HomeMy WebLinkAbout09-0005-Resilient-Floors-(FSB)_Rev_2Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011 Addendum No. 4, February 2322, 2021
Addendum No. 5, February 23, 2021
RESILIENT FLOORS
09 0005 - 1
SECTION 09 0005
RESILIENT FLOORS
(Filed Sub-Bid Required)
1.1 GENERAL PROVISIONS
A. Attention is directed to the General And Supplemental Conditions of the Contract and all
Sections within Division 1 - General Requirements which are hereby made a part of this Section
of the Specifications.
B. Time, Manner and Requirements for Submitting Sub-Bids:
2. Sub-bids for work under this Section shall be for the complete work and shall be filed in a
sealed envelope with the Awarding Authority at a time and place as stipulated in the
"Instructions to Bidders".
The following should appear on the upper left hand corner of the envelope:
NAME OF SUB-BIDDER: (Insert name of sub-bidder)
SUB-BID FOR SECTION: 09 0005 - RESILIENT FLOORS
3. Each sub-bid submitted for work under this Section shall be on forms furnished by the
Awarding Authority as required by Section 44F of Chapter 149 of the General Laws, as
amended.
4. Sub-bids filed with the Awarding Authority shall be accompanied by BID BOND or CASH
or CERTIFIED CHECK or TREASURER'S CHECK or CASHIER'S CHECK issued by a
responsible bank or trust company payable to the Dennis-Yarmouth Regional School
District in the amount of five percent of the sub-bid. A sub-bid accompanied by any other
form of bid deposit than those specified will be rejected.
C. Sub Sub-Bid Requirements: (None required under this Section.)
D. Reference Drawings: The Work of this Filed Sub-Bid is shown on the following Contract
Drawings.
2. Architectural Drawings “A” Series
1.2 DESCRIPTION OF WORK
1.3 DESCRIPTION OF WORK
A. Work Included: Provide labor, materials and equipment necessary to complete the work of this
Section, including but not limited to the following:
1. All Work of Section 03 5416 “Hydraulic Cement Underlayment” to the extent required
under 09 0561 for areas where resilient flooring trade contractor owns the flooring
2. Work of Section 09 0561 “Common Work Results for Flooring Preparation” where the
resilient flooring trade contractor owns the flooring.
3. All Work of Section 09 0561.13 “Moisture Vapor Emission Control” to the extent required
in 01_2200 Unit Prices
4. All Work of Section 09 6513 “Resilient Base And Accessories.
5. All Work of Section 09 6516 “Resilient Sheet Flooring.”
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011 Addendum No. 4, February 2322, 2021
Addendum No. 5, February 23, 2021
RESILIENT FLOORS
09 0005 - 2
6. All Work of Section 09 6543 “Linoleum Flooring.”
7. All Work of Section 09 6566 “Resilient Athletic Flooring.”
A.B. Alternates: None.
END OF SECTION