HomeMy WebLinkAboutJ5951-11 Dennis Yarmouth Middle School WE 2021-08-13Summary Report #11
August 16, 2021
Job No: 5951
Job Name:Dennis Yarmouth Middle School
296 Station Ave
South Yarmouth, MA 02664
Application No.:
TESTING
INSPECTION
ENGINEERING
EM
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
August 9, 2021
Arsene Ntwali reported to Mitch Miller with PMA at the jobsite. Performed soils compaction testing. No Samples Taken. See attached.
Arsene Ntwali performed reinforcing steel placement inspection. See attached.
The work observed was, to the best of Arsene's knowledge, in accordance with the approved plans, specifications and applicable standards of
workmanship.
August 10, 2021
Arsene Ntwali reported to Mitch Miller with PMA at the jobsite. Performed concrete placement and sampling inspection. Concrete sample(s)
obtained: (5) per set, (1) set(s), (5) total. See attached.
Arsene Ntwali performed soils compaction testing. No Samples Taken. See attached.
The work observed was, to the best of Arsene's knowledge, in accordance with the approved plans, specifications and applicable standards of
workmanship.
August 11, 2021
Arsene Ntwali reported to Mitch Miller with PMA at the jobsite. Performed soils compaction testing. Soil samples obtained: (1) total. See attached.
The work observed was, to the best of Arsene's knowledge, in accordance with the approved plans, specifications and applicable standards of
workmanship.
John Lydstone picked up (15) concrete cylinders from the jobsite.
August 12, 2021
Arsene Ntwali reported to Mitch Miller with PMA at the jobsite. Performed soils compaction testing. No Samples Taken. See attached.
Arsene Ntwali performed reinforcing steel placement inspection. See attached.
The work observed was, to the best of Arsene's knowledge, in accordance with the approved plans, specifications and applicable standards of
TESTING
INSPECTION
ENGINEERING
EM
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
workmanship.
John Lydstone picked up (2) buckets of soil from the jobsite.
August 13, 2021
Arsene Ntwali reported to Mitch Miller with PMA at the jobsite. Performed concrete placement and sampling inspection. Concrete sample(s)
obtained: (5) per set, (2) set(s), (10) total. See attached.
Arsene Ntwali performed observation of earthwork activities. No Samples Taken. See attached.
The work observed was, to the best of Arsene's knowledge, in accordance with the approved plans, specifications and applicable standards of
workmanship.
Laboratory test results are enclosed if testing was done during the period covered by this report.
Limitations: These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as
acceptance or guarantee of the work. Even with diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the
code.
Reviewed by:
Enea Mushi
Project Manager
08-25-2021
Date
Technical Contact: Bruce Tie, Engineering Manager (btie@fenaghengineering.com)
Administrative Contact: Andrew Kelley (akelley@fenaghengineering.com)
TESTING
INSPECTION
ENGINEERING
Soils Compaction
FET Project #: 5951
Project Name: Dennis Yarmouth Middle School TAA #: NA
Inspection Address: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Arsene Ntwali
August 9, 2021
Time In: 07:00 Time Out: 15:00
Weather: Sunny
Temperature: 83°F
Permit No. :
Plans Dated: 03/26/2021
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable
standards of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
Arsene Ntwali
Inspector
08-09-2021
Date Enea Mushi
Project Manager
08-16-2021
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Arsene Ntwali reported to Mitch Miller with PMA at the jobsite. Performed soils compaction testing. Equipment used was Plate
compactor , excavator , Dozer. No samples taken.
Density Std (DS):
2537
Moisture Std (MS):
472
Specified Compaction:
95%
Soils Report prepared by:
Fenagh Engineering
Source of Fill:
Native:
General Location of Fill:
Building D
Nuclear Gauge:
Humbolt HS-5001EZ 5200
calibration expiration date 09/2021
Soils Report Dated:
06-07-2021
Results Reported to:
Mitch Miller
Equipment Observed:
Compaction: Plate compactor
Excavation: excavator
Earthwork: Dozer
Description of material Reference CurveID Lab Log ID Max Dry Density(pcf)Optimum Moisture
Loose Glacial 1 S774 115.8 10
Test#Test Location Probe
Depth (in)
Test Elev.
(ft)
Ref.
Curve
Used
Test Dry
Density (lbs/cu.
ft.)
