Architect: Perkins Eastman DPC
Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File
ARCHITECT’S SITE OBSERVATION REPORT
DATE OF VISIT: 07/28/2021 PROJECT: Dennis Yarmouth Intermediate
Middle School
286 Station Avenue
South Yarmouth, MA 02664
DATE OF ISSUE: 08/06/2021 PROJECT NO: 71011
WEATHER
CONDITIONS:
CLOUDY, 70s ARCHITECT: Perkins Eastman, DPC
20 Ashburton Street
8th floor
Boston, MA
The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit.
WORK IN PROGRESS:
1) Excavation and subgrade prepping for foundations in Area B
2) Placing concrete for walls and footings (D and C)
3) Setting forms and rebar for footings, and piers at Area C
4) Vibratory stone column installation
5) Backfilling of of sewer force main connection
6) Ongoing work on VSC installation
7) Ongoing layout work by survey crew.
8) Road grading and general site prep
FIELD OBSERVATIONS:
PE visited the site to review ongoing progress with the site work and foundations.
1. RBO has prepared Footing line B22 and B25 from K to area C and B and by the end of the day on 7-28 they
prepared lines J/B30 to J/B32 and J.7/B35 to J.7/B33, as well as north south return at line B33 (see also attached
GPI report).
2. Most of the walls and piers at Area D have been stripped and are ready for backfill and Marguerite is making final
concrete placement preparations at the foundation wall from D.3 to D.24 for a concrete pour today.
3. Concrete is also being placed today for footings on line E (area C)
4. At area C Marguerite is in the process of tying rebar for footing, pier and wall placements. Footing forms are being
prepared on line H and line C21 (south elevation and around south east corner) for placement later this week, and
many interior column footings in area C have are formed and tied.
5. The pump station for sewer force main is in place; force main has been installed from lift station to limit of work
(on 7-27) and RBO is in the process of backfilling.
6. CNC is installing vibratory stone columns at southwest part of Area A(see photo); VSC installation is due to be
completed today.
7. Brennan is continuing to install controls for anchor bolts at piers in Area D
8. Processed gravel has been backfilled above cultic chambers at UGI 5.
9. Commodore is planning on having some additional trees removed as necessitated by the correction of the limit of
work fence along the west edge of the site.
10. PE observed the stockpile of recycled glass for backfill around utility pipes; the new delivery appears to be mostly
glass and glass detritus (see photo); there is little odor from the pile.
REPORT BY: RH Page 2 of 3
PROGRESS PHOTOS
PUMP CHAMBER FOR SEWER FORCE MAIN EXCAVATION FOR A FOOTING LINE AT AREA B
FOUNDATION WALL AT LINE D1-D2 (D WEST) PREPARATION FOR WALL POUR ON LINE E
PREP FOR FOOTING PLACEMENT AT LINE E (AREA C) PREP OF FOOTING FORMS AT LINE H (AREA C)
REPORT BY: RH Page 3 of 3
SUBGRADE PREP ON FOOTING LINE J.7 FOOTING FORMS AT LINE C1/C2
LAST DAY OF VSC INSTALLATION DETAIL FROM RECYCLED GLASS AGGREGATE STOCKPILE
COMPANY LLP
10 Waterchase
Rocky Hill,
Office:
Fax:
Drive
CT 06067
(860) 563-3820
(860) 563-3860
GIRARD
AND
STRUCTURAL ENGINEERS
girardco.com
Field Observation Report - 02
July 27, 2021
Attn: Daniel Colli, AIA
Perkins Eastman
Boston, MA 02110
Re: Site Visit – July 22, 2021
Dennis Yarmouth Intermediate Middle School
Yarmouth, MA
On Wednesday, July 22, 2021, our office visited the job site to observe the
construction progress for the Dennis Yarmouth Intermediate Middle School.
The Construction trades working this day included Site contractors. During the
visit, I spoke with representatives from Commodore Builders and PMA. Andy
Hazelton and I walked the site and attended the weekly owner meeting.
Aggregate pier installation is in progress with one installation machine.
Excavations for footings are continuing into Area C and will be following the RAP
installation South. Stone is being placed over the excavated surface, and a
representative from GPI was monitoring the activity.
