HomeMy WebLinkAboutDYIMS PE Site report 20210819 Architect: Perkins Eastman DPC Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File ARCHITECT’S SITE OBSERVATION REPORT DATE OF VISIT: 08/19/2021 PROJECT: Dennis Yarmouth Intermediate Middle School 286 Station Avenue South Yarmouth, MA 02664 DATE OF ISSUE: 08/20/2021 PROJECT NO: 71011 WEATHER CONDITIONS: CLOUDY, SPRINKLING, 70s ARCHITECT: Perkins Eastman, DPC 20 Ashburton Street 8th floor Boston, MA The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit. WORK IN PROGRESS: 1) Ongoing underground plumbing work in Area D. 2) Excavation and subgrade prepping for foundations in Area A and Area B (simultaneously). 3) Preparation for concrete placement in Area B. 4) Completing underground infiltration structure no. 2 5) Electrical tie-in at transformer pad by Anesse. 6) Layout work for parking lot striping FIELD OBSERVATIONS: PE visited the site to review ongoing progress with the site work and foundation work. 1. RBO is preparing the subgrade for the foundation for the double slab at the underfloor HVAC ductwork in the lower orchestra area of the auditorium, including the haunched footings for the block walls that support the floor slab (see photo, and see also GPI reports for 8/18 and 8/19). Since the last PE report RBO completed prepping wall footings on lines W/A.15 (music wing) and interior column footings in the same general area. 2. RBO is completing the placement of the cultec structures at the underground infiltration structure no. 2. 3. RBO has placed asphalt at the east access road, the utility corridor next to the administration building, and at the main parking area (see photos). 4. Underground plumbing work is in progress at Area D, with underground electrical work to follow immediately behind (see photo). 5. Building D foundation wall damp-proofing is completed; placement of foundation insulation is scheduled to begin next week according to Commodore. 6. Area C foundations have been placed, minus a few piers in the center. 7. Marguerite is tying rebar and making other Area B wall placement preparations on lines B2.4/B2.5 and P.1, as well as at the future perimeter along lines P.6/P.9 and a3.2/b3.2. (i.e. at the south and east walls of the main gym and at the ancillary area to the south of the gym). 8. Brennan is Installing controls at Area C for as-builts on anchor bolts that will be sent to Norgate for coordination. 9. The exterior mockup panel is framed, and has been completely sheathed --appearing ready for WRM installation. 10. The 8 inch water main that connects out from behind the school was tied in on 8/18. 11. Anesse has placed the main electrical ductbank and conduit up to the transformer pad, and is in the process of installing the sweeps for the connections to the future transformer (see photo). 12. Commodore reports that the Area D steel is in fabrication, and that Norgate is on schedule to commence steel erection on September 13. REPORT BY: ABH Page 2 of 3 PROGRESS PHOTOS PAVED UTILITY CORRIDOR (FUTURE WEST ENTRANCE) PAVEMENT AT MAIN PARKING LOT STRIPPED TOP SOIL AT FUTURE STATION AVE FIELD CONDUIT INSTALLATION AT FUTURE TRANFORMER PAD FOOTING PREP FOR CMU KNEE WALL FOOTINGS (AUDITORIUM) UNDERGROUND PLUMBING PROGRESS (AREA D) INSTALLATION OF UGI #2 REPORT BY: ABH Page 3 of 3 STRIPPED ELEVATOR PIT WALLS AT AREA C FOUNDATION @ WIXON COURTWARD (BETWEEN D & C) FOOTING PLACED 8-18 AT @ K-B.22 (AREA B BY GYM) WALLS PLACED 8-18 @ LINES B3.2, B3.3 & J.7 (GYM N.E.) REBAR ABOVE FOOTING PEN. FOR RWL (B.25 – P.1) WALL REBAR PREPARATIONS @ B3.2/B3.0 AND P.6/P.9    Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.                Date on site: 8/13/21, Humid – Low 80’s                                                                                                             Caseyville, Il 62232                 _________________________________________________________________________________________________  FOOTING PREPARATION:    THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:   Excavate to six inches below proposed Bottom of Footing Elevation   Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor   Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade   Compact said Crushed Stone   Crushed Stone Base now ready for Footing installation                                                Activity for Friday, August 13th, 2021:  AREA “A “    Footing Subgrade Compaction / Preparation Detail :  The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of  non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture  content of the soil. Since the encountered materials are of native, (natural) deposition the water content can vary from  location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are  utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with  supplied water in order to certify proper compaction in these circumstances.    THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:  FOOTING LINE  FROM – TO  FOOTING  COORDINATE  FOOTING  SIZE and TYPE  BOTTOM  ELEVATION   COMMENTS  a6.3/T.7 – a5.4/T.7 Strip 3’ Wide 23.2 Complete  a5/T – a5/S Strip 3’ Wide 23.2 Complete  Isolated a6/V F 5.0 23.2 Complete  Isolated a6/U F 9.0 22.7 Complete  Isolated a5/T.1 F 5.0 23.2 Complete  Isolated a5/S F 5.0 23.2 Complete      See Photos:     Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.                Date on site: 8/13/21, Humid – Low 80’s                                                                                                             Caseyville, Il 62232                 _________________________________________________________________________________________________      Excavating South End of Line a5.4      Placing Crushed Stone – South End Line a5.4       Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.                