Test Moisture
(%)
Compaction
(95%)
(%)
Comments
1 D.5/d8 6 -4 TOW 1 110.2 5.0 95 Pass
2 E/d8 6 -3 TOW 1 111.5 5.9 96 Pass
TESTING
INSPECTION
ENGINEERING
Project No: 5951
Project Name: Dennis Yarmouth Middle School
Project Location: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Arsene Ntwali
Inspection Type: Reinforcing Steel Placement
Pg. 1 of 1
August 9, 2021
Time In: 11:00 Time Out: 12:00
Weather: Sunny
Temperature: 83°F
Permit No. :
Plans Dated: 06/11/2021
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable
standards of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
Arsene Ntwali
Inspector
08-09-2021
Date Enea Mushi
Project Manager
08-16-2021
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Additional Notes: Foundation: J.7-N/b33, c18-22/E, E-F.5/c22rnWall: G-H/c21, c17-21/H
Arsene Ntwali reported to Mitch Miller with PMA at the jobsite. Observed placement of reinforcing steel for L1 footings at
J.7-N/b33, c18-22/E, E-F.5/c22. Work complete. Reference detail Sheet R008, R007.
Reinforcing Steel and Anchor Bolts
Y N Y N
Rebar Installed Per Approved Details ✓General Notes And Typical Details Reviewed ✓
Rebar The Proper Size ✓Rebar The Proper Type/grade ✓
Rebar Spacing Acceptable ✓Min Clearances Achieved Around Rebar ✓
Min Lap Splice Lengths Achieved ✓Additional Required Rebar Has Been Placed ✓
Coupler/t-heads Torque Tested If Applicable ✓Coupler/t-heads Placed Per Approved Details If Applicable ✓
Rebar Testing Complete And Passed If Required ✓
TESTING
INSPECTION
ENGINEERING
Project No: 5951
Project Name: Dennis Yarmouth Middle School
Project Location: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Arsene Ntwali
Inspection Type: Concrete Placement and Sampling
Pg. 1 of 1
August 10, 2021
Time In: 07:00 Time Out: 09:00
Weather: Sunny
Temperature: 80°F
Permit No. :
Plans Dated: 05/19/2021
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable
standards of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
Arsene Ntwali
Inspector
08-10-2021
Date Enea Mushi
Project Manager
08-16-2021
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Arsene Ntwali reported to Mitch Miller with PMA at the jobsite. Observed placement of and performed sampling of concrete for
Level 1, wall(s) at Building C and B (mix no. 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified
air content from 4.5% to 7.5%, and 55 cubic yards placed). Monitored loads for mix no., slump, temp., and time limit. Prepared 4x8"
cylinder test specimens sampled from TRUCK DISCHARGE.
Set
No.
Slump
(in.)
Mix
Temp.
(°F)
Air Temp.
(°F)
Air Content
(%)
Unit Weight
(pcf)
Truck
No.Location Qty. of
Samples Batch Time Sample Time Subcontractor Ticket
No.
1 5.75 71 70 5.7 144.7 73 C18/E 5 7:00 AM 7:45 AM Marguerite 3133
9
5 Total
Additional Notes: Foundation: J.7-N/b33, c18-22/E, E-F.5/c22rnWall: G-H/c21, c17-21/H
Referenced Details: Mix Design 3500D-3/4 Design Concrete
TESTING
INSPECTION
ENGINEERING
Soils Compaction
FET Project #: 5951
Project Name: Dennis Yarmouth Middle School TAA #: NA
Inspection Address: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Arsene Ntwali
August 10, 2021
Time In: 09:00 Time Out: 15:00
Weather: Sunny
Temperature: 80°F
Permit No. :
Plans Dated: 03/26/2021
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable
standards of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
Arsene Ntwali
Inspector
08-10-2021
Date Enea Mushi
Project Manager
08-16-2021
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Arsene Ntwali reported to Mitch Miller with PMA at the jobsite. Performed soils compaction testing. Equipment used was Plate
compactor , excavator . No samples taken.
Density Std (DS):
2535
Moisture Std (MS):
475
Specified Compaction:
95%
Soils Report prepared by:
Fenagh Engineering
Source of Fill:
Native:
General Location of Fill:
Electrical line by Gate B
Nuclear Gauge:
Humbolt HS-5001EZ 5200
calibration expiration date 09/2021
Soils Report Dated:
06-07-2021
Results Reported to:
Mitch Miller
Equipment Observed:
Compaction: Plate compactor
Excavation: excavator
Earthwork:
Description of material Reference CurveID Lab Log ID Max Dry Density(pcf)Optimum Moisture
Loose Glacial 1 S774 115.8 10
Test#Test Location Probe
Depth (in)
Test
Elev. (ft)
Ref.
