HomeMy WebLinkAboutDYIMS PE Site report 20210901 Architect: Perkins Eastman DPC Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File ARCHITECT’S SITE OBSERVATION REPORT DATE OF VISIT: 09/01/2021 PROJECT: Dennis Yarmouth Intermediate Middle School 286 Station Avenue South Yarmouth, MA 02664 DATE OF ISSUE: 09/07/2021 PROJECT NO: 71011 WEATHER CONDITIONS: OVERCAST; DRIZZLE; 70s ARCHITECT: Perkins Eastman, DPC 20 Ashburton Street 8th floor Boston, MA The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit. WORK IN PROGRESS: 1) Underground plumbing work in Area C. 2) Underground electrical work in Area D link 3) Insulating and Backfilling foundations at Area C 4) Concrete placement at Area A 5) Setting forms and re-bar in preparation for future concrete placement at Area A 6) Ongoing survey and layout work 7) Fenagh is on site for 3rd party rebar inspections and compaction testing FIELD OBSERVATIONS: PE visited the site to review ongoing progress with the site work, underground utilities and foundation installation. 1. On Monday RBO completed subgrade prep for the elevator pit in Area B, as well as for the remainder of the interior footings at the music wing area (Area A), and today was continuing to prepare interior footings subgrade in the central part of B (specifically on line L on B17 to B21 and also on lines M and M.5). see photo. Also see GPI report for more detail. 2. RBO is preparing subgrade for transformer pad (see photo). 3. UG plumbing and electrical work at area D is substantially complete, and RBO has loaded crushed stone into at the Area D future slab on grade so that final preparations can be made for the subgrade for the slab (see photo) 4. Harold Bros. is currently trenching for underground plumbing at Area C (see photo). 5. Foundation insulation has been placed and walls backfilled at most of area C, including the courtyard and the C-D links 6. In the early morning Marguerite placed the central foundation wall along the north side of Areas B and extending into A—i.e. on line B12.3 up to line K, and on line K up to B1; they also placed concrete for knee wall footings at the auditorium ‘lower bowl’ area (see photos). 7. Forms have already been set for the music wing south wall, and around to the auditorium (lines W/A.1). It was sprinkling lightly at the time of observation, and Marguerite was in the process of tying rebar and setting forms for interior column footings at Area A, and for the continuation of the foundation wall on line A2 (auditorium West). 8. PE had a discussion with Commodore about the extent of structural foundation wall detail 3/S201, which was not dimensioned in plan on the drawings; PE provided a clarifying sketch and also walked Commodore through clarifications that the design team provided on the loading dock area rebar shop drawings. 9. Commodore said that Marguerite protected the work that was placed today in preparation for expected rain. 10. Brennan is doing ongoing ‘as built’ surveying of anchor bolts for Norgate (area B). REPORT BY: ABH Page 2 of 3 PROGRESS PHOTOS EXCAVATING INTERIOR FOOTING IN AREA B INSTALLING CRUSHED STONE FOR TRANFORMER PAD CRUSHED STONE LOADED IN AREA D IN PREPARATION FOR PLACEMENT OF SLAB ON GRADE TRENCHING FOR UNDERGROUND PLUMBING (AREA C) AREA B WALL PLACED ON SEPT. 1 (LINE K UP TO B1) REPORT BY: ABH Page 3 of 3 LOADING DOCK AREA FOOTINGS WITH WALL REBAR AREA C-B ‘LINK’ WALL PLACED ON SEPT 1 (B12.3) “LOWER BOWL” FOOTINGS PLACED ON SEPT 1 (FOR INTERIOR AUDITORIUM NORTH SIDE KNEE WALLS) PARTIALLY TIED REBAR AND WALL FORMS BEING ERECTED AT AREA A (LINE A2 AT FUTURE STAGE FOLDING DOOR)    Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.                Date on site: 8/31/21, Mostly Cloudy, Low  80’s                                                                                                 Caseyville, Il 62232                _________________________________________________________________________________________________  FOOTING PREPARATION:    THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:   Excavate to six inches below proposed Bottom of Footing Elevation   Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor   Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade   Compact said Crushed Stone   Crushed Stone Base now ready for Footing installation                                              Activity for Tuesday, August 31st, 2021  AREA “A “    Footing Subgrade Compaction / Preparation Detail :  The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of  non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture  content of the soil. Since the encountered materials are of native, (natural) deposition the water content can vary from  location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are  utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with  supplied water in order to certify proper compaction in these circumstances.    THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:  FOOTING LINE  FROM – TO  FOOTING  COORDINATE  FOOTING  SIZE and TYPE  BOTTOM  ELEVATION   COMMENTS  Building “A”  South Ramp  Refer to Plan  S‐1.11A  Varies with  application  21.9 Complete  Isolated a9.3/T.7 F 4.0 24.2 Complete  Isolated a11/T.7 F 3.0 24.2 Complete  Isolated a10/U F 6.0 23.2 Complete  Isolated a11/U F 5.0 23.2 Complete  Isolated a11/V F 5.0 23.2 Complete  Isolated Elevator Pit Area B F 8.7 X 7.0 22.2 Complete    See four photos, all refer to Footing # a11/T.7       Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.                Date on site: 8/31/21, Mostly Cloudy, Low  80’s                                                                                                 Caseyville, Il 62232                _________________________________________________________________________________________________      Excavating    Preparing Subgrade         Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.                Date on site: 8/31/21, Mostly Cloudy, Low  80’s                                                                                                 Caseyville, Il 62232                _________________________________________________________________________________________________      Placing Crushed Stone    Compacting Crushed Stone     Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.                