HomeMy WebLinkAboutDYIMS PE Site report 20210722
Architect: Perkins Eastman DPC
Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File
ARCHITECT’S SITE OBSERVATION REPORT
DATE OF VISIT: 07/22/2021 PROJECT: Dennis Yarmouth Intermediate
Middle School
286 Station Avenue
South Yarmouth, MA 02664
DATE OF ISSUE: 07/23/2021 PROJECT NO: 71011
WEATHER
CONDITIONS:
SUNNY, 70s ARCHITECT: Perkins Eastman, DPC
20 Ashburton Street
8th floor
Boston, MA
The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit.
WORK IN PROGRESS:
1) Ongoing work on installation of vibratory stone columns
2) Excavation for sanitary manholes
3) Excavation and subgrade prep for foundation walls and piers at Area C
4) Preparing forms and setting rebar for footings, walls, and piers at Area D
5) Ongoing layout work by survey crew on layout
6) Road grading and general site prep at parking area
7) Topsoil Stripping at future Station Avenue soccer field
FIELD OBSERVATIONS:
PE visited the site to review ongoing progress with the site work and foundations.
1) RBO was in the process of excavation for grease trap and manhole for sanitary line east of column line
2) CNC was in the process of installing VSCs at the east side of Area B, with the intention of finishing all but the last
300 or so during this week.
3) RBO has prepared the footing line along column lines C1/C2 as well as along column line E, where footing
formwork has been started.
4) At various times on Thursday RBO was excavating and preparing the subgrade and base for the footing line
along column line H (south side of area C), as well as interior footings at Area C, and commencing work at the
west link connecting from C back toward Area B.
5) Marguerite is installing rebar along line D and at adjacent interior piers for a pier and wall pour scheduled for next
week, as well as setting forms and rebar for footings along column line E (at north side of area C) as well as
interior footings in area C.
6) Marguerite was also stripping wall forms from the walls placed on 7-19 on the north east side of Area D. All of
the interior column footings for Area D have been either been placed or are formed and prepared for placement.
According to Ryan DiRico of Commodore, the plan is to complete foundations for Area D at the end of the month.
7) RBO has infilled at UGI-1 at the main parking area and is working on sugrade. Infill is also complete at UGI 6 and
UGI 7. (see photo)
8) Commodore said that they are in the process of installing controls for anchor bolts at each pier in Area D
9) Brennan’s survey crew was onsite doing ongoing work on layout for VSCs and foundation walls/footings.
10) Commodore stated that next Friday they are planning on having some trees removed as necessitated by the
correction of the limit of work fence along the west edge of the site. PE asked Commodore to preserve if possible
the substantial oak tree that is immediately behind the abutting property at 19 Heywood Avenue.
REPORT BY: ABH Page 2 of 3
PROGRESS PHOTOS
EXCAVATION FOR GREASE TRAP AND MANHOLES INFILL AND GRADING ABOVE UGI NO. 1
STRIPPING FOUNDATION WALLS PLACED ON 7-19 TYING REBAR FOR WALL / PIER PLACEMENT ON LINE D
FOOTING FORMS ON COLUMN LINE E (AREA C NORTH) PLACED FOOTINGS AND FORMS AT D-C ‘LINK’
REPORT BY: ABH Page 3 of 3
TYING PIER REBAR INTERIOR FOOTINGS ON LINE B (AREA D NE)
FORMWORK FOR WALL PLACEMENT ON LINES D.2/D.1
FOOTING FORMS AND REBAR AT D/D12
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/15/21, Partly Cloudy – Low 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
This Report is a summary installation list of installed vibratory stone columns, (VSC), in accordance with Submittal #31
3400-02.0 31 3400 – Aggregate Piers, prepared by CMC Professional Services LLC, 335 E. Geneva Rd #3116, Carol
Stream, Il 60188.
Glossary of Header Terms:
VSC Pier #: Each pier is identified by number according to location plan included in the above referenced
Submittal.
Proposed Depth: Total VSC depth from working grade to proposed bottom elevation as put forth in design
criteria.
Installed Depth: The as-built length of pier as constructed from working grade to termination in suitable native,
(bearing) soil.
Stone Take: The amount of Crushed Stone used in constructing a given Pier, (expressed in volume), one cubic
yard weighs approximately 1.2 Ton.
Comments: Note any deviation from standard installation procedures, proposed depths or changes in location of
said Pier.