Concrete installation is in progress. Area D footings and walls are in various stages
of completion. Interior footings and piers, the North and East footings and walls,
and the West footings are installed. Formwork is in place along the West wall,
and reinforcing is installed. The observed reinforcing size, spacing, and cover are
in conformance. I had a brief conversation with the reinforcing foreman to
review his general procedures and found them to be acceptable.
The concrete visual quality of the finished concrete is good, with no voids or
indications of formwork failures. Anchor rods for the building columns are set
with plywood templates, and the exposed threads are protected with heavy tape.
The formwork for the column footings was simplified at line A columns, d6 and
d8. Additional plain concrete was placed between the column footings creating
a monolithic placement. The contractor was informed that any deviation should
be brought to our attention prior to procceding with the work. We have reviewed
this condition, and it is acceptable as installed.
Additional concrete is placed at the footing elevation under the exterior aprons.
This additional concrete will simplify the wall formwork and is acceptable.
Footing penetrations were reviewed with Paul Genereux. Final underground
coordination will require a wall footing penetration at line c21 between columns
F.5 and G. The wall footing penetration detail can be used at this location. It will
be acceptable to eliminate the wall footing between the faces of the column
footings.
Field Observation Report - 02
Dennis Yarmouth Intermediate Middle School
Yarmouth, MA
Page: 2 of 2
Girard and Company, LLP
July 27, 2021
The schedule was reviewed with the commodore. There is a need to backfill the interior area without
backfilling the exterior, creating an unbalanced load on the foundation wall. We asked that the contractor
submit an RFI with this question. We will review and provide direction through the RFI response.
In general, the work observed appears in conformance with standard industry practice. Other than the
items noted above, there were no apparent deficiencies noted.
Respectfully,
Girard and Company, LLP
Kenneth P. Anderson, PE
Field observations performed by Girard and Company, LLP are not detailed inspections and do not relieve the contractor from their
obligations under the construction contract, including but not limited to the construction means and methods and job site safety. The
purpose of the field observations is to verify that the progress of work is in general conformance with the contract documents.
file: H:\2017\17-030 Dennis Yarmouth MS\Construction Control\OR\17030_OR002.docx
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/23/21, Partly Cloudy – Mid 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
This Report is a summary installation list of installed vibratory stone columns, (VSC), in accordance with Submittal #31
3400-02.0 31 3400 – Aggregate Piers, prepared by CMC Professional Services LLC, 335 E. Geneva Rd #3116, Carol
Stream, Il 60188.
Glossary of Header Terms:
VSC Pier #: Each pier is identified by number according to location plan included in the above referenced
Submittal.
Proposed Depth: Total VSC depth from working grade to proposed bottom elevation as put forth in design
criteria.
Installed Depth: The as-built length of pier as constructed from working grade to termination in suitable native,
(bearing) soil.
Stone Take: The amount of Crushed Stone used in constructing a given Pier, (expressed in volume), one cubic
yard weighs approximately 1.2 Ton.
Comments: Note any deviation from standard installation procedures, proposed depths or changes in location of
said Pier.
Activity for Friday July 23rd, 2021:
VSC Pier # Proposed Depth Installed Depth Stone Take Cu. Yds. Comments
NO PIERS WERE INSTALLED THIS DATE
FOOTING PREPARATION:
THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:
Excavate to six inches below proposed Bottom of Footing Elevation
Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor
Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade
Compact said Crushed Stone
Crushed Stone Base now ready for Footing installation
Activity for Friday July 23rd, 2021: AREA C
Footing Subgrade Compaction / Preparation Detail :
The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of a
non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture
content of the soil. Since the encountered materials are of native, (natural) deposition the water content can be variable
from location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are
utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with
supplied water in order to certify proper compaction in these circumstances.
