HomeMy WebLinkAbout07-0001-Waterproofing,-Dampproofing-and-Caulking-(FSB)_Rev_1Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
WATERPROOFING, DAMPPROOFING, AND CAULKING
07 0001 - 1
SECTION 07 0001
WATERPROOFING, DAMPPROOFING, AND CAULKING
(Filed Sub-Bid Required)
PART 1 - GENERAL
1.1 GENERAL PROVISIONS
A. Attention is directed to the General And Supplemental Conditions of the Contract and all
Sections within Division 1 - General Requirements which are hereby made a part of this Section
of the Specifications.
B. Time, Manner and Requirements for Submitting Sub-Bids:
1. Sub-bids for work under this Section shall be for the complete work and shall be filed in a
sealed envelope with the Awarding Authority at a time and place as stipulated in the
"Instructions to Bidders".
The following should appear on the upper left hand corner of the envelope:
NAME OF SUB-BIDDER: (Insert name of sub-bidder)
SUB-BID FOR SECTION: 07 0001 - WATERPROOFING, DAMPPROOFING AND
CAULKING
2. Each sub-bid submitted for work under this Section shall be on forms furnished by the
Awarding Authority as required by Section 44F of Chapter 149 of the General Laws, as
amended.
3. Sub-bids filed with the Awarding Authority shall be accompanied by BID BOND or CASH
or CERTIFIED CHECK or TREASURER'S CHECK or CASHIER'S CHECK issued by a
responsible bank or trust company payable to the Dennis-Yarmouth Regional School
District in the amount of five percent of the sub-bid. A sub-bid accompanied by any other
form of bid deposit than those specified will be rejected.
C. Sub Sub-Bid Requirements: (None required under this Section.)
D. Reference Drawings: The Work of this Filed Sub-Bid is shown on the following Contract
Drawings.
1. Site Drawings “C” and “L” Series
2. Architectural Drawings “A” Series
3. Structural Drawings “S” Series
4. Fire Protection Drawings “FP” Series
5. Plumbing Drawings “P” Series
6. Mechanical Drawings “M” Series
7. Electrical Drawings “E” Series
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
WATERPROOFING, DAMPPROOFING, AND CAULKING
07 0001 - 2
1.2 DESCRIPTION OF WORK
A. Work Included: Provide labor, materials and equipment necessary to complete the work of this
Section, including but not limited to the following:
1. All Work of Section 07 1113 “Bituminous Dampproofing.”
2. All Work of Section 07 1416 “Cold Fluid-Applied Waterproofing.”
3. All Work of Section 07 2715 “Non-Bituminous Self-Adhering Sheet Air Barriers.”
4. All Work of Section 07 2726 “Fluid-Applied Membrane Air Barriers.”
5. All Work of Section 07 9100 “Preformed Joint Seals.”
6. All Work of Section 07 9200 “Joint Sealants.”
7. All Work of Section 07 9219 “Acoustical Joint Sealants.”
END OF SECTION