Activity for Thursday, July 15th, 2021:
VSC Pier # Proposed Depth Installed Depth Stone Take Cu. Yds. Comments
2407 14 14 1.5 Routine
2410 14 14 1.5 Routine
2498 14 14 1.5 Routine
2406 14 14 1.5 Routine
2409 14 14 1.5 Routine
2411 6 6 .7 Routine
2412 6 6 .7 Routine
2413 6 6 .7 Routine
2414 6 6 .7 Routine
2415 9 9 1 Routine
2416 14 14 1.5 Routine
2418 14 14 1.5 Routine
2417 14 14 1.5 Routine
2420 14 14 1.5 Routine
2419 14 14 1.5 Routine
2421 14 14 1.5 Routine
2422 6 6 .7 Routine
2448 6 6 .7 Routine
2449 9 9 1 Routine
2450 9 9 1 Routine
2423 6 6 .7 Routine
2451 14 14 14 Routine
2453 14 14 14 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/15/21, Partly Cloudy – Low 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
2452 14 14 1.5 Routine
2455* 14 14 1.5 Routine
2454 14 14 1.5 Routine
2456 14 14 1.5 Routine
2424 6 6 .7 Routine
2384 6 6 .7 Routine
2425 6 6 .7 Routine
2385 6 6 .7 Routine
2426 6 6 .7 Routine
2386 6 6 .7 Routine
2427 6 6 .7 Routine
2387 6 6 .7 Routine
2428 6 6 .7 Routine
2388** 6 6 .7 Routine
2429 6 6 .7 Routine
2389 14 14 1.5 Routine
2390 14 14 1.5 Routine
2391 14 14 1.5 Routine
2359 10 10 1 Routine
2392 14 14 1.5 Routine
2393 14 14 1.5 Routine
2430 6 6 .7 Routine
2394 6 6 .7 Routine
2431 6 6 .7 Routine
2395 6 6 .7 Routine
2432 6 6 .7 Routine
2396 6 6 .7 Routine
2433 6 6 .7 Routine
2397 6 6 .7 Routine
2434 6 6 .7 Routine
2398 6 6 .7 Routine
2435 6 6 .7 Routine
2399 6 6 .7 Routine
2436 6 6 .7 Routine
2400 6 6 .7 Routine
2437 6 6 .7 Routine
2401 6 6 .7 Routine
2438 6 6 .7 Routine
2402 6 6 .7 Routine
2471 6 6 .7 Routine
2472 6 6 .7 Routine
2473 10 10 1 Routine
2474 9 9 1 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/15/21, Partly Cloudy – Low 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
2475 9 9 1 Routine
2509 6 6 .7 Routine
2510 10 10 1 Routine
2529 9 9 1 Routine
2530 10 10 1 Routine
2527 9 9 1 Routine
2528 9 9 1 Routine
2592 9 9 1 Routine
2591 9 9 1 Routine
2590 9 9 1 Routine
2589 9 9 1 Routine
2556 6 6 .75 Routine
2588 9 9 1 Routine
2587 9 9 1 Routine
2586 9 9 1 Routine
2616 9 9 1 Routine
2615 9 9 1 Routine
2614 9 9 1 Routine
2613 9 9 1 Routine
2612 9 9 1 Routine
2610 9 9 1 Routine
2611 6 6 .7 Routine
2608 6 6 .7 Routine
2609 9 9 1 Routine
2607 9 9 1 Routine
2606 9 9 1 Routine
2605 6 6 .7 Routine
2604 9 9 1 Routine
2603 9 9 1 Routine
2602 6 6 .7 Routine
2601 9 9 1 Routine
2600 9 9 1 Routine
2599 9 9 1 Routine
2598 9 9 1 Routine
* Performance Test, Movement = ¼” ‐ Acceptable
** Performance Test, Movement = 1/8” ‐ Acceptable
Total Production Piers this day = 100
Total Production Piers to date = 1295
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/15/21, Partly Cloudy – Low 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
FOOTING PREPARATION:
THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:
Excavate to six inches below proposed Bottom of Footing Elevation
Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor
Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade
Compact said Crushed Stone
Crushed Stone Base now ready for Footing installation
Activity for Thursday, July 15th, 2021: AREA D
Footing Subgrade Compaction / Preparation Detail :
The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of a
non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture
content of the soil. Since the encountered materials are of native, (natural) deposition the water content can be variable
from location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are
utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with
supplied water in order to certify proper compaction in these circumstances.
THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:
FOOTING LINE
FROM – TO
FOOTING
COORDINATE
FOOTING
SIZE and TYPE
BOTTOM
ELEVATION
COMMENTS
D/d10‐D/d22 D/d14 F7.0 23.0 Complete
D/d10‐D/d22 D/d16 F7.0 23.0 Complete
D.1/c115‐D.1/c116 D.1/c115 F6.0 23.2 Complete
D.1/c115‐D.1/c116 D.1/c116 F5.0 23.2 Complete
D.3/c115 D.3/c115 F9.0 22.7 Complete
D/d10‐D/d22 D/d20 F9.0 22.7 Complete
D.2/jj‐D.5/jj D.5/jj F5.0 21.2 Complete‐Area C
See Photos:
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/15/21, Partly Cloudy – Low 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
Survey Pier Layout, whiskers & flags in foreground – look closely!
Lone Pier, East end of “D” Line, (left of center)
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/15/21, Partly Cloudy – Low 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
First Pass to expose piers, Footing Location, prior to final Subgrade Elevation and subsequent compaction, (typical)
High CFM air pressure aids in advancing Mandrel to Design Depth, (typical)
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/16/21, Partly Cloudy – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
This Report is a summary installation list of installed vibratory stone columns, (VSC), in accordance with Submittal #31
3400-02.0 31 3400 – Aggregate Piers, prepared by CMC Professional Services LLC, 335 E. Geneva Rd #3116, Carol
Stream, Il 60188.
