28 0800 Electronic Safety and Security Systems Commissioning
1 of 2
SECTION 28 08 00
ELECTRONIC SAFETY AND SECURITY SYSTEMS COMMISSIONING
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and General Provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section.
1.2 RELATED SECTIONS
A. Division 23 – Heating, Ventilating and Air Conditioning
B. Division 28 - Electronic Safety and Security Systems
C. Section 019113 - General Commissioning Requirements
1.3 REQUIRMENTS
A. The Commissioning process requires the participation of Division 28, Electronic Safety and
Security, to ensure that all systems fulfill the functional and pre-functional requirements set forth
in these construction documents. The general commissioning requirements and coordination
are detailed in Section 019113. Division 28, Electronic Safety and Security, shall fulfill
commissioning responsibilities assigned to division 28 in accordance with Section 019113.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.1 PRE-FUNCTIONAL CHECKLISTS
A. Pre-functional checklists assist in the process to document that the equipment and systems are
installed properly.
a. The contractor will be provided with construction checklists from the CA for completion. The
contractor shall complete the checklists as provide the CA with completed copies in accordance
with 019113.
b. See attached for a sample pre-functional performance test checklist, attached is included only
to provide sample of a typical process and scope.
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
28 0800 Electronic Safety and Security Systems Commissioning
2 of 2
3.2 FUNCTIONAL PERFORMANCE TESTING
A. Intent of functional performance testing is to prove thru functional test procedures proper
system operation.
B. The contractor will be provided with functional performance test procedures to perform while CA
witnesses. The contractor shall perform functional tests in accordance with 019113.
C. See attached for a sample functional performance test checklist, attached is included only to
provide sample of a typical process and scope.
3.3 PREFUNCTIONAL CHECKLISTS AND FUNCTIONAL PREFORMANCE TESTING
A. Pre-Functional Checklists and Functional performance testing procedures will be
performed on the following system types. (Pre Functional and Functional performance
testing requirements are in addition to and do not replace any testing required
elsewhere in Division 28 or by applicable codes.) Equipment specifically marked as
such below shall be provided with start-up of equipment by factory-authorized service
representative.
1. Fire Alarm Systems
2. Security Systems including review of Card Readers, In
3. Video Surveillance Systems
3.4 SAMPLE CHECKLISTS
A. See Attached.
End of Section
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
28 0800 Electronic Safety and Security Systems Commissioning
3 of 2
Contractor Checklist and Functional Test Procedures
SECURITY SYSTEM - Access Control and Video Surveillance
Please refer to the Master Deficiency and Resolution Log for numbers referenced in parenthe-
ses, which will indicate deficiencies discovered and resolved.
1. Participants
Discipline Name Company
CxA
Mechanical
Controls
TAB
Plumbing
Electrical
Date Returned to CxA
2. Prerequisite Checklist
Check Description
☐ The above equipment and systems integral to them are complete and ready for functional
testing.
☐ All control system functions for this and all interlocking systems are programmed and oper-
able per contract documents, including final setpoints and schedules with debugging, loop
tuning and sensor calibrations completed.
☐ Test and balance completed and approved for the hydronic systems and terminal units
connected
☐ All A/E punchlist items for this equipment corrected.
☐ Safeties and operating ranges reviewed.
Schedules and reviewed
• This checklist does not take the place of the manufacturer’s recommended
checkout and startup procedures.
• Items that do not apply shall be noted with the reasons on this form (N/A = not
applicable, BO = by others).
• Contractor’s assigned responsibility for sections of the checklist shall be respon-
sible to see that checklist items by their subcontractors are completed and
checked off.
Dennis Yarmouth Intermediate Middle School January 19, 2021
Dennis Yarmouth Regional School District 100% Construction Documents
Perkins Eastman DPC, project #71011
28 0800 Electronic Safety and Security Systems Commissioning
4 of 2
3. Installation Checks
Check if Okay. Enter comment or note number if deficient.
Check Equip Tag-> Comments
General Installation
Surfaces, coatings, finishes and equipment is without damage ☐
All wiring fastened and tied in an approved workmanship manner ☐
All material and equipment new and unused
Entry Access Control System:
3 x 5 Color Video Sentry Tilt System installed ☐
Color Monitor is operational ☐
Audio operational ☐
The checklist items all successfully completed for given trade ☐YES ☐NO
4. Functional Testing Record
Test # Mode ID Test Procedure Expected Response Pass
Y/N Note
1
Color Video Sen-
try Tilt System –
Door Intercom
With one person outside (at the entry door) and one person inside at the
reception area, have the person out-
side push the call button
The incoming call will sound
chime at the reception area. The
person inside will pick up to an-
swer and the visitor will speak
hands free. The person inside
will see the person via the cam-era. The person inside will press
the door release button which
will allow the visitor to enter.
2 Video Surveil-
lance
At the head end station, ensure that
the dome cameras are accurately
displaying the area that they are monitoring
The display at the head end should continuously show accu-
rate information of what is being
monitored and also will record the monitored area.
3 Card Readers Using a staff members HID card, pass
the card over the HID Card Reader
The card shall be accurately
read and access will be allowed.
The functional tests have all passed for given trade ☐YES ☐NO