Date on site: 8/13/21, Humid – Low 80’s                                                                                                             Caseyville, Il 62232                 _________________________________________________________________________________________________      Grading Crushed Stone South End Line a5.4       Compacting Crushed Stone Line a5.4      Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 8/16/21, Partly Cloudy – Low 80’s                                                                                                 Caseyville, Il 62232                 _________________________________________________________________________________________________  FOOTING PREPARATION:    THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:   Excavate to six inches below proposed Bottom of Footing Elevation   Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor   Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade   Compact said Crushed Stone   Crushed Stone Base now ready for Footing installation                                                Activity for Monday, August 16th, 2021:  AREA “A “    Footing Subgrade Compaction / Preparation Detail :  The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of  non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture  content of the soil. Since the encountered materials are of native, (natural) deposition the water content can vary from  location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are  utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with  supplied water in order to certify proper compaction in these circumstances.    THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:  FOOTING LINE  FROM – TO  FOOTING  COORDINATE  FOOTING  SIZE and TYPE  BOTTOM  ELEVATION   COMMENTS  Isolated a8/V F 5.0 23.2 Complete  Isolated a7/U F 7.0 23.0 Complete  Isolated a5.4/S.8 F 3.0 24.1 Complete  Isolated a5.4/S.6 F 3.0 24.1 Complete  Isolated a5.4/S.5 F 3.0 24.1 Complete  Isolated a5.4/S.2 F 3.0 24.1 Complete    See Photos:       Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 8/16/21, Partly Cloudy – Low 80’s                                                                                                 Caseyville, Il 62232                 _________________________________________________________________________________________________      Excavating Footing a8/V                        Preparing Subgrade Footing a8/V         Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 8/16/21, Partly Cloudy – Low 80’s                                                                                                 Caseyville, Il 62232                 _________________________________________________________________________________________________      Grading Crushed Stone Footing a8/V    Compacting Crushed Stone Footing a8/V     Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 8/17/21, Partly Cloudy – High 70’s                                                                                                 Caseyville, Il 62232                _________________________________________________________________________________________________  FOOTING PREPARATION:    THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:   Excavate to six inches below proposed Bottom of Footing Elevation   Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor   Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade   Compact said Crushed Stone   Crushed Stone Base now ready for Footing installation                                                Activity for Tuesday, August 17th, 2021  AREA “A “    Footing Subgrade Compaction / Preparation Detail :  The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of  non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture  content of the soil. Since the encountered materials are of native, (natural) deposition the water content can vary from  location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are  utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with  supplied water in order to certify proper compaction in these circumstances.    THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:  FOOTING LINE  FROM – TO  FOOTING  COORDINATE  FOOTING  SIZE and TYPE  BOTTOM  ELEVATION   COMMENTS    NOTE: The Footings depicted in this report are Haunch Footings, the area constructed is not conducive to report in the  routine format presented in the above referenced table since the size and configuration is typically variable. There are  fifteen such footings proposed, encompassing 32 VSC Piers. Their location can approximately be defined as an area  bounded in four corners by the exiting plan coordinate system, NE corner‐a5.7/R, SE corner‐a8/T.7, NW corner‐a5.7/T.4,  and SW corner a.8/T.7. Please refer to Foundation Plan # S‐1.11A for more detailed information. The photos included  show the footing area in partial stages of construction, and of this date are not yet complete.    See two photographs:     Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 8/17/21, Partly Cloudy – High 70’s                                                                                                 Caseyville, Il 62232                _________________________________________________________________________________________________      Overview of  Haunch Footing Area, Subgrade, Looking North    Placing Crushed Stone in said area, Southwest Corner     Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 8/18/21, Partly Cloudy – High 70’s                                                                                                 Caseyville, Il 62232                _________________________________________________________________________________________________    FOOTING PREPARATION:  THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:   Excavate to six inches below proposed Bottom of Footing Elevation   Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor   Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade   Compact said Crushed Stone   Crushed Stone Base now ready for Footing installation                                            Activity for Wednesday, August 18th, 2021  AREA “A “  Footing Subgrade Compaction / Preparation Detail :  The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of  non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture  content of the soil. Since the encountered materials are of native, (natural) deposition the water content can vary from  location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are  utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with  supplied water in order to certify proper compaction in these circumstances.    THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:  FOOTING LINE  FROM – TO  FOOTING  COORDINATE  FOOTING  SIZE and TYPE  BOTTOM  ELEVATION   COMMENTS    NOTE: The Footings depicted in this report are Haunch Footings, the area constructed is not conducive to report in the  routine format presented in the above referenced table since the size and configuration is typically variable. There are  fifteen such footings proposed, encompassing 32 VSC Piers. Their location can approximately be defined as an area  bounded in four corners by the exiting plan coordinate system, NE corner‐a5.7/R, SE corner‐a8/T.7, NW corner‐a5.7/T.4,  and SW corner a.8/T.7. Please refer to Foundation Plan # S‐1.11A for more detailed information. The photos included  show the footing area in partial stages of construction, and of this date are not yet complete.    Haunch Footing Specifications :  Typical 20 inch wide X 8 inch deep – length and alignment configuration varies  according to location and application. The Compacted Crushed Stone  not only underlies the footing as a base but also  acts as the confinement, i.e. the form for the concrete placement. The haunchs are hewn out of the Crushed Stone in  the 8” X 20” size configuration – visible in the attached photographs. Haunch preparation is approximately 65%  complete.       Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 8/18/21, Partly Cloudy – High 70’s                                                                                                 Caseyville, Il 62232                _________________________________________________________________________________________________    See Attached:    Overview – constructing crushed stone base      Individual haunch cut out of crushed stone – now fully dressed and ready foe concrete placement     Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 8/18/21, Partly Cloudy – High 70’s                                                                                                 Caseyville, Il 62232                _________________________________________________________________________________________________          View multiple rows – shown in larger format in order to enhance detail     Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.                Date on site: 8/19/21, Showers – High 70’s                                                                                                 Caseyville, Il 62232                         _________________________________________________________________________________________________  FOOTING PREPARATION:  THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:   Excavate to six inches below proposed Bottom of Footing Elevation   Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor   Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade   Compact said Crushed Stone   Crushed Stone Base now ready for Footing installation                                            Activity for Thursday, August 19th, 2021  AREA “A “  Footing Subgrade Compaction / Preparation Detail :  The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of  non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture  content of the soil. Since the encountered materials are of native, (natural) deposition the water content can vary from  location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are  utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with  supplied water in order to certify proper compaction in these circumstances.    THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:  FOOTING LINE  FROM – TO  FOOTING  COORDINATE  FOOTING  SIZE and TYPE  BOTTOM  ELEVATION   COMMENTS  Isolated a5.7/P F 7.5 X 29 22.7 Complete    NOTE: The Footings depicted in this report are Haunch Footings, the area constructed is not conducive to report in the  routine format presented in the above referenced table since the size and configuration is typically variable. There are  fifteen such footings proposed, encompassing 32 VSC Piers. Their location can approximately be defined as an area  bounded in four corners by the exiting plan coordinate system, NE corner‐a5.7/R, SE corner‐a8/T.7, NW corner‐a5.7/T.4,  and SW corner a.8/T.7. Please refer to Foundation Plan # S‐1.11A for more detailed information. The photos included  show the footing area in partial stages of construction, and of this date are not yet complete.    Haunch Footing Specifications :  Typical 20 inch wide X 8 inch deep – length and alignment configuration varies  according to location and application. The Compacted Crushed Stone  not only underlies the footing as a base but also  acts as the confinement, i.e. the form for the concrete placement. The haunchs are hewn out of the Crushed Stone in  the 8” X 20” size configuration – visible in the attached photographs. Haunch preparation is 100% COMPLETE.  See two Photos:     Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.                Date on site: 8/19/21, Showers – High 70’s                                                                                                 Caseyville, Il 62232                         _________________________________________________________________________________________________      Further Haunch Footing Construction    Completing Final Rows – Haunch Footings