Glossary of Header Terms:
VSC Pier #: Each pier is identified by number according to location plan included in the above referenced
Submittal.
Proposed Depth: Total VSC depth from working grade to proposed bottom elevation as put forth in design
criteria.
Installed Depth: The as-built length of pier as constructed from working grade to termination in suitable native,
(bearing) soil.
Stone Take: The amount of Crushed Stone used in constructing a given Pier, (expressed in volume), one cubic
yard weighs approximately 1.2 Ton.
Comments: Note any deviation from standard installation procedures, proposed depths or changes in location of
said Pier.
Activity for Friday, July 16th, 2021:
VSC Pier # Proposed Depth Installed Depth Stone Take Cu. Yds. Comments
2581* 6 6 .7 Routine
2597 9 9 1 Routine
2596 9 9 1 Routine
2579 9 9 1 Routine
2595 9 9 1 Routine
2578 6 6 .7 Routine
2593 9 9 1 Routine
2594 9 9 1 Routine
2547 6 6 .7 Routine
2546 6 6 .7 Routine
2577 9 9 1 Routine
3245 6 6 .7 Routine
2576 9 9 1 Routine
2575 9 9 1 Routine
2543 9 9 1 Routine
2544 9 9 1 Routine
2574 9 9 1 Routine
2573 9 9 1 Routine
2572 9 9 1 Routine
2542 6 6 .7 Routine
2571 9 9 1 Routine
2570 9 9 1 Routine
2541 9 9 1 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/16/21, Partly Cloudy – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
2540 9 9 1 Routine
2569 9 9 1 Routine
2568 9 9 1 Routine
2539 6 6 .7 Routine
2538 9 9 1 Routine
2537 9 9 1 Routine
2567 9 9 1 Routine
2566 9 9 1 Routine
2536 6 6 .7 Routine
2565 9 9 1 Routine
2564 9 9 1 Routine
2535 6 6 .7 Routine
2563 9 9 1 Routine
2562 9 9 1 Routine
2490 9 9 1 Routine
2489 9 9 1 Routine
2534 6 6 .7 Routine
2561 9 9 1 Routine
2488 6 6 .7 Routine
2487 9 9 1 Routine
2486 9 9 1 Routine
2485 6 6 .7 Routine
2460 9 9 1 Routine
2533 6 6 .7 Routine
2559 9 9 1 Routine
2558 9 9 1 Routine
2484 6 6 .7 Routine
2557 9 9 1 Routine
2531 9 9 1 Routine
2532 9 9 1 Routine
2483 9 9 1 Routine
2482 9 9 1 Routine
2481 9 9 1 Routine
2480 9 9 1 Routine
2478 14 14 1.5 Routine
2479 14 14 1.5 Routine
2477 14 14 1.5 Routine
2476 14 12 1.5 REFUSAL
2442 6 6 .7 Routine
2443 6 6 .7 Routine
2444 6 6 .7 Routine
2445 6 6 .7 Routine
2446 6 6 .7 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/16/21, Partly Cloudy – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
2447 6 6 .7 Routine
2491 6 6 .7 Routine
2492 6 6 .7 Routine
2493 6 6 .7 Routine
2494 6 6 .7 Routine
2495 6 6 .7 Routine
2457 6 6 .7 Routine
2496 6 6 .7 Routine
2458 6 6 .7 Routine
2459 9 9 1 Routine
2460 9 9 1 Routine
2497 6 6 .7 Routine
2498 6 6 .7 Routine
2461 6 6 .7 Routine
2499 6 6 .7 Routine
2462 6 6 .7 Routine
2620 10 10 1 Routine
2619 10 10 1 Routine
2618 10 10 1 Routine
2617 10 10 1 Routine
2463** 6 6 .7 Routine
2464 6 6 .7 Routine
2465 6 6 .7 Routine
2466 6 6 .7 Routine
2467 6 6 .7 Routine
2468 6 6 .7 Routine
2469 6 6 .7 Routine
2470 6 6 .7 Routine
2511 9 9 1 Routine
2512 9 9 1 Routine
2500 6 6 .7 Routine
2548 9 9 1 Routine
2513 9 9 1 Routine
2514 9 9 1 Routine
2501 6 6 .7 Routine
2515 9 9 1 Routine
2549 6 6 .7 Routine
2516 9 9 1 Routine
2517 9 9 1 Routine
* Performance Test, Movement = 1/8” ‐ Acceptable
** Performance Test, Movement = ¼” – Acceptable
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/16/21, Partly Cloudy – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
Total Production Piers this day = 105
Total Production Piers to date = 1400
FOOTING PREPARATION:
THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:
Excavate to six inches below proposed Bottom of Footing Elevation
Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor
Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade
Compact said Crushed Stone
Crushed Stone Base now ready for Footing installation
Activity for Friday, July 16th, 2021: AREA C
Footing Subgrade Compaction / Preparation Detail :
The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of a
non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture
content of the soil. Since the encountered materials are of native, (natural) deposition the water content can be variable
from location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are
utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with
supplied water in order to certify proper compaction in these circumstances.
THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:
FOOTING LINE
FROM – TO
FOOTING
COORDINATE
FOOTING
SIZE and TYPE
BOTTOM
ELEVATION
COMMENTS
D.5/ii‐D.9/ii N/A strip 23.2 Complete
D.5/jj‐D.9/jj N/A strip 23.2 Complete
D3/c115‐E/c115 D.7/c115 F5.0 23.2 Complete
D.1/c116‐E/c116 D.7/c116 F5.0 23.2 Complete
E/c2‐E/c6 E/c2 F5.0 23.2 Complete
E/c2‐E/c6 E/c4 F7.0 23.0 Complete
See Photos:
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/16/21, Partly Cloudy – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
2
Exposed Piers along c116 Line @ D.4,+/‐, Looking East
First Cut, Bldg. C (proper) Northwest Corner
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/16/21, Partly Cloudy – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
Subgrade along “ E “ Line From Corner Looking East
Compacting Crushed Stone “ E “ Line ‐ West End, Looking East
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/19/21, Partly Cloudy – Mid 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
This Report is a summary installation list of installed vibratory stone columns, (VSC), in accordance with Submittal #31
3400-02.0 31 3400 – Aggregate Piers, prepared by CMC Professional Services LLC, 335 E. Geneva Rd #3116, Carol
Stream, Il 60188.
Glossary of Header Terms:
VSC Pier #: Each pier is identified by number according to location plan included in the above referenced
Submittal.
Proposed Depth: Total VSC depth from working grade to proposed bottom elevation as put forth in design
criteria.
Installed Depth: The as-built length of pier as constructed from working grade to termination in suitable native,
(bearing) soil.
Stone Take: The amount of Crushed Stone used in constructing a given Pier, (expressed in volume), one cubic
yard weighs approximately 1.2 Ton.
Comments: Note any deviation from standard installation procedures, proposed depths or changes in location of
said Pier.
Activity for Monday, July 19th , 2021:
VSC Pier # Proposed Depth Installed Depth Stone Take Cu. Yds. Comments
2502 6 6 .7 Routine
2550 6 6 .7 Routine
2580 6 6 .7 Routine
2582 6 6 .7 Routine
2583 6 6 .7 Routine
2584 6 6 .7 Routine
2585 6 6 .7 Routine
2503 6 6 .7 Routine
2518 9 9 1 Routine
2551 6 6 .7 Routine
2519 9 9 1 Routine
2504 6 6 .7 Routine
2552 6 6 .7 Routine
2520 9 9 1 Routine
2521 9 9 1 Routine
2505 6 6 .7 Routine
2553 6 6 .7 Routine
2522 9 9 1 Routine
2506* 6 6 .7 Routine
2523 9 9 1 Routine
2554 6 6 .7 Routine
2524 9 9 1 Routine
2555 6 6 .7 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/19/21, Partly Cloudy – Mid 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
2525 9 9 1 Routine
2507 6 6 .7 Routine
2526 9 9 1 Routine
2508 6 6 .7 Routine
1250 10 10 1 Routine
1248 6 6 .7 Routine
1247 10 10 1 Routine
1244 10 10 1 Routine
1245 6 6 .7 Routine
1242 10 10 1 Routine
1241 6 6 .7 Routine
1240 10 10 1 Routine
1238 6 6 .7 Routine
1237 10 10 1 Routine
1234 10 10 1 Routine
1235 6 6 .7 Routine
1180 6 6 .7 Routine
1179 6 6 .7 Routine
1178 6 6 .7 Routine
1177 6 6 .7 Routine
1176 6 6 .7 Routine
1175 9 9 1 Routine
1215 9 9 1 Routine
1214 9 9 1 Routine
1281 9 9 1 Routine
1280 9 9 1 Routine
1312 9 9 1 Routine
1332 9 9 1 Routine
1331 9 9 1 Routine
1379 9 9 1 Routine
1425 9 9 1 Routine
1424 9 9 1 Routine
1426 9 9 1 Routine
1470 9 9 1 Routine
1503 9 9 1 Routine
1505 9 9 1 Routine
1504 9 9 1 Routine
1506 6 6 .7 Routine
1548 9 9 1 Routine
1549 9 9 1 Routine
1550 9 9 1 Routine
1551 9 9 1 Routine
1552 9 9 1 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/19/21, Partly Cloudy – Mid 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
1553 9 9 1 Routine
1554 9 9 1 Routine
1555 9 9 1 Routine
1563 9 9 1 Routine
1564 9 9 1 Routine
1565 9 9 1 Routine
1566 9 9 1 Routine
1568** 9 9 1 Routine
1567 9 9 1 Routine
1569 9 9 1 Routine
1570 9 9 1 Routine
1571 9 9 1 Routine
1572 9 9 1 Routine
1573 9 9 1 Routine
1574 9 9 1 Routine
1575 9 9 1 Routine
1576 9 9 1 Routine
1577 9 9 1 Routine
1578 9 9 1 Routine
1579 9 9 1 Routine
1580 9 9 1 Routine
1581 9 9 1 Routine
1582 9 9 1 Routine
1583 9 9 1 Routine
1584 9 9 1 Routine
1585 9 9 1 Routine
1586 9 9 1 Routine
* Performance Test, Movement = 1/8” Acceptable
** Performance Test, Movement = 3/16” Acceptable
Total Production Piers this day = 94
Total Production Piers to date = 1577
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/19/21, Partly Cloudy – Mid 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
FOOTING PREPARATION:
THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:
Excavate to six inches below proposed Bottom of Footing Elevation
Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor
Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade
Compact said Crushed Stone
Crushed Stone Base now ready for Footing installation
Activity for Monday, July 19th, 2021: AREA C
Footing Subgrade Compaction / Preparation Detail :
The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of a
non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture
content of the soil. Since the encountered materials are of native, (natural) deposition the water content can be variable
from location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are
utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with
supplied water in order to certify proper compaction in these circumstances.
THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:
FOOTING LINE
FROM – TO
FOOTING
COORDINATE
FOOTING
SIZE and TYPE
BOTTOM
ELEVATION
COMMENTS
E/ii‐E/c18 E/ii F 8.0 22.9 Complete
E/ii‐E/c18 E/c8 F 5.0 23.2 Complete
E/ii‐E/c18 E/c9 F 7.0 23.0 Complete
E/ii‐E/c18 E/c12 F 6.0 23.2 Complete
E/ii‐E/c18 E/c14 F 6.0 23.2 Complete
E/ii‐E/c18 E/c16 F 6.0 23.2 Complete
E/ii‐E/c18 E/c18 F 8.0 22.9 Complete
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/19/21, Partly Cloudy – Mid 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
Revealed Piers Location D.7/c14.5
Placing Crushed Stone Location E/c13
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/19/21, Partly Cloudy – Mid 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
Compacting Subgrade Location E/c16
Compacting Crushed Stone Location E/c16
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/20/21, Partly Cloudy – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
This Report is a summary installation list of installed vibratory stone columns, (VSC), in accordance with Submittal #31
3400-02.0 31 3400 – Aggregate Piers, prepared by CMC Professional Services LLC, 335 E. Geneva Rd #3116, Carol
Stream, Il 60188.
Glossary of Header Terms:
VSC Pier #: Each pier is identified by number according to location plan included in the above referenced
Submittal.
Proposed Depth: Total VSC depth from working grade to proposed bottom elevation as put forth in design
criteria.
Installed Depth: The as-built length of pier as constructed from working grade to termination in suitable native,
(bearing) soil.
Stone Take: The amount of Crushed Stone used in constructing a given Pier, (expressed in volume), one cubic
yard weighs approximately 1.2 Ton.
Comments: Note any deviation from standard installation procedures, proposed depths or changes in location of
said Pier.
Activity for Tuesday, July 20th, 2021:
VSC Pier # Proposed Depth Installed Depth Stone Take Cu. Yds. Comments
1249 6 6 .7 Routine
1295 10 10 1 Routine
1294 6 6 .7 Routine
1358 6 6 .7 Routine
1357 10 10 1 Routine
1356 6 6 .7 Routine
1355 10 10 1 Routine
1354 10 10 1 Routine
1394 10 10 1 Routine
1393 10 10 1 Routine
1443 10 10 1 Routine
1444 10 10 1 Routine
1487 6 6 .7 Routine
1521 14 14 1.5 Routine
1525 14 14 1.5 Routine
1523* 14 14 1.5 Routine
1524 14 14 1.5 Routine
1522 14 14 1.5 Routine
1626 14 14 1.5 Routine
1520 6 6 .7 Routine
1562 6 6 .7 Routine
1519 11 11 1 Routine
1561 6 6 .7 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/20/21, Partly Cloudy – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
1518 11 11 1 Routine
1517 11 11 1 Routine
1516 6 6 .7 Routine
1560 6 6 .7 Routine
1515 6 6 .7 Routine
1559 6 6 .7 Routine
1514 9 9 1 Routine
1513 9 9 1 Routine
1512 6 6 .7 Routine
1558 6 6 .7 Routine
1511 6 6 .7 Routine
1557 6 6 .7 Routine
1510 6 6 .7 Routine
1556 6 6 .7 Routine
1509 6 6 .7 Routine
1508 6 6 .7 Routine
1507 6 6 .7 Routine
1471 6 6 .7 Routine
1427 6 6 .7 Routine
1472 6 6 .7 Routine
1428 6 6 .7 Routine
1473 6 6 .7 Routine
1429 6 6 .7 Routine
1474 9 9 1 Routine
1475 9 9 1 Routine
1430 6 6 .7 Routine
1476 9 9 1 Routine
1477 9 9 1 Routine
1431 9 9 1 Routine
1432 9 9 1 Routine
1478 9 9 1 Routine
1433 9 9 1 Routine
1479 6 6 .7 Routine
1434 6 6 .7 Routine
1480 6 6 .7 Routine
1436 6 6 .7 Routine
1438 10 10 1 Routine
1481 10 10 1 Routine
1482 10 10 1 Routine
1483 10 10 1 Routine
1439 10 10 1 Routine
1484 6 6 1 Routine
1440 6 6 1 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/20/21, Partly Cloudy – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
1441 9 9 1 Routine
1485 6 6 .7 Routine
1486 6 6 .7 Routine
1442 6 6 .7 Routine
1380 6 6 .7 Routine
1333 6 6 .7 Routine
1381 6 6 .7 Routine
1334 9 9 1 Routine
1335 9 9 1 Routine
1382 6 6 .7 Routine
1336 6 6 .7 Routine
