit 2 - 3 2 Credit 5 TT / PE
5 Credit 5 - 1 1 Credit 2 CM / TT
4 Credit 4 - 1 1 Credit 2 CM / TT
1 Credit 1 - / - 1 1 Credit Building Product Disclosure and Optimization - Material Ingredients 2 CM / TT
1 Credit 1 - / - 2 Credit 2 CM / TT
1 Credit Green Vehicles 1 TR / PE
10 1 2 4 16 Role
3 0 0 9 12 Role Y Prereq Required GGD
Y Prereq Required CDW / CM Y Prereq Required TT / PMA
Y Prereq Required PMA / CDW Y Prereq Required CTA / PE
1 Credit 1 CDW / TR / PE 2 Credit 2 GGD / PE
2 Credit 2 - / - 2 1 1 Credit 3 CM / TT
1 Credit 1 - / - 1 Credit 1 CM / PMA
3 Credit 3 - / - 2 Credit 2 CM / PMA
2 Credit 2 - / - 1 Credit 1 GGD
1 Credit 1 GGD / TT 1 1 Credit 2 TT / GGD / PE
1 Credit 1 - 1 2 Credit 3 PE / TT
1 Credit Joint Use of Facilities 1 PE / PMA 1 Credit 1 TT / PE
1 Credit 1 CTA
8 0 0 4 12 Role
Y Prereq Required TR / CDW / TR 6 0 0 0 6 Role
Y Prereq Required TT / VAV / CMA 1 Credit 1 PE / TT
Y Prereq Building-Level Water Metering Required TT / VAV 1 Credit 1 PE / TT
2 Credit 2 TR / CDW 1 Credit 1 GGD / TT
3 4 Credit 7 TT / VAV / CMA 1 Credit 1 PE / TT
2 Credit 2 - 1 Credit 1 PE / TT
1 Credit Water Metering 1 GGD / TT 1 Credit 1 TT
24 3 5 0 31 Role 3 0 0 3 4 Role
Y Prereq Required SMMA / PMA 1 Credit Regional Priority: Renewable Energy Production (2 pt threshold) 1 TT / GGD
Y Prereq Required TT / - 1 Credit Regional Priority: Optimize Energy Performance (8 pt threshold) 1 TT / GGD
Y Prereq Required PMA / GGD / TT 1 Credit Regional Priority: Building Life-Cycle Impact Reduction (2 pt threshold) 1 TT / PE
Y Prereq Required GGD 1 Credit Regional Priority: Open Space (1 pt threshold)1 TT / CDW
5 1 Credit 6 SMMA / RJK / PMA / GGD 1 Credit Regional Priority: Outdoor Water Use Reduction (2 pt threshold) 1 TR / CDW
14 2 Credit 16 TT / GGD 1 Credit Regional Priority: Indoor Water Use Reduction (4 pt threshold) 1 TT / GGD
1 Credit 1 GGD / TT
2 Credit 2 PMA / GGD / TT 63 5 10 36 TOTALS Possible Points: 110
4 Credit 0 - / -Certified: 40 to 49 points, Silver: 50 to 59 points, Gold: 60 to 79 points, Platinum: 80 to 110
1 Credit 1 GGD
2 Credit 5 TT / PMA
Construction and Demolition Waste Management Planning
Building Product Disclosure and Optimization - Sourcing of Raw Materials
Minimum Indoor Air Quality Performance
Indoor Environmental Quality
Building Product Disclosure and Optimization - Environmental ProductDeclarations
Building Life-Cycle Impact Reduction
Enhanced Indoor Air Quality Strategies
Minimum Acoustic Performance
Environmental Tobacco Smoke Control
Date: Nov 18, 2020
Site Master Plan
Site Development - Protect or Restore Habitat
Construction Indoor Air Quality Management Plan
Storage and Collection of Recyclables
Location and Transportation
Construction and Demolition Waste Management
Access to Quality Transit
Reduced Parking Footprint
Environmental Site Assessment
Site Assessment
Construction Activity Pollution Prevention
Light Pollution Reduction
LEED for Neighborhood Development Location
Materials and Resources
Demand Response
Renewable Energy Production
Heat Island Reduction
Regional Priority
ID Credit 1.2: Innovation in Design: Pilot Credit for Design with Nature
ID Credit 1.3: Innovation in Design: Low Mercury Lighting
ID Credit 1.4: Innovation in Design: Green Building Education
ID Credit 1.5: Innovation in Design: WELL Features: Beauty and Design I (celebration of culture, spirit, place, art)
Indoor Air Quality Assessment
LEED Accredited Professional
Low-Emitting Materials
Thermal Comfort
ID Credit 1.1: School as a teaching tool
Water Efficiency
Advanced Energy Metering
Minimum Energy Performance
Optimize Energy Performance
Fundamental Refrigerant Management
Enhanced Commissioning
Indoor Water Use Reduction
Building-Level Energy Metering
Green Power and Carbon Offsets
Integrative Process
Indoor Water Use Reduction
Energy and Atmosphere
Fundamental Commissioning and Verification
Sensitive Land Protection
Open Space
Outdoor Water Use Reduction
Cooling Tower Water Use
High Priority Site
Surrounding Density and Diverse Uses
Outdoor Water Use Reduction
Bicycle Facilities
Sustainable Sites
Rainwater Management
Enhanced Refrigerant Management
Quality Views
Daylight
Acoustic Performance
Interior Lighting
Innovation