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/23/21, Partly Cloudy – Mid 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:
FOOTING LINE
FROM – TO
FOOTING
COORDINATE
FOOTING
SIZE and TYPE
BOTTOM
ELEVATION
COMMENTS
H/c3 – H/c17 H / c5 F 7.0 23.0 Complete
H/c3 – H/c17 H / c7 F 9.0 22.7 Complete
H/c3 – H/c17 H / c9 F 6.0 23.2 Complete
H/c3 – H/c17 H / c11 F7.0 23.0 Complete
H/c3 – H/c17 H / c13 F 6.0 23.2 Complete
H/c3 – H/c17 H / c15 F 9.0 22.7 Complete
H/c3 – H/c17 H / c17 F 7.0 23.0 Complete
See Photos:
Preparing Subgrade Footing # H / c7
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/23/21, Partly Cloudy – Mid 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
Grading Crushed Stone Footing # H / c7
Compacting Crushed Stone Footing # H / c7
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/23/21, Partly Cloudy – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
This Report is a summary installation list of installed vibratory stone columns, (VSC), in accordance with Submittal #31
3400-02.0 31 3400 – Aggregate Piers, prepared by CMC Professional Services LLC, 335 E. Geneva Rd #3116, Carol
Stream, Il 60188.
Glossary of Header Terms:
VSC Pier #: Each pier is identified by number according to location plan included in the above referenced
Submittal.
Proposed Depth: Total VSC depth from working grade to proposed bottom elevation as put forth in design
criteria.
Installed Depth: The as-built length of pier as constructed from working grade to termination in suitable native,
(bearing) soil.
Stone Take: The amount of Crushed Stone used in constructing a given Pier, (expressed in volume), one cubic
yard weighs approximately 1.2 Ton.
Comments: Note any deviation from standard installation procedures, proposed depths or changes in location of
said Pier.
Activity for Monday, July 26th, 2021:
VSC Pier # Proposed Depth Installed Depth Stone Take Cu. Yds. Comments
NO PIERS WERE INSTALLED THIS DATE
FOOTING PREPARATION:
THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:
Excavate to six inches below proposed Bottom of Footing Elevation
Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor
Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade
Compact said Crushed Stone
Crushed Stone Base now ready for Footing installation
Activity for Monday, July 26th,2021: AREA C
Footing Subgrade Compaction / Preparation Detail :
The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of a
non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture
content of the soil. Since the encountered materials are of native, (natural) deposition the water content can be variable
from location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are
utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with
supplied water in order to certify proper compaction in these circumstances.
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/23/21, Partly Cloudy – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:
FOOTING LINE
FROM – TO
FOOTING
COORDINATE
FOOTING
SIZE and TYPE
BOTTOM
ELEVATION
COMMENTS
F/c22 – H/c22 F/c22 F 5.0 23.2 Complete
F/c22 – H/c22 F.5/c22 F 4.0 23.2 Complete
F/c22 – H/c22 G.5/c22 F 35.7 x 5 22.7 Complete
H/c17 – H/c21 H/c19 F 7.0 23.0 Complete
See Photos:
Excavating to Subase Footing # G.5/c22
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/23/21, Partly Cloudy – Mid 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
Placing Crushed Stone Footing # G.5/c22
Compacting Crushed Stone Line/Loc. # H/c18
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/27/21, Partly Cloudy – High 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
This Report is a summary installation list of installed vibratory stone columns, (VSC), in accordance with Submittal #31
3400-02.0 31 3400 – Aggregate Piers, prepared by CMC Professional Services LLC, 335 E. Geneva Rd #3116, Carol
Stream, Il 60188.
Glossary of Header Terms:
VSC Pier #: Each pier is identified by number according to location plan included in the above referenced
Submittal.
Proposed Depth: Total VSC depth from working grade to proposed bottom elevation as put forth in design
criteria.
Installed Depth: The as-built length of pier as constructed from working grade to termination in suitable native,
(bearing) soil.
Stone Take: The amount of Crushed Stone used in constructing a given Pier, (expressed in volume), one cubic
yard weighs approximately 1.2 Ton.
Comments: Note any deviation from standard installation procedures, proposed depths or changes in location of
said Pier.