1337 9 9 1 Routine
1338 9 9 1 Routine
1383 6 6 .7 Routine
1384 6 6 .7 Routine
1339 6 6 .7 Routine
1317 11 11 1 Routine
1319 11 11 1 Routine
1318 11 11 1 Routine
1340 10 10 1 Routine
1341 6 6 .7 Routine
1342 10 10 1 Routine
1385 6 6 .7 Routine
1343 10 10 1 Routine
1344 6 6 .7 Routine
1386 10 10 1 Routine
1435 10 10 1 Routine
1387 10 10 1 Routine
1345 10 10 1 Routine
1387 10 10 1 Routine
1345 6 6 .7 Routine
1347 10 10 1 Routine
1388 6 6 .7 Routine
1389 10 10 1 Routine
1348 6 6 .7 Routine
1349 10 10 1 Routine
1390 6 6 .7 Routine
1350 6 6 .7 Routine
1351 10 10 1 Routine
1391 6 6 .7 Routine
1352 10 10 .7 Routine
1353 6 6 .7 Routine
1392 6 6 .7 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/20/21, Partly Cloudy – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
1313 6 6 .7 Routine
1314 6 6 .7 Routine
1315 6 6 .7 Routine
1316 6 6 .7 Routine
1320 10 10 1 Routine
1321 6 6 .7 Routine
1322 6 6 .7 Routine
1323 6 6 .7 Routine
1324 6 6 .7 Routine
1325 6 6 .7 Routine
1326 6 6 .7 Routine
* Performance Test, Movement = 3/8” Acceptable
Total Production Piers this day = 120
Total Production Piers to date = 1697
FOOTING PREPARATION:
THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:
Excavate to six inches below proposed Bottom of Footing Elevation
Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor
Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade
Compact said Crushed Stone
Crushed Stone Base now ready for Footing installation
Activity for Tuesday, July 20th, 2021: AREA C
Footing Subgrade Compaction / Preparation Detail :
The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of a
non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture
content of the soil. Since the encountered materials are of native, (natural) deposition the water content can be variable
from location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are
utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with
supplied water in order to certify proper compaction in these circumstances.
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/20/21, Partly Cloudy – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:
FOOTING LINE
FROM – TO
FOOTING
COORDINATE
FOOTING
SIZE and TYPE
BOTTOM
ELEVATION
COMMENTS
E/c2‐H/c2 F/c2 F 5.0 23.2 Complete
E/c2‐H/c2 F.4/c2 F 4.0 23.2 Complete
E/c2‐H/c2 G.5/c1 F30.7x5 22.7 Complete
ISOLATED F/c4 F 7.0 23.0 Complete
ISOLATED F/ii F 9.0 22.7 Complete
ISOLATED G/c3 F 7.0 23.0 Complete
ISOLATED G/c5 F 6.0 23.2 Complete
See Photos:
Excavating c2 Line, Looking South from Location E/c2
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/20/21, Partly Cloudy – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
Preparing Subgrade along same location
Compacting Crushed Stone upon same
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/21/21, Partly Cloudy – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
This Report is a summary installation list of installed vibratory stone columns, (VSC), in accordance with Submittal #31
3400-02.0 31 3400 – Aggregate Piers, prepared by CMC Professional Services LLC, 335 E. Geneva Rd #3116, Carol
Stream, Il 60188.
Glossary of Header Terms:
VSC Pier #: Each pier is identified by number according to location plan included in the above referenced
Submittal.
Proposed Depth: Total VSC depth from working grade to proposed bottom elevation as put forth in design
criteria.
Installed Depth: The as-built length of pier as constructed from working grade to termination in suitable native,
(bearing) soil.
Stone Take: The amount of Crushed Stone used in constructing a given Pier, (expressed in volume), one cubic
yard weighs approximately 1.2 Ton.
Comments: Note any deviation from standard installation procedures, proposed depths or changes in location of
said Pier.
