The existing bathroom layout will remain the same.
Existing tub will be refinished. Tub/shower trim,
mixing valve, and trip level drain will be replaced.
Water supply lines and waste piping will not be changed
Existing sink will be removed. New vanity and under -
mount sink will be installed in same position. New
faucet and water shutoff valves will be installed.
Water supply lines and waste piping in wall will not
be changed,
Existing toilet will be removed and stored, and then
reinstalled in same position after drywall, painting
and floor tiling is completed. Water supply line and
waste piping will not be changed.
Plumbing Work:
Disconnect fixtures (sink,
toilet and tub) from water
supply and waste piping.
Remove existing sink and
install new sink with new
shutoff valves after new
vanity is installed.
Remove toilet and store
Reinstall toilet after
floor tilinq is completed.
Replace tub drain and
shower and tub trim.
Dining
Install wall
tile above
tub.
Refinish exist.
tub after wall
& floor tiling
is completed. --
S
E W
N
FIRST FLOOR PLAN
Owners: Robert & Shirley Letourneau
Living Room
Other Work:
Remove existing drywall,
wall tiles, and insulation.
Install new insulation and
drywall.
Door and window trim will
be removed and replaced.
Remove existing ceiling
drywall and insulation
and replace with new
drywall and insulation.
Remove vanity and sink.
Install new vanity and
sink after drywall and
floor tiling is
Bedroom
Remove and replace
approx. 90 sq. ft. of
white cedar shingles.
Master Closet
MccC-UID
MAY 20 2021
HEALTH DEPT.
Electrical Work:
Remove three ceiling lights.
Install two ceiling lights
and two wall sconces.
Replace GFCI outlet.
Replace light switches
and wiring as necessary.
Master Bedroom
GUEST BATHROOM
RENOVATIONS
FIRST FLOOR PLAN
5 PAR THREE DRIVE
SOUTH YARMOUTH, MA
OWNERS: ROBERT & SHIRLEY
LETOURNEAU
REVISED MAY 17, 2021