Curve
Used
Test Dry Density
(lbs/cu. ft.)
Test Moisture
(%)
Compaction
(95%)
(%)
Comments
1 Electric line 6 22 1 110.8 5.7 96 Pass
2 Electric line 6 23 1 110.5 5.5 95 Pass
TESTING
INSPECTION
ENGINEERING
Soils Compaction
FET Project #: 5951
Project Name: Dennis Yarmouth Middle School TAA #: NA
Inspection Address: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Arsene Ntwali
August 11, 2021
Time In: 07:00 Time Out: 15:00
Weather: Sunny
Temperature: 75°F
Permit No. :
Plans Dated: 03/26/2021
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable
standards of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
Arsene Ntwali
Inspector
08-11-2021
Date Enea Mushi
Project Manager
08-16-2021
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Arsene Ntwali reported to Mitch Miller with PMA at the jobsite. Performed soils compaction testing. Equipment used was Plate
compactor , excavator . Obtained (1) sample(s).
Dense Grade structural fill from Stockpile on site Test required: ASTM D1557 Moisture-Density Relations of Soil Using Modified
Effort (Modified Proctor).
Density Std (DS):
2542
Moisture Std (MS):
478
Specified Compaction:
95%
Soils Report prepared by:
Fenagh Engineering
Source of Fill:
Native:
General Location of Fill:
Grease trap catch base
Nuclear Gauge:
Humbolt HS-5001EZ 5200
calibration expiration date 09/2021
Soils Report Dated:
06-07-2021
Results Reported to:
Mitch Miller
Equipment Observed:
Compaction: Plate compactor
Excavation: excavator
Earthwork:
Description of material Reference CurveID Lab Log ID Max Dry Density(pcf)Optimum Moisture
Loose Glacial 1 S774 115.8 10
Test#Test Location Probe
Depth (in)
Test
Elev. (ft)
Ref.
Curve
Used
Test Dry Density
(lbs/cu. ft.)
Test Moisture
(%)
Compaction
(95%)
(%)
Comments
1 DGCB #5 6 22 1 111.4 5.2 96 Pass
2 DGCB #5 6 23 1 111.1 5.9 96 Pass
Daily Pick Up Report
Job Number: Project Name:
Fenagh Representative: Date:
Cylinders
Shotcrete
Grout
Mortar
Grout Cubes
Prisms
PT Cables
Fireproofing Samples
Soil Samples
Rebar Samples
Steel Plates
Other
Additional Comments:
Job Site Shop Batch Plant/Quarry Other: ________
Cure Box Temp: ______ High/Low Temp: ________ Outside Temp: ______
Dennis-Yarmouth MS 5951
John Lydstone 08/11/2021
n
NA 75
15
NA
TESTING
INSPECTION
ENGINEERING
Soils Compaction
FET Project #: 5951
Project Name: Dennis Yarmouth Middle School TAA #: NA
Inspection Address: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Arsene Ntwali
August 12, 2021
Time In: 07:00 Time Out: 15:00
Weather: Sunny
Temperature: 78°F
Permit No. :
Plans Dated: 03/26/2021
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable
standards of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
Arsene Ntwali
Inspector
08-12-2021
Date Enea Mushi
Project Manager
08-16-2021
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Arsene Ntwali reported to Mitch Miller with PMA at the jobsite. Performed soils compaction testing. Equipment used was Plate
compactor , excavator , Dozer. No samples taken.
Density Std (DS):
2538
Moisture Std (MS):
472
Specified Compaction:
95%
Soils Report prepared by:
Fenagh Engineering
Source of Fill:
Import:
General Location of Fill:
Buildin D
Nuclear Gauge:
Humbolt HS-5001EZ 5200
calibration expiration date 09/2021
Soils Report Dated:
06-07-2021
Results Reported to:
Mitch Miller
Equipment Observed:
Compaction: Plate compactor
Excavation: excavator
Earthwork: Dozer
Description of material Reference CurveID Lab Log ID Max Dry Density(pcf)Optimum Moisture
R.B.O Structural fill 1 C-185b 130.4 8.2
Test#Test Location
Probe
Depth
(in)
Test Elev.