Activity for Wednesday, July 21st, 2021:
VSC Pier # Proposed Depth Installed Depth Stone Take Cu. Yds. Comments
1327 6 6 .7 Routine
1328 6 6 .7 Routine
1329 6 6 .7 Routine
1296* 6 6 .7 Routine
1330 9 9 1 Routine
1329A 10 10 1 Routine
1296A 10 10 1 Routine
1297 9 9 1 Routine
1298 6 6 .7 Routine
1282 6 6 .7 Routine
1283 6 6 .7 Routine
1284 6 6 .7 Routine
1285 6 6 .7 Routine
1286 6 6 .7 Routine
1287 10 10 1 Routine
1288 6 6 .7 Routine
1289 6 6 .7 Routine
1290 6 6 .7 Routine
1291 6 6 .7 Routine
1292 6 6 .7 Routine
1293 6 6 .7 Routine
1216 6 6 .7 Routine
1217 6 6 .7 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/21/21, Partly Cloudy – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
1218 6 6 .7 Routine
1219 9 9 1 Routine
1220 9 9 1 Routine
1222 14 14 1.5 Routine
1221 14 14 1.5 Routine
1223 14 14 1.5 Routine
1224 14 14 1.5 Routine
1225 14 14 1.5 Routine
1226 14 14 1.5 Routine
1228 10 10 1 Routine
1227 10 10 1 Routine
1229 10 10 1 Routine
1230 6 6 .7 Routine
1231 10 10 1 Routine
1232 6 6 .7 Routine
1233 6 6 .7 Routine
1236 6 6 .7 Routine
1239 6 6 .7 Routine
1243 6 6 .7 Routine
1246 6 6 .7 Routine
1251 10 10 1 Routine
1250(A} 10 10 1 Routine
1138 9 9 1 Routine
1136 9 9 1 Routine
1137 9 9 1 Routine
1108 9 9 1 Routine
1109 9 9 1 Routine
1076 9 9 1 Routine
1077 9 9 1 Routine
1013 9 9 1 Routine
1014 9 9 1 Routine
1001 9 9 1 Routine
1002 9 9 1 Routine
1003 9 9 1 Routine
1139 6 6 .7 Routine
1140 14 14 1.5 Routine
1141 14 14 1.5 Routine
1142 14 14 1.5 Routine
1143 14 14 1.5 Routine
1144 6 6 .7 Routine
1145 6 6 .7 Routine
1146** 9 9 1 Routine
1147 9 9 1 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/21/21, Partly Cloudy – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
1181 9 9 1 Routine
1182 9 9 1 Routine
1148 6 6 .7 Routine
1183(A) 6 6 .7 Routine
1184 9 9 1 Routine
1149 9 9 1 Routine
1150 9 9 1 Routine
1185 6 6 .7 Routine
1151 9 9 1 Routine
1186 9 9 1 Routine
1187 6 6 .7 Routine
1152 9 9 1 Routine
1188 9 9 1 Routine
1189 6 6 .7 Routine
1153 9 9 1 Routine
1190 9 9 1 Routine
1154 9 9 1 Routine
1191 6 6 .7 Routine
1192 9 9 1 Routine
1155 9 9 1 Routine
1193 6 6 .7 Routine
1156 9 9 1 Routine
1157 9 9 1 Routine
1184 9 9 1 Routine
1158 9 9 1 Routine
1195 9 9 1 Routine
1196 9 9 1 Routine
1161 14 14 1.5 Routine
1199 14 14 1.5 Routine
1200 14 14 1.5 Routine
1160 14 14 1.5 Routine
1159 14 14 1.5 Routine
1163 14 14 1.5 Routine
1162 14 14 1.5 Routine
1197 14 14 1.5 Routine
1198 14 14 1.25 Routine
1201 14 14 1.25 Routine
1255 14 14 1.25 Routine
1252 14 14 1.25 Routine
1256 14 14 1.25 Routine
1258 14 14 1.25 Routine
1253 14 14 1.25 Routine
1202 14 14 1.25 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/21/21, Partly Cloudy – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
* Performance Test, Movement = <1/8” Acceptable
** Performance Test, Movement = 1/8” Acceptable
Total Production Piers this day = 109
Total Production Piers to date = 1806
FOOTING PREPARATION:
THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:
Excavate to six inches below proposed Bottom of Footing Elevation
Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor
Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade
Compact said Crushed Stone
Crushed Stone Base now ready for Footing installation
Activity for Wednesday, July 21st, 2021: AREA C
Footing Subgrade Compaction / Preparation Detail :
The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of a
non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture
content of the soil. Since the encountered materials are of native, (natural) deposition the water content can be variable
from location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are
utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with
supplied water in order to certify proper compaction in these circumstances.
THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:
FOOTING LINE
FROM – TO
FOOTING
COORDINATE
FOOTING
SIZE and TYPE
BOTTOM
ELEVATION
COMMENTS
Isolated G/c7 F 8.0 22.9 Complete
Isolated F/c8 F 6.0 23.2 Complete
Elevator Pit F.5/c8.3 8.7 x 6.0 22.2 Complete
Isolated F/c9 F 7.0 23.0 Complete
Isolated G/c9 F 7.0 23.0 Complete
Isolated F/c12 F 7.0 23.0 Complete
See Photos:
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/21/21, Partly Cloudy – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
First Pass @ Elevator Pit Subgrade four Piers visible
Compacting Subgrade – Elevator Pit
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/21/21, Partly Cloudy – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
View four completed Footing Pads, Elevator Pit in center
Installing typical Pier, Northwest section of Area “A”
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/22/21, Partly Cloudy – Mid 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
This Report is a summary installation list of installed vibratory stone columns, (VSC), in accordance with Submittal #31
3400-02.0 31 3400 – Aggregate Piers, prepared by CMC Professional Services LLC, 335 E. Geneva Rd #3116, Carol
Stream, Il 60188.
