HomeMy WebLinkAboutDYIMS PE Site report 20210805 Architect: Perkins Eastman DPC Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File ARCHITECT’S SITE OBSERVATION REPORT DATE OF VISIT: 08/05/2021 PROJECT: Dennis Yarmouth Intermediate Middle School 286 Station Avenue South Yarmouth, MA 02664 DATE OF ISSUE: 08/09/2021 PROJECT NO: 71011 WEATHER CONDITIONS: CLOUDY, RAINY, 70s ARCHITECT: Perkins Eastman, DPC 20 Ashburton Street 8th floor Boston, MA The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit. WORK IN PROGRESS: 1) Excavation and subgrade prepping for foundations in A and B. 2) (in AM) Preparation for placing concrete for walls and footings (C and B) (work suspended due to rain). 3) Dense grading at east access road. 4) Excavation and laying pipe for sewer force main. 5) Backfill and compaction from manhole 2 to manhole 3 at electrical duct bank for parking lot lights. FIELD OBSERVATIONS: PE visited the site to review ongoing progress with the site work and foundation work. 1. RBO has recently prepared footing lines at areas B and A, including lines at the south area of the gym and was in the process of preparing line W from A1 to A9 on Thursday (see also attached GPI report). 2. Up until they suspended work in the morning due to heavy rain, Marguerite had been making concrete placement preparations for footings in the J / J.7 area of the gym, as well as walls on line H. 3. Up until the rain, National Grid had been on site installing the gas main, but they suspended work. 4. The footprint of the building at Area D inside the foundations has been backfilled and leveled with structural fill; the work was done in accordance with the GAC directive to keep the backfill 12” below TOW; according to Commodore the underground plumbing work at Area D is scheduled to commence on Monday August 9, with underground electrical work to follow immediately behind. 5. Dense grade for surfacing the east road (including above UGI 3 and UGI 7) was done on Wednesday 8-4, and at the time of observation this was ongoing at the very north end of the east access road. 6. The concrete pad for the exterior wall mockup panel has been placed (located just east of the SAE east parking lot). 7. The following structures have been installed around UGI#1: Manholes #25 and #28, Catch basins #19 and #24. 8. Some trees within the limit of work were cleared on Wednesday for the force main extension to the existing treatment plant behind the High School. 9. RBO has installed sewer force main pipe from the lift station to limit of work (fence), and RBO is currently in the process of excavating and laying pipe to extend the force main from there to the treatment plant (see photo). An existing HP line was damaged in the process but will be repaired by RBO. 10. Vibratory stone column installation has been completed, and as of 8-29 CNC is no longer on site. REPORT BY: ABH Page 2 of 3 PROGRESS PHOTOS PAD FOR EXT WALL MOCKUP PANEL DENSE GRADING FOR NEW EAST ACCESS ROAD SEWER FORCE MAIN EXCAVATION PREPARED FOOTING LINE AT P.1 LOOKING WEST (AREA B) PREPARED FOOTING LINE AT A.1 LOOKING NORTH (A) REPORT BY: ABH Page 3 of 3 FORMED AND TIED FOOTINGS AT J.1 AND J.7 (AREA B) LINE D.1/D.2 LOOKING SOUTH (SHOWING FILL) POURED FOOTING AT CORNER C.21/H (AREA C) GERNERAL FOUNDATION WORK VIEW LOOKING EAST (AREA C)    Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 7/29/21, Clear – Low 70’s                                                                                                 Caseyville, Il 62232                                _________________________________________________________________________________________________  FOOTING PREPARATION:    THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:   Excavate to six inches below proposed Bottom of Footing Elevation   Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor   Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade   Compact said Crushed Stone   Crushed Stone Base now ready for Footing installation                                              Activity for Thursday, July 29th, 2021:  AREA “B”    Footing Subgrade Compaction / Preparation Detail :  The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of  non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture  content of the soil. Since the encountered materials are of native, (natural) deposition the water content can vary from  location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are  utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with  supplied water in order to certify proper compaction in these circumstances.  THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:  FOOTING LINE  FROM – TO  FOOTING  COORDINATE  FOOTING  SIZE and TYPE  BOTTOM  ELEVATION   COMMENTS  K.4/b33‐P.1/b33 K.8/b33 F 6.0 23.2 Complete  K.4/b33‐P.1/b33 L.6/b33 F 5.0 23.2 Complete  K.4/b33‐P.1/b33 M.3/b33 F 5.0 23.2 Complete  K.4/b33‐P.1/b33 N/b33 F 6.0 23.2 Complete  K.4/b33‐P.1/b33 N.7/b33 F 5.0 23.2 Complete  Isolated P.2/b32 F 5.0 23.2 Complete  Isolated P.4/b32 F 5.0 23.2 Complete  Isolated P.6/b31 F 5.0 23.2 Complete      See Photos:     Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 7/29/21, Clear – Low 70’s                                                                                                 Caseyville, Il 62232                                _________________________________________________________________________________________________    Completed Footing Line J from j/b32 to J/b25 Looking West      Exposed Piers, prior