(ft)
Ref.
Curve
Used
Test Dry
Density (lbs/cu.
ft.)
Test Moisture
(%)
Compaction
(95%)
(%)
Comments
1 B/d4 6 -2 TOW 1 125.0 5.4 96 Pass
2 A/d2 6 -1 TOW 1 125.7 5.0 96 Pass
3 D/d3 6 -1 TOW 1 124.2 5.9 95 Pass
Additional Notes: Proctor provided by PMA.
TESTING
INSPECTION
ENGINEERING
Project No: 5951
Project Name: Dennis Yarmouth Middle School
Project Location: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Arsene Ntwali
Inspection Type: Reinforcing Steel Placement
Pg. 1 of 1
August 12, 2021
Time In: 11:00 Time Out: 12:00
Weather: Sunny
Temperature: 78°F
Permit No. :
Plans Dated: 06/11/2021
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable
standards of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
Arsene Ntwali
Inspector
08-12-2021
Date Enea Mushi
Project Manager
08-16-2021
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Additional Notes: Wall: J-J.3/b24,b24-31/JrnFoundation: K-N.7/b24, b24-33/P, P.3-P.4/b32, N.4-P.2/b33
Arsene Ntwali reported to Mitch Miller with PMA at the jobsite. Observed placement of reinforcing steel for L1 wall(s) at
Wall: J-J.3/b24,b24-31/J Foundation: K-N.7/b24, b24-33/P, P.3-P.4/b32, N.4-P.2/b33. Work complete. Reference detail Sheet
R007, R013.
Reinforcing Steel and Anchor Bolts
Y N Y N
Rebar Installed Per Approved Details ✓General Notes And Typical Details Reviewed ✓
Rebar The Proper Size ✓Rebar The Proper Type/grade ✓
Rebar Spacing Acceptable ✓Min Clearances Achieved Around Rebar ✓
Min Lap Splice Lengths Achieved ✓Additional Required Rebar Has Been Placed ✓
Coupler/t-heads Torque Tested If Applicable ✓Coupler/t-heads Placed Per Approved Details If Applicable ✓
Rebar Testing Complete And Passed If Required ✓
Daily Pick Up Report
Job Number: Project Name:
Fenagh Representative: Date:
Cylinders
Shotcrete
Grout
Mortar
Grout Cubes
Prisms
PT Cables
Fireproofing Samples
Soil Samples
Rebar Samples
Steel Plates
Other
Additional Comments:
Job Site Shop Batch Plant/Quarry Other: ________
Cure Box Temp: ______ High/Low Temp: ________ Outside Temp: ______
Dennis-Yarmouth MS 5951
John Lydstone 08/12/2021
n
NA 79
2 buckets of soil
NA
TESTING
INSPECTION
ENGINEERING
Project No: 5951
Project Name: Dennis Yarmouth Middle School
Project Location: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Arsene Ntwali
Inspection Type: Concrete Placement and Sampling
Pg. 1 of 1
August 13, 2021
Time In: 07:00 Time Out: 10:00
Weather: Sunny
Temperature: 80°F
Permit No. :
Plans Dated: 05/19/2021
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable
standards of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
Arsene Ntwali
Inspector
08-13-2021
Date Enea Mushi
Project Manager
08-16-2021
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Arsene Ntwali reported to Mitch Miller with PMA at the jobsite. Observed placement of and performed sampling of concrete for
Level 1, footings at Building B (mix no. 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air
content from 4.5% to 7.5%, and 110 cubic yards placed). Monitored loads for mix no., slump, temp., and time limit. Prepared 4x8"
cylinder test specimens sampled from TRUCK DISCHARGE.
Set
No.
Slump
(in.)
Mix
Temp.
(°F)
Air Temp.
(°F)
Air Content
(%)
Unit Weight
(pcf)
Truck
No.Location Qty. of
Samples Batch Time Sample Time Subcontractor Ticket
No.