Glossary of Header Terms:
VSC Pier #: Each pier is identified by number according to location plan included in the above referenced
Submittal.
Proposed Depth: Total VSC depth from working grade to proposed bottom elevation as put forth in design
criteria.
Installed Depth: The as-built length of pier as constructed from working grade to termination in suitable native,
(bearing) soil.
Stone Take: The amount of Crushed Stone used in constructing a given Pier, (expressed in volume), one cubic
yard weighs approximately 1.2 Ton.
Comments: Note any deviation from standard installation procedures, proposed depths or changes in location of
said Pier.
Activity for Thursday, July 22nd, 2021:
VSC Pier # Proposed Depth Installed Depth Stone Take Cu. Yds. Comments
1257* 14 14 1.25 Routine
1259 14 13 1.25 REFUSAL
1254 14 14 1.25 Routine
1260 14 14 1.25 Routine
1361 14 14 1.2 Routine
1365 14 14 1.25 Routine
1363 14 14 1.2 Routine
1364 14 14 1.2 Routine
1362 14 14 1.2 Routine
1366 14 14 1.2 Routine
1359 10 10 1 Routine
1360 10 10 1 Routine
1395 6 6 .7 Routine
1393A 10 10 1 Routine
1446 6 6 .7 Routine
1445 10 10 1 Routine
1488 6 6 .7 Routine
1527 6 6 .7 Routine
1528 6 6 .7 Routine
1489 6 6 .7 Routine
1529 9 9 1 Routine
1530 9 9 1 Routine
1531 6 6 .7 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/22/21, Partly Cloudy – Mid 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
1490 6 6 .7 Routine
1532 6 6 .7 Routine
1491 6 6 .7 Routine
1492** 6 6 .7 Routine
1533 11 11 1 Routine
1534 11 11 1 Routine
1535 11 11 1 Routine
1536 6 6 .7 Routine
1493 6 6 .7 Routine
1537 6 6 .7 Routine
1494 6 6 .7 Routine
1538 6 6 .7 Routine
1495 6 6 .7 Routine
1539 6 6 .7 Routine
1496 6 6 .7 Routine
1540 9 9 1 Routine
1541 9 9 1 Routine
1497 6 6 .7 Routine
1542 6 6 .7 Routine
1498 6 6 .7 Routine
1543 6 6 .7 Routine
1499 6 6 .7 Routine
1544 6 6 .7 Routine
1500 6 6 .7 Routine
1545 9 9 1 Routine
1546 9 9 1 Routine
1502 9 9 1 Routine
1501 9 9 1 Routine
1467 6 6 .7 Routine
1468 9 9 1 Routine
1469 9 9 1 Routine
1421 6 6 .7 Routine
1423 9 9 1 Routine
1422 9 9 1 Routine
1420 6 6 .7 Routine
1377 9 9 1 Routine
1378 9 9 1 Routine
1376 6 6 .7 Routine
1311 9 9 1 Routine
1309 6 6 .7 Routine
1310 9 9 1 Routine
1277 6 6 .7 Routine
1278 9 9 1 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/22/21, Partly Cloudy – Mid 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
1279 9 9 1 Routine
1213 9 9 1 Routine
1212 6 6 .7 Routine
1174 9 9 1 Routine
1173 6 6 .7 Routine
1135 9 9 1 Routine
* Performance Test, Movement = ¼” Acceptable
** Performance Test, Movement =< 1/8” Acceptable
Total Production Piers this day = 72
Total Production Piers to date = 1878
FOOTING PREPARATION:
THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:
Excavate to six inches below proposed Bottom of Footing Elevation
Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor
Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade
Compact said Crushed Stone
Crushed Stone Base now ready for Footing installation
Activity for Thursday, July 22nd, 2021: AREA C
Footing Subgrade Compaction / Preparation Detail :
The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of a
non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture
content of the soil. Since the encountered materials are of native, (natural) deposition the water content can be variable
from location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are
utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with
supplied water in order to certify proper compaction in these circumstances.
THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:
FOOTING LINE
FROM – TO
FOOTING
COORDINATE
FOOTING
SIZE and TYPE
BOTTOM
ELEVATION
COMMENTS
H/c1 – H/c3.2 H/c3 F 7.0 23.0 Complete
Isolated F/c14 F 7.0 23.0 Complete
Isolated F/c16 F 6.0 23.2 Complete
Isolated F/c18 F 8.0 22.7 Complete
Isolated G/c11 F 7.0 23.0 Complete
Isolated G/c13 F 7.0 23.2 Complete
Isolated G/c15 F 9.0 22.7 Complete
Isolated G/c17 F 6.0 23.2 Complete
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/22/21, Partly Cloudy – Mid 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
Loction F/c14 piers highly visible in the white sand Subgrade
Compacting final lift Location F/c14