to subgrade compaction, (typical)         Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 7/29/21, Clear – Low 70’s                                                                                                 Caseyville, Il 62232                                _________________________________________________________________________________________________                            Excavating Southeast Corner Building “B”      Typical Pier revealed in the early phase of excavation     Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 7/30/21, Clear – High 70’s                                                                                                               Caseyville, Il 62232                 _________________________________________________________________________________________________  FOOTING PREPARATION:    THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:   Excavate to six inches below proposed Bottom of Footing Elevation   Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor   Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade   Compact said Crushed Stone   Crushed Stone Base now ready for Footing installation                                              Activity for Friday, July 30th, 2021:  AREA “B”    Footing Subgrade Compaction / Preparation Detail :  The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of  non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture  content of the soil. Since the encountered materials are of native, (natural) deposition the water content can vary from  location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are  utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with  supplied water in order to certify proper compaction in these circumstances.  THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:  FOOTING LINE  FROM – TO  FOOTING  COORDINATE  FOOTING  SIZE and TYPE  BOTTOM  ELEVATION   COMMENTS  P.1/b28‐P.1/b32 P.1/b28 F 6.0 23.2 Complete  P.1/b28‐P.1/b32 P.1/b29 F 6.0 23.2 Complete  P.1/b28‐P.1/b32 P.1/b30 F 6.0 23.2 Complete  P.1/b28‐P.1/b32 P.1/b32 F 5.0 23.2 Complete  P.9/b28‐P.9/a31 P.9/b28 F 5.0 23.2 Complete  P.9/b28‐P.9/a31 P.9/b29 F 5.0 23.2 Complete  P.9/b28‐P.9/a31 P.9/a31 F 5.0 23.2 Complete  Isolated P.8/a32 F 5.0 23.2 Complete  Isolated P.6/a32 F 5.0 23.2 Complete  K.2/b25‐K.4/b25 Line b25 Strip 23.2 Complete    See Photos:       Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 7/30/21, Clear – High 70’s                                                                                                               Caseyville, Il 62232                 _________________________________________________________________________________________________             Preparing Subgrade Footing # P.1/b29      Placing Crushed Stone Footing # P.1/b29     Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 7/30/21, Clear – High 70’s                                                                                                               Caseyville, Il 62232                 _________________________________________________________________________________________________        Grading Crushed Stone Footing# P.1/b29      Compacting Crushed Stone Footing # P.1/b29     Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.                Date on site: 8/3/21, Cloudy – High 70’s                                                                                                               Caseyville, Il 62232                _________________________________________________________________________________________________  FOOTING PREPARATION:    THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:   Excavate to six inches below proposed Bottom of Footing Elevation   Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor   Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade   Compact said Crushed Stone   Crushed Stone Base now ready for Footing installation                                              Activity for Tuesday, August 3rd, 2021:  AREA “A “  Footing Subgrade Compaction / Preparation Detail :  The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of  non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture  content of the soil. Since the encountered materials are of native, (natural) deposition the water content can vary from  location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are  utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with  supplied water in order to certify proper compaction in these circumstances.  THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:  FOOTING LINE  FROM – TO  FOOTING  COORDINATE  FOOTING  SIZE and TYPE  BOTTOM  ELEVATION   COMMENTS  a1/W‐a1/V a1/W F 5.0 23.2 Complete  a1/W‐a1/V a1/V.5 F 5.0 23.2 Complete  a1/W‐a1/V a1/V F 5.0 23.2 Complete  A2/U‐a2/R a2/U F 7.0 23.0 Complete  A2/U‐a2/R a2/T F 8.0 22.9 Complete  A2/U‐a2/R a2/S.2 F 6.0 23.2 Complete  A2/U‐a2/R a2/R F 5.0 23.2 Complete        See Photos:         Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.                Date on site: 8/3/21, Cloudy – High 70’s                                                                                                               Caseyville, Il 62232                _________________________________________________________________________________________________        Grading Crushed Stone # a1/W      Compacting Subgrade # a1/V     Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.                