1 5.25 72 80 5.0 144.5 68 P.1/b33 5 7:00 AM 7:38 AM Marguerite 3141
0
2 6.0 69 80 5.5 144.0 68 J.3/b24 5 9:00 AM 9:50 AM Marguerite 3141
6
10 Total
Additional Notes: Wall: J-J.3/b24,b24-31/JrnFoundation: K-N.7/b24, b24-33/P, P.3-P.4/b32, N.4-P.2/b33
Referenced Details: Mix Design 3500D-3/4 Design Concrete
TESTING
INSPECTION
ENGINEERING
Soils Observation
FET Project #: 5951
Project Name: Dennis Yarmouth Middle School TAA #: NA
Inspection Address: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Arsene Ntwali
August 13, 2021
Time In: 10:00 Time Out: 15:00
Weather: Sunny
Temperature: 80°F
Permit No. :
Plans Dated: 03/26/2021
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable
standards of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
Arsene Ntwali
Inspector
08-13-2021
Date Enea Mushi
Project Manager
08-16-2021
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Arsene Ntwali reported to Mitch Miller with PMA at the jobsite. Performed observation of earthwork activities. No samples taken.
Additional Notes: Observed placement and compaction of 3” of dense grade in the parking lot.rnProctor to be provided later for
surface density test.
TESTING
INSPECTION
ENGINEERING
Project No: 5951
Project Name: Dennis Yarmouth Middle School
Project Location: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Arsene Ntwali
Inspection Type: Samples made by Client Representative
Pg. 1 of 1
August 11, 2021
Permit No. :
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Fenagh laboratory received 1 L-Soil ASTM D1557 Moisture-Density Relations of Soil Using Modified Effort (Modified Proctor),ASTM
D422 Particle-Size Analysis of Soils (without Hydrometer) samples for test(s).
Sample information including but not limited to material, schedule(s), and specified requested test(s) were provided by Client
Representative and cannot be corroborated by Fenagh.
NCR ID#Date Location Inspector Issue RFI/ Submittal
No.Resolved? (Y/N)Sub/ Contractor Date Resolved Comment
EOR to Advise
00/00/2021
7 day break Set 1 = psi
00/00/2021
28 day break Set 1 = psi
Legend:
Status: Closed
Status: Open
TESTING
INSPECTION
ENGINEERING
Field Number: 5 Laboratory Compression Test (4x8)
Project Name: Dennis Yarmouth Middle School Permit No.:
Project No.:5951 Sampled by: Arsene Ntwali Report Date: 08/10/2021
Client: PMA
Date of Sampling: 07/09/2021 Lab Log No.: 15185 (2528C)
Reviewed by: Henry Soares
08/10/2021
Date
ASTM Standards Used: Unless noted, material was sampled and tested in accordance with ASTM C172, C31, C143, C231, C470, C511, C1077,
C1231,C1064, C138 and E4. Compressive strength tests per ASTM C39.
Testing was performed by qualifed personnel in accordance with generally accepted industry practice, material testing consultants procedures and the above reference standards. This report is
applicable only to the items listed herein. The test performed and in this report are not intended to be considered as any guarantee or warranty of suitability for service or fitness of use of itemstested and it should not be relied on as such. The report has been prepared for the exclusive use of the client and any partial or whole reproduction without the consent of the client is prohibited.Pg. 1 of 1
Information provided by Field Technician
Mix #: 3500D Supplier: Cape Cod Mix Contractor: Marguerite
Set: 1 of 1 Truck #: 83 Design Strength (psi): 3,500 @28 days Ticket#: 169176
Sample Material/Shape: 4x8 Cylinders Type of Structure: Footings
Location: Onsite
Location for overall pour: Foundation Footings at d2-d19
Location when sampled: D4
Concrete Quality Actual Req'ment Actual Req'ment Actual Req'ment
Mix Temperature (ºF):70 50-90 Slump or Spread (in.):5.5 4-6 Unit Wt (#cu ft):144.2 140-150
Air Temperature (ºF):72 >40 Air Content (%):5.0 4.5-7.5 Time Sampled:11:10 AM
Aggregate Size (in):3/4 N/A Batch Time:10:11 AM Time in Truck:59 minutes
Information supplied by Laboratory Technician
Date Received: 07/12/2021 Technician that received: Billy Coughlin
Test #
Age of
Test
(Days)
Date Technician Diameter Length Area (in²)Cure Loc Ultimate Load
(lbs)
Compressive
Strength (psi)
Type of
Fracture
A 7 07/16/2021 Max Nabulsi 4.00 8.00 12.57 Lab 36,938 2,940 psi Type 2
B 28 08/06/2021 Charles Martens 4.00 8.00 12.57 Lab 53,730 4,270 psi Type 5
C 28 08/06/2021 Charles Martens 4.00 8.00 12.57 Lab 51,650 4,110 psi Type 4
D 28 08/06/2021 Charles Martens 4.00 8.00 12.57 Lab 48,690 3,870 psi Type 3
E H H 4.00 8.00 12.57 Lab
MEETS DESIGN STRENGTH
28 Day Avg.:4,080 psi
Remarks: Test B-D samples tested at Allied Testing Laboratories, Inc, CTL #207-018
TESTING
INSPECTION
ENGINEERING
Field Number: 10 Laboratory Compression Test (4x8)
Project Name: Dennis Yarmouth Middle School Permit No.:
Project No.:5951 Sampled by: Arsene Ntwali Report Date: 08/10/2021
Client: PMA
Date of Sampling: 07/28/2021 Lab Log No.: 15519 (2744-2745)
Reviewed by: Henry Soares
08/10/2021
Date
ASTM Standards Used: Unless noted, material was sampled and tested in accordance with ASTM C172, C31, C143, C231, C470, C511, C1077,
C1231,C1064, C138 and E4. Compressive strength tests per ASTM C39.
