26 0800 Electrical Systems Commissioning
1 of 2
SECTION 26 08 00
ELECTRICAL SYSTEMS COMMISSIONING
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and General Provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section.
1.2 RELATED SECTIONS
A. Division 26 – Electrical
B. Section 019113 – General Commissioning Requirements
1.3 REQUIRMENTS
A. The Commissioning process requires the participation of Division 26, Electrical, to ensure
that all systems fulfill the functional and pre-functional requirements set forth in these
construction documents. The general commissioning requirements and coordination are
detailed in Section 019113. Division 26, Electrical, shall fulfill commissioning
responsibilities assigned to division 26 in accordance with Section 019113.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.1 PRE-FUNCTIONAL CHECKLISTS
A. Pre-functional checklists assist in the process to document that the equipment and systems
are installed properly.
1) The contractor will be provided with construction checklists from the CA for
completion. The contractor shall complete the checklists as provide the CA with
completed copies in accordance with 019113.
2) See attached for a sample pre-functional performance test checklist, attached is
included only to provide sample of a typical process and scope.
3.2 FUNCTIONAL PERFORMANCE TESTING
A. Intent of functional performance testing is to prove thru functional test procedures proper
system operation.
B. The contractor will be provided with functional performance test procedures to perform
while CA witnesses. The contractor shall perform functional tests in accordance with
019113.
C. See attached for a sample functional performance test checklist, attached is included only
to provide sample of a typical process and scope.
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
26 0800 Electrical Systems Commissioning
2 of 2
3.3 PREFUNCTIONAL CHECKLISTS AND FUNCTIONAL PREFORMANCE TESTING
A. Pre-Functional Checklists and Functional performance testing procedures will be
performed on the following system types. (Pre Functional and Functional performance
testing requirements are in addition to and do not replace any testing required elsewhere
in Division 26 or by applicable codes.) Equipment specifically marked as such below shall
be provided with start-up of equipment by factory-authorized service representative.
1. Emergency Generator and associated transfer panels (if applicable)-Provide with
factory authorized start-up.
2. Lighting Control Systems
3. Electrical Service and switchgear, transformers, motor control centers, distribution
systems, low voltage systems, grounding and bonding systems.
3.4 SAMPLE CHECKLISTS
A. See Attached.
End of Section
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
26 0800 Electrical Systems Commissioning
3 of 2
Contractor Checklist and Functional Test Procedures
Lighting Control Systems
Please refer to the Master Deficiency and Resolution Log for numbers referenced in parentheses, which
will indicate deficiencies discovered and resolved.
1. Participants
Discipline Name Company
CxA
Mechanical
Controls
TAB
Plumbing
Electrical
Date Returned to CxA
Check Description ☐ The above equipment and systems integral to them are complete and ready for functional testing.
☐ All control system functions for this and all interlocking systems are programmed and operable per
contract documents, including final setpoints and schedules with debugging, loop tuning and sensor
calibrations completed. ☐ Test and balance completed and approved for the hydronic systems and terminal units connected ☐ All A/E punchlist items for this equipment corrected. ☐ Safeties and operating ranges reviewed.
Schedules and reviewed
• This checklist does not take the place of the manufacturer’s recommended checkout and
startup procedures.
• Items that do not apply shall be noted with the reasons on this form (N/A = not applicable,
BO = by others).
• Contractor’s assigned responsibility for sections of the checklist shall be responsible to
see that checklist items by their subcontractors are completed and checked off.
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
26 0800 Electrical Systems Commissioning
4 of 2
3. Installation Checks
Check if Okay. Enter comment or note number if deficient.
Check Equip Tag Light-
ing
Comments
Lighting
Devices installed per manufacturer’s instructions and specifi-cations ☐
Lighting control system installed per plans, specifications and manufacturer’s recommendations ☐
Switches and occupancy sensors installed at correct height
and have correct cover / escutcheon plate ☐
The checklist items all successfully completed for given trade ☐YES ☐NO
4. Operational Checks
Check if Okay. Enter comment or note number if deficient.
Check Equip Tag Lighting Comments
Operational
Lights are all functioning. No bulbs are burned out ☐
Lights are not turning on and off frequently causing a disrup-
tions ☐
The checklist items all successfully completed for given trade ☐YES ☐NO
5. Functional Testing Record
Lighting Systems
The functional tests have all passed for given trade ☐YES ☐NO
Test# Mode ID Test Procedure Expected Response
Pas
s
Y/N
Not
e
1 Interior Lighting – Occupancy
Sensors
With the room unoccupied and the
lights off, enter the space
The occupancy sensor shall see
you and the lights shall energize
on. While in the space, the lights
shall not continually turn off and on.
2 Interior Lighting – Daylight Dim-
ming
With the room occupied, and the
lights on, shine a flashlight on the
photocell
The lights should dim as they
sense more light in the space.
3 Exterior Lights
On
Engage the time clock/photocell
function to simulate a need for the
exterior lighting. Cover the Photo-
cell to simulate darkness and over-
ride the time clock to simulate a
suitable time to be on
All exterior lights should energize
on including pole lights, wall packs etc.
4 Exterior Lights
Off
Set the time clock back to normal schedules and remove the cover-
ing from the photocell
All exterior lights should turn off in-
cluding pole lights, wall packs, etc.
5 Stage / Theatri-cal Lighting
Try out all functions of the theatri-
cal lighting to ensure that it is
working per specification
System should operate the theatri-
cal lighting as setup in accordance
with the owners request