Date on site: 8/3/21, Cloudy – High 70’s                                                                                                               Caseyville, Il 62232                _________________________________________________________________________________________________      Compacting Crushed Stone along Line a1                            Completed Footing Line # a1/W – a1/V     Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 8/4/21, Drizzle – Low 70’s                                                                                                               Caseyville, Il 62232                 _________________________________________________________________________________________________  FOOTING PREPARATION:    THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:   Excavate to six inches below proposed Bottom of Footing Elevation   Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor   Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade   Compact said Crushed Stone   Crushed Stone Base now ready for Footing installation                                              Activity for Wednesday, August 4th, 2021:  AREA “A “  Footing Subgrade Compaction / Preparation Detail :  The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of  non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture  content of the soil. Since the encountered materials are of native, (natural) deposition the water content can vary from  location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are  utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with  supplied water in order to certify proper compaction in these circumstances.    THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:  FOOTING LINE  FROM – TO  FOOTING  COORDINATE  FOOTING  SIZE and TYPE  BOTTOM  ELEVATION   COMMENTS  b2/N.9 – b2/L.9 b2/N.9 F 5.0 23.2 Complete  b2/N.9 – b2/L.9 b2/M.9 F 5.0 21.7 Complete  b2/N.9 – b2/L.9 b2/L.9 F 6.0 21.7 Complete  Loading Dock  Configuration  Refer to Bldg. “A”  Foundation Plan  Multiple Strip  Footings  19.7 Partial  Installation      See Photos:           Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 8/4/21, Drizzle – Low 70’s                                                                                                               Caseyville, Il 62232                 _________________________________________________________________________________________________      Excavation – Loading Dock    Subgrade Prep – Loading Dock         Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 8/4/21, Drizzle – Low 70’s                                                                                                               Caseyville, Il 62232                 _________________________________________________________________________________________________      Crushed Stone Grading (Partial) – Loading Dock    Compacting Crushed Stone, Loading Dock, (Partial) South End, Looking Southwest     Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.                Date on site: 8/5/21, Rain – Low 70’s                                                                                                               Caseyville, Il 62232                     _________________________________________________________________________________________________  FOOTING PREPARATION:    THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:   Excavate to six inches below proposed Bottom of Footing Elevation   Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor   Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade   Compact said Crushed Stone   Crushed Stone Base now ready for Footing installation                                              Activity for Thursday, August 5th, 2021:  AREA “A “  Footing Subgrade Compaction / Preparation Detail :  The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of  non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture  content of the soil. Since the encountered materials are of native, (natural) deposition the water content can vary from  location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are  utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with  supplied water in order to certify proper compaction in these circumstances.      THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:  FOOTING LINE  FROM – TO  FOOTING  COORDINATE  FOOTING  SIZE and TYPE  BOTTOM  ELEVATION   COMMENTS  W/a1 – W/a9 a3/W F 5.0 23.2 Complete  W/a1 – W/a9 a5/W F 5.0 23.2 Complete  W/a1 – W/a9 a6/W F 5.0 23.2 Complete  W/a1 – W/a9 a8/W F 5.0 23.2 Complete  W/a1 – W/a9 a9/W F 5.0 23.2 Complete      See Photos:         Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.                Date on site: 8/5/21, Rain – Low 70’s                                                                                                               Caseyville, Il 62232                     _________________________________________________________________________________________________      Excavating Line “W” at a1/W Looking East      Compacting Subgrade along Line “W”       Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.                Date on site: 8/5/21, Rain – Low 70’s                                                                                                               Caseyville, Il 62232                     _________________________________________________________________________________________________        Placing Crushed Stone upon same      Compacting Crushed Stone along Line “W” including Footing # a3/W