Testing was performed by qualifed personnel in accordance with generally accepted industry practice, material testing consultants procedures and the above reference standards. This report is
applicable only to the items listed herein. The test performed and in this report are not intended to be considered as any guarantee or warranty of suitability for service or fitness of use of itemstested and it should not be relied on as such. The report has been prepared for the exclusive use of the client and any partial or whole reproduction without the consent of the client is prohibited.Pg. 1 of 2
Information provided by Field Technician
Mix #: 3500D Supplier: Cape Cod Mix Contractor: Marguerite
Set: 1 of 2 Truck #: 55 Design Strength (psi): 3,500 @28
days Ticket#: 31197
Sample Material/Shape: ASTM C39 Compressive Strength of Cylindrical
Concrete Specimens (4x8)Type of Structure: Footings
Location: Onsite
Location for overall pour: Level 1 Footings at C116/D.3, C16/E, c20/G
Location when sampled: C16/E
Concrete Quality Actual Req'ment Actual Req'ment Actual Req'ment
Mix Temperature (ºF):70 50-90 Slump or Spread (in.):5 4-6 Unit Wt (#cu ft):144.2 140-150
Air Temperature (ºF):72 >40 Air Content (%):5.4 4.5-7.5 Time Sampled:7:55 AM
Aggregate Size (in):3/4 N/A Batch Time:7:02 AM Time in Truck:53 minutes
Information supplied by Laboratory Technician
Date Received: 07/30/2021 Technician that received: Max Nabulsi
Test #
Age of
Test
(Days)
Date Technician Diameter Length Area (in²)Cure Loc Ultimate Load
(lbs)
Compressive
Strength (psi)
Type of
Fracture
A 7 08/04/2021 Evan Mei 4.00 8.00 12.57 Lab 33,496 2,660 psi Type 2
B 28 08/25/2021 4.00 8.00 12.57 Lab
C 28 08/25/2021 4.00 8.00 12.57 Lab
D 28 08/25/2021 4.00 8.00 12.57 Lab
E H H 4.00 8.00 12.57 Lab
Remarks: Received Sample Condition: Acceptable and/or Satisfactory
TESTING
INSPECTION
ENGINEERING
Field Number: 10 Laboratory Compression Test (4x8)
Project Name: Dennis Yarmouth Middle School Permit No.:
Project No.:5951 Sampled by: Arsene Ntwali Report Date: 08/10/2021
Client: PMA
Date of Sampling: 07/28/2021 Lab Log No.: 15519 (2744-2745)
Reviewed by: Henry Soares
08/10/2021
Date
ASTM Standards Used: Unless noted, material was sampled and tested in accordance with ASTM C172, C31, C143, C231, C470, C511, C1077,
C1231,C1064, C138 and E4. Compressive strength tests per ASTM C39.