Activity for Tuesday, July 27th, 2021:
VSC Pier # Proposed Depth Installed Depth Stone Take Cu. Yds. Comments
1449* 14 14 1.5 Routine
1448 14 14 1.5 Routine
1447 14 14 1.5 Routine
1450 14 14 1.5 Routine
1451 14 14 1.5 Routine
1452 9 9 1 Routine
1453 9 9 1 Routine
1455 14 14 1.5 Routine
1456 14 14 1.5 Routine
1454 14 14 1.5 Routine
1457 14 14 1.5 Routine
1459 14 14 1.5 Routine
1458 14 14 1.5 Routine
1460 6 6 .7 Routine
1461 6 6 .7 Routine
1462 6 6 .7 Routine
1463 6 6 .7 Routine
1464 6 6 .7 Routine
1465 6 6 .7 Routine
1466 6 6 .7 Routine
1397 9 9 1 Routine
1396 9 9 1 Routine
1399 6 6 .7 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/27/21, Partly Cloudy – High 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
1398 6 6 .7 Routine
1401 6 6 .7 Routine
1400 6 6 .7 Routine
1402 6 6 .7 Routine
1403 9 9 1 Routine
1404 9 9 1 Routine
1406 9 9 1 Routine
1407 9 9 1 Routine
1405 9 9 1 Routine
1409 6 6 .7 Routine
1408 6 6 .7 Routine
1411 6 6 .7 Routine
1410 6 6 .7 Routine
1413 6 6 .7 Routine
1412 6 6 .7 Routine
1415 6 6 .7 Routine
1414 6 6 .7 Routine
1417 6 6 .7 Routine
1416 6 6 .7 Routine
1419 6 6 .7 Routine
1418 6 6 .7 Routine
1367 6 6 .7 Routine
1299 6 6 .7 Routine
1368 6 6 .7 Routine
1300 9 9 1 Routine
1301 9 9 1 Routine
1302 9 9 1 Routine
1369 9 9 1 Routine
1370 6 6 .7 Routine
1303 6 6 .7 Routine
1371 6 6 .7 Routine
1304 6 6 .7 Routine
1372 6 6 .7 Routine
1305 6 6 .7 Routine
1373 6 6 .7 Routine
1306 6 6 .7 Routine
1374 6 6 .7 Routine
1307 6 6 .7 Routine
1375 6 6 .7 Routine
1308 6 6 .7 Routine
1261 9 9 1 Routine
1262 9 9 1 Routine
1203 6 6 .7 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/27/21, Partly Cloudy – High 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
1264 14 14 1.5 Routine
1263 14 14 1.5 Routine
1204 6 6 .7 Routine
1265 14 14 1.5 Routine
1267 14 14 1.5 Routine
1266 14 14 1.5 Routine
1268 6 6 .7 Routine
1205 6 6 .7 Routine
1269 6 6 .7 Routine
1206 6 6 .7 Routine
1270 6 6 .7 Routine
1207 6 6 .7 Routine
1271 9 9 1 Routine
1272 9 9 1 Routine
1208 6 6 .7 Routine
1273 6 6 .7 Routine
1209 6 6 .7 Routine
1274 9 9 1 Routine
1275 9 9 1 Routine
1210 6 6 .7 Routine
1276 6 6 .7 Routine
1211 6 6 .7 Routine
1116 6 6 .7 Routine
1117 6 6 .7 Routine
1118 6 6 .7 Routine
1119 6 6 .7 Routine
1120 6 6 .7 Routine
1121 6 6 .7 Routine
1123 6 6 .7 Routine
1124 6 6 .7 Routine
1083 6 6 .7 Routine
1084 6 6 .7 Routine
1085 6 6 .7 Routine
1086 6 6 .7 Routine
1087 6 6 .7 Routine
1088 6 6 .7 Routine
1089 6 6 .7 Routine
1090 6 6 .7 Routine
1091 6 6 .7 Routine
1164 6 6 .7 Routine
1165 6 6 .7 Routine
1125 6 6 .7 Routine
1166 6 6 .7 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/27/21, Partly Cloudy – High 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
1126 6 6 .7 Routine
1167 6 6 .7 Routine
1127 6 6 .7 Routine
1168 6 6 .7 Routine
1128 6 6 .7 Routine
1169 6 6 .7 Routine
1129 6 6 .7 Routine
1170 6 6 .7 Routine
1130 6 6 .7 Routine
1171 6 6 .7 Routine
1131 6 6 .7 Routine
1172** 6 6 .7 Routine
1132 6 6 .7 Routine
1133 6 6 .7 Routine
1134 14 14 1.5 Routine
1107 14 14 1.5 Routine
1105 14 14 1.5 Routine
1106 14 14 1.5 Routine
1104 14 14 1.5 Routine
1075 14 14 1.5 Routine
1073 14 14 1.5 Routine
1074 14 14 1.5 Routine
1071 10 10 1 Routine
1072 9 9 1 Routine
* Performance Test – Movement = 1/4” – Acceptable
** Performance Test – Movement = 1/8” – Acceptable
Total Piers this day = 134, Total Piers to date = 2012
FOOTING PREPARATION:
THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:
Excavate to six inches below proposed Bottom of Footing Elevation
Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor
Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade
Compact said Crushed Stone
Crushed Stone Base now ready for Footing installation
Activity for Tuesday, July 27th, 2021: AREA “B”
Footing Subgrade Compaction / Preparation Detail :
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/27/21, Partly Cloudy – High 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of a
non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture
content of the soil. Since the encountered materials are of native, (natural) deposition the water content can be variable
from location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are
utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with
supplied water in order to certify proper compaction in these circumstances.
THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:
FOOTING LINE
FROM – TO
FOOTING
COORDINATE
FOOTING
SIZE and TYPE
BOTTOM
ELEVATION
COMMENTS
H.2/b22‐K/b22 H.5/b22 F 5.0 23.2 Complete
H.2/b22‐K/b22 J.3/b22 F 5.0 23.2 Complete
H.2/b25‐K/b25 H.5/b25 F 5.0 23.2 Complete
H.2/b25‐K/b25 J/b25 F 5.0 23.2 Complete
H.2/b25‐K/b25 J.3/b25 F 5.0 23.2 Complete
H.2/b25‐K/b25 J.7/b25 F 5.0 23.2 Complete
H.2/b25‐K/b25 K/b25 F 5.0 23.2 Complete
J/b25.5‐J/b29.9 J/b28 F 5.0 23.2 Complete
J/b25.5‐J/b29.9 J/b29 F 5.0 23.2 Complete
See Photos:
Installing Pier # 1458 to 14’ depth ‐ Area A
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/27/21, Partly Cloudy – High 80’s Caseyville, Il 62232
_________________________________________________________________________________________________
“ Top Dressing “ Pier # 1458
“ Side Dressing “ Pier # 1458
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/28/21, Cloudy – Low 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
This Report is a summary installation list of installed vibratory stone columns, (VSC), in accordance with Submittal #31
3400-02.0 31 3400 – Aggregate Piers, prepared by CMC Professional Services LLC, 335 E. Geneva Rd #3116, Carol
Stream, Il 60188.
Glossary of Header Terms:
VSC Pier #: Each pier is identified by number according to location plan included in the above referenced
Submittal.
Proposed Depth: Total VSC depth from working grade to proposed bottom elevation as put forth in design
criteria.
Installed Depth: The as-built length of pier as constructed from working grade to termination in suitable native,
(bearing) soil.
Stone Take: The amount of Crushed Stone used in constructing a given Pier, (expressed in volume), one cubic
yard weighs approximately 1.2 Ton.
Comments: Note any deviation from standard installation procedures, proposed depths or changes in location of
said Pier.