Date on site: 9/1/21 Mostly Cloudy, Low  80’s                                                                                                    Caseyville, Il 62232                 _________________________________________________________________________________________________    FOOTING PREPARATION:    THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:   Excavate to six inches below proposed Bottom of Footing Elevation   Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor   Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade   Compact said Crushed Stone   Crushed Stone Base now ready for Footing installation                                              Activity for Wednesday, September 1st, 2021  AREA “B “    Footing Subgrade Compaction / Preparation Detail :  The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of  non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture  content of the soil. Since the encountered materials are of native, (natural) deposition the water content can vary from  location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are  utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with  supplied water in order to certify proper compaction in these circumstances.    THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:  FOOTING LINE  FROM – TO  FOOTING  COORDINATE  FOOTING  SIZE and TYPE  BOTTOM  ELEVATION   COMMENTS  Isolated L/b21 F 7.0 22.1 Complete  Isolated L/b20 F 7.0 23.2 Complete  Isolated L/b19 F7.0 23.2 Complete  Isolated L/b18 F8.0 22.9 Complete  Isolated L.6/b20.1 F 5.5 X 2 23.2 Complete  Isolated M/b20.1 F 5.5 X 2 23.2 Complete  Isolated M.5/b20.5 F 31 X 6 22.7 Complete    See four photos, all refer to Footing # L/b20       Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.                Date on site: 9/1/21 Mostly Cloudy, Low  80’s                                                                                                    Caseyville, Il 62232                 _________________________________________________________________________________________________        Excavating    Preparing Subgrade       Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.                Date on site: 9/1/21 Mostly Cloudy, Low  80’s                                                                                                    Caseyville, Il 62232                 _________________________________________________________________________________________________      Placing Crushed Stone      Compacting Crushed Stone     Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.                Date on site: 9/2/21, Partly Cloudy, low 70’s                                                                                                  Caseyville, Il 62232                     _________________________________________________________________________________________________  FOOTING PREPARATION:    THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:   Excavate to six inches below proposed Bottom of Footing Elevation   Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor   Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade   Compact said Crushed Stone   Crushed Stone Base now ready for Footing installation                                              Activity for Thursday, September 2nd, 2021  AREA “B “    Footing Subgrade Compaction / Preparation Detail :  The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of  non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture  content of the soil. Since the encountered materials are of native, (natural) deposition the water content can vary from  location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are  utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with  supplied water in order to certify proper compaction in these circumstances.    THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:  FOOTING LINE  FROM – TO  FOOTING  COORDINATE  FOOTING  SIZE and TYPE  BOTTOM  ELEVATION   COMMENTS  Isolated L/b17 F 7.0 23.0 Complete  Isolated L/b15 F 8.0 22.9 Complete  Isolated L/b12 F 6.0 23.2 Complete  Isolated M.5/a25 F 5.0 23.2 Complete  Isolated M.5/a23 F 8.0 22.9 Complete  Isolated M.5/a20 F 6.0 23.2 Complete  Isolated M.5/a17 F 8.0 22.9 Complete    See four photos, all refer to Footing # L/b17         Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.                Date on site: 9/2/21, Partly Cloudy, low 70’s                                                                                                  Caseyville, Il 62232                     _________________________________________________________________________________________________      Excavating      Preparing Subgrade       Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.                Date on site: 9/2/21, Partly Cloudy, low 70’s                                                                                                  Caseyville, Il 62232                     _________________________________________________________________________________________________      Placing Crushed Stone      Compacting Crushed Stone     Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 9/3/21, Partly Cloudy, High 70’s                                                                                                     Caseyville, Il 62232                _________________________________________________________________________________________________  FOOTING PREPARATION:    THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:   Excavate to six inches below proposed Bottom of Footing Elevation   Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor   Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade   Compact said Crushed Stone   Crushed Stone Base now ready for Footing installation                                              Activity for Friday, September 3rd, 2021  AREA “B “    Footing Subgrade Compaction / Preparation Detail :  The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of  non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture  content of the soil. Since the encountered materials are of native, (natural) deposition the water content can vary from  location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are  utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with  supplied water in order to certify proper compaction in these circumstances.      THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:  FOOTING LINE  FROM – TO  FOOTING  COORDINATE  FOOTING  SIZE and TYPE  BOTTOM  ELEVATION   COMMENTS  Isolated N.3/b21 F 6.0 23.2 Complete  Isolated N.5/a28 F 10.0 22.7 Complete  Isolated N.5/a26 F 6.0 23.2 Complete  Isolated N.5/a23 F 10.0 22.7 Complete  Isolated N.5/a22 F 6.0 23.3 Complete    All Photos refer to footing # N.5/a23         Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 9/3/21, Partly Cloudy, High 70’s                                                                                                     Caseyville, Il 62232                _________________________________________________________________________________________________      Excavating      Compacting Subgrade       Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 9/3/21, Partly Cloudy, High 70’s                                                                                                     Caseyville, Il 62232                _________________________________________________________________________________________________      Placing Crushed Stone      Compacting Crushed Stone