Testing was performed by qualifed personnel in accordance with generally accepted industry practice, material testing consultants procedures and the above reference standards. This report is
applicable only to the items listed herein. The test performed and in this report are not intended to be considered as any guarantee or warranty of suitability for service or fitness of use of itemstested and it should not be relied on as such. The report has been prepared for the exclusive use of the client and any partial or whole reproduction without the consent of the client is prohibited.Pg. 2 of 2
Information provided by Field Technician
Mix #: 3500D Supplier: Cape Cod Mix Contractor: Marguerite
Set: 2 of 2 Truck #: 53 Design Strength (psi): 3,500 @28
days Ticket#: 31199
Sample Material/Shape: ASTM C39 Compressive Strength of Cylindrical
Concrete Specimens (4x8)Type of Structure: Footings
Location: Onsite
Location for overall pour: Level 1 Footings at C116/D.3, C16/E, c20/G
Location when sampled: c18/F
Concrete Quality Actual Req'ment Actual Req'ment Actual Req'ment
Mix Temperature (ºF):67 50-90 Slump or Spread (in.):6 4-6 Unit Wt (#cu ft):144.7 140-150
Air Temperature (ºF):72 >40 Air Content (%):5.7 4.5-7.5 Time Sampled:8:55 AM
Aggregate Size (in):3/4 N/A Batch Time:7:51 AM Time in Truck:64 minutes
Information supplied by Laboratory Technician
Date Received: 07/30/2021 Technician that received: Max Nabulsi
Test #
Age of
Test
(Days)
Date Technician Diameter Length Area (in²)Cure Loc Ultimate Load
(lbs)
Compressive
Strength (psi)
Type of
Fracture
A 7 08/04/2021 Evan Mei 4.00 8.00 12.57 Lab 37,601 2,990 psi Type 2
B 28 08/25/2021 4.00 8.00 12.57 Lab
C 28 08/25/2021 4.00 8.00 12.57 Lab
D 28 08/25/2021 4.00 8.00 12.57 Lab
E H H 4.00 8.00 12.57 Lab
Remarks: Received Sample Condition: Acceptable and/or Satisfactory
TESTING
INSPECTION
ENGINEERING
Soils Test Report
Project Name: Dennis Yarmouth Middle School Place of Sampling : Permit No.:
Project No.:5951 Sampled by: Arsene Ntwali Report Date: 08/10/2021
Client: PMA Date of Sampling: 08/05/2021 Lab Log No.: 15656 (S785)
Reviewed by: Henry Soares
08/10/2021
Date
ASTM Standards Used: Unless otherwise noted ASTM D-1557, D422, D4318, D2216, D1140,Method-C
Testing was performed by qualifed personnel in accordance with generally accepted industry practice, material testing consultants procedures and the above reference standards. This report is
applicable only to the items listed herein. The test performed and in this report are not intended to be considered as any guarantee or warranty of suitability for service or fitness of use of itemstested and it should not be relied on as such. The report has been prepared for the exclusive use of the client and any partial or whole reproduction without the consent of the client is prohibited.Pg. 1 of 1
Max Density
131.9 pcf @ 7.6%
As Received Moisture
9.8%
Source
Color
Brown
Description
Specific Gravity
2.7 Estimated
Date Received: 08/05/2021
Date Tested: 08/10/2021
Tested by: Max Nabulsi
Desc of Rammer: Mechanical
Material: Reclaimed Asphalt
Preparation Method: Moist
Oversized Material: Percent of: 16.02 ;Specific Gravity: 2.7;Percent Moisture: 0.85
Remarks: Received Sample Condition: Acceptable and/or Satisfactory
TESTING
INSPECTION
ENGINEERING
Field Number: 10 Laboratory Compression Test (4x8)
Project Name: Dennis Yarmouth Middle School Permit No.:
Project No.:5951 Sampled by: Arsene Ntwali Report Date: 08/11/2021
Client: PMA
Date of Sampling: 07/30/2021 Lab Log No.: 15564 (2802-2803)
Reviewed by: Henry Soares
08/11/2021
Date
ASTM Standards Used: Unless noted, material was sampled and tested in accordance with ASTM C172, C31, C143, C231, C470, C511, C1077,
C1231,C1064, C138 and E4. Compressive strength tests per ASTM C39.