Activity for Wednesday, July 28th, 2021:
VSC Pier # Proposed Depth Installed Depth Stone Take Cu. Yds. Comments
1115 6 6 .7 Routine
1082 6 6 .7 Routine
1022 11 11 1 Routine
1020 11 11 1 Routine
1021 11 11 1 Routine
1023 9 9 1 Routine
1024 9 9 1 Routine
1025* 14 14 1.5 Routine
1026 14 14 1.5 Routine
1027 14 14 1.5 Routine
1028 14 14 1.5 Routine
1113 9 9 1 Routine
1114 9 9 1 Routine
1112 6 6 .7 Routine
1080 6 6 .7 Routine
1081 6 6 .7 Routine
1019 9 9 1 Routine
1017 6 6 .7 Routine
1018 9 9 1 Routine
1809 6 6 .7 Routine
1011 9 9 1 Routine
1012 9 9 1 Routine
1010 9 9 1 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/28/21, Cloudy – Low 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
1111 6 6 .7 Routine
1110 6 6 .7 Routine
1079 6 6 .7 Routine
1078 6 6 .7 Routine
1016 6 6 .7 Routine
1015 6 6 .7 Routine
1004 6 6 .7 Routine
1006 9 9 1 Routine
1005 9 9 1 Routine
1007 9 9 1 Routine
1008 9 9 1 Routine
1029 9 9 1 Routine
1030 9 9 1 Routine
1031 9 9 1 Routine
1032 9 9 1 Routine
1033 9 9 1 Routine
1034 9 9 1 Routine
1035 9 9 1 Routine
1036 9 9 1 Routine
1037 9 9 1 Routine
1038 9 9 1 Routine
1039 9 9 1 Routine
1040 9 9 1 Routine
1041 9 9 1 Routine
1092 6 6 .7 Routine
1093 9 9 1 Routine
1094 9 9 1 Routine
1095 6 6 .7 Routine
1096 6 6 .7 Routine
1097 10 10 1 Routine
1098 10 10 1 Routine
1099 6 6 .7 Routine
1100 12 12 1.1 Routine
1101 12 12 1.1 Routine
1102 6 6 .7 Routine
1103 6 6 .7 Routine
1042 9 9 1 Routine
1043 9 9 1 Routine
1053 10 10 1 Routine
1054 10 10 1 Routine
1055 6 6 .7 Routine
1044 9 9 1 Routine
1045 9 9 1 Routine
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/28/21, Cloudy – Low 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
1046 9 9 1 Routine
1047 6 6 .7 Routine
1048 9 9 1 Routine
1056 10 10 1 Routine
1057 6 6 .7 Routine
1058 10 10 1 Routine
1049 9 9 1 Routine
1059 6 6 .7 Routine
1060 10 10 1 Routine
1061 10 10 1 Routine
1050 9 9 1 Routine
1062 6 6 .7 Routine
1063 10 10 1 Routine
1051 9 9 1 Routine
1052 9 9 1 Routine
1064 12 12 1.2 Routine
1065 12 12 1.1 Routine
1066 12 12 1.1 Routine
1067 12 12 1.1 Routine
1070 12 12 1.1 Routine
1069 12 12 1.1 Routine
1068 12 12 1.1 Routine
* Performance Test – Movement = 1/8” – Acceptable
Total Piers this day = 88 Total Production Piers to date = 2091
Note: Pier Installation, JOB WIDE, is now Complete.
FOOTING PREPARATION:
THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:
Excavate to six inches below proposed Bottom of Footing Elevation
Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor
Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade
Compact said Crushed Stone
Crushed Stone Base now ready for Footing installation
Activity for Wednesday, July 28th, 2021: AREA “B”
Footing Subgrade Compaction / Preparation Detail :
The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of a
non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/28/21, Cloudy – Low 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
content of the soil. Since the encountered materials are of native, (natural) deposition the water content can be variable
from location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are
utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with
supplied water in order to certify proper compaction in these circumstances.
THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:
FOOTING LINE
FROM – TO
FOOTING
COORDINATE
FOOTING
SIZE and TYPE
BOTTOM
ELEVATION
COMMENTS
J/b30‐J/b32 J/b30 F 5.0 23.2 Complete
J/b30‐J/b32 J/b32 F 5.0 23.2 Complete
J.7/b25.3‐J.7/b33 J.7/b28 F 6.0 23.2 Complete
J.7/b25.3‐J.7/b33 J.7/b29 F 6.0 23.2 Complete
J.7/b25.3‐J.7/b33 J.7/b30 F 6.0 23.2 Complete
J.7/b25.3‐J.7/b33 J.7/b32 F 5.0 23.2 Complete
J/b32‐J.7/b32 Line b32 2.9’ wide Strip 23.2 Complete
J.7/b33‐K.4/b33 K.1/b33 F 5.0 23.2 Complete
See Photos:
Excavating Line J.7 Line Looking East from Footing # J.7/b25, note visible Pier @ Subgrade
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 7/28/21, Cloudy – Low 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
Placing Crushed Stone upon West end of J.7 Line
Compacting Crushed Stone upon said Line