Testing was performed by qualifed personnel in accordance with generally accepted industry practice, material testing consultants procedures and the above reference standards. This report is
applicable only to the items listed herein. The test performed and in this report are not intended to be considered as any guarantee or warranty of suitability for service or fitness of use of itemstested and it should not be relied on as such. The report has been prepared for the exclusive use of the client and any partial or whole reproduction without the consent of the client is prohibited.Pg. 1 of 2
Information provided by Field Technician
Mix #: 3500D Supplier: Cape Cod Mix Contractor: Marguerite
Set: 1 of 2 Truck #: 52 Design Strength (psi): 3,500 @28
days Ticket#: 31234
Sample Material/Shape: ASTM C39 Compressive Strength of Cylindrical
Concrete Specimens (4x8)Type of Structure: Footings
Location: Onsite
Location for overall pour: Level 1 Footings at Building C
Location when sampled: D.3/c116
Concrete Quality Actual Req'ment Actual Req'ment Actual Req'ment
Mix Temperature (ºF):70 50-90 Slump or Spread (in.):6 4-6 Unit Wt (#cu ft):144.0 140-150
Air Temperature (ºF):72 >40 Air Content (%):6.2 4.5-7.5 Time Sampled:10:45 AM
Aggregate Size (in):3/4 N/A Batch Time:9:50 AM Time in Truck:55 minutes
Information supplied by Laboratory Technician
Date Received: 08/04/2021 Technician that received: Max Nabulsi
Test #
Age of
Test
(Days)
Date Technician Diameter Length Area (in²)Cure Loc Ultimate Load
(lbs)
Compressive
Strength (psi)
Type of
Fracture
A 7 08/06/2021 Charles Martens 4.00 8.00 12.57 Lab 29,320 2,330 psi Type 3
B 28 08/27/2021 4.00 8.00 12.57 Lab
C 28 08/27/2021 4.00 8.00 12.57 Lab
D 28 08/27/2021 4.00 8.00 12.57 Lab
E H H 4.00 8.00 12.57 Lab
Remarks: All samples tested at Allied Testing Laboratories, Inc, CTL #207-018
TESTING
INSPECTION
ENGINEERING
Field Number: 10 Laboratory Compression Test (4x8)
Project Name: Dennis Yarmouth Middle School Permit No.:
Project No.:5951 Sampled by: Arsene Ntwali Report Date: 08/11/2021
Client: PMA
Date of Sampling: 07/30/2021 Lab Log No.: 15564 (2802-2803)
Reviewed by: Henry Soares
08/11/2021
Date
ASTM Standards Used: Unless noted, material was sampled and tested in accordance with ASTM C172, C31, C143, C231, C470, C511, C1077,
C1231,C1064, C138 and E4. Compressive strength tests per ASTM C39.
Testing was performed by qualifed personnel in accordance with generally accepted industry practice, material testing consultants procedures and the above reference standards. This report is
applicable only to the items listed herein. The test performed and in this report are not intended to be considered as any guarantee or warranty of suitability for service or fitness of use of itemstested and it should not be relied on as such. The report has been prepared for the exclusive use of the client and any partial or whole reproduction without the consent of the client is prohibited.Pg. 2 of 2
Information provided by Field Technician
Mix #: 3500D Supplier: Cape Cod Mix Contractor: Marguerite
Set: 2 of 2 Truck #: 53 Design Strength (psi): 3,500 @28
days Ticket#: 31238
Sample Material/Shape: ASTM C39 Compressive Strength of Cylindrical
Concrete Specimens (4x8)Type of Structure: Footings
Location: Onsite
Location for overall pour: Level 1 Footings at Building C
Location when sampled: c5/H
Concrete Quality Actual Req'ment Actual Req'ment Actual Req'ment
Mix Temperature (ºF):70 50-90 Slump or Spread (in.):6 4-6 Unit Wt (#cu ft):144.5 140-150
Air Temperature (ºF):72 >40 Air Content (%):5.7 4.5-7.5 Time Sampled:1:30 PM
Aggregate Size (in):3/4 N/A Batch Time:12:19 PM Time in Truck:71 minutes
Information supplied by Laboratory Technician
Date Received: 08/04/2021 Technician that received: Max Nabulsi
Test #
Age of
Test
(Days)
Date Technician Diameter Length Area (in²)Cure Loc Ultimate Load
(lbs)
Compressive
Strength (psi)
Type of
Fracture
A 7 08/06/2021 Charles Martens 4.00 8.00 12.57 Lab 31,480 2,500 psi Type 3
B 28 08/27/2021 4.00 8.00 12.57 Lab
C 28 08/27/2021 4.00 8.00 12.57 Lab
D 28 08/27/2021 4.00 8.00 12.57 Lab
E H H 4.00 8.00 12.57 Lab
Remarks: All samples tested at Allied Testing Laboratories, Inc, CTL #207-018