HomeMy WebLinkAboutDYIMS PE Site report 20210929
Architect: Perkins Eastman DPC
Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File
ARCHITECT’S SITE OBSERVATION REPORT
DATE OF VISIT: 09/29/2021 PROJECT: Dennis Yarmouth Intermediate
Middle School
286 Station Avenue
South Yarmouth, MA 02664
DATE OF ISSUE: 10/04/2021 PROJECT NO: 71011
WEATHER
CONDITIONS:
SUNNY AND CLEAR; MID 70s ARCHITECT: Perkins Eastman, DPC
20 Ashburton Street
8th floor
Boston, MA
The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit.
WORK IN PROGRESS:
1) Steel erection, deck installation, and detailing
2) Moment welding
3) Concrete placement and placement prep
4) Underground plumbing work in Area B.
5) Site electrical work in general
6) Ongoing survey and layout work by Brennan
7) Fenagh is on site for 3rd party rebar inspections and steel inspections.
FIELD OBSERVATIONS:
PE visited the site on 9-29, in order to review ongoing progress with the steel erection, deck installation, site work,
foundation installation, insulation installation, etc.
1. RBO completed the balance of the footing prep on 9-28. Work completed this week includes the interior footing at
A10.8/S.4, the base for the wall at the auditorium lobby and lobby corridor [B.14 from S.1 to U.2], and interior
footings along B12 from S.1 to S.8. (See attached photos as well as GPI field reports.)
2. Stellar Steel has completed steel erection at area C, not including bar joists, and at the time of observation the
crew was in the process of erecting steel at the north side of the gym on line J.7 and at the locker room area north
of the gymnasium (see photos).
3. Stellar steel is in the process of installing metal deck at area C, and deck stud installation has been completed at
area D (see photo). Commodore reports that by the end of next week decking installation and detailing should be
complete for both C and D.
4. At the time of observation the welding crew was making moment welds at the NW corner of area C (see photo).
5. Backfilling of areas A and B interior (up to structural fill level) is ongoing ahead of steel erection. The backfill
inside the footings has been completed at the adaptive PE area, and RBO is in the process of installing the
crushed stone pad at the gym area (see photos).
6. The base plate has been installed at the remediated pier at lines K/B.24.
7. Marguerite has prepped the forms and rebar for the last pour at the auditorium lower bowl area, and is in the
process of preparing for the footing placement on line B14 (auditorium lobby corroder foundation wall), and
adjacent interior footings in Area A (see photo). Foundation work is nearly complete overall.
8. During shop drawing review PE picked up the fact that the wall at the brick return for the Mattacheese entrance
(at the corner of Q and B.21—see attached photo) was placed 3” too far to the west (because that is what was
drawn), so GAC issued a drawing to correct this by padding out a 4” brick shelf here that is pinned into the
existing wall (Bulletin 18). PE asked Commodore to hold off insulation and backfill here pending this correction.
REPORT BY: ABH Page 2 of 3
PROGRESS PHOTOS
AREA OFF OF LINE Q WHERE BRICK SHELF MUST EXTEND INSTALLED FOOTINGS AT LINES W AND A.14
PREP FOR FOOTING PLACEMENT ON B.14 (WITH FRAME OF AREA C IN BACKGROUND)
BACKFILLED INTERIOR AT SE OF AREA B MOMENT WELDING AT E-C.4
REPORT BY: ABH Page 3 of 3
ERECTED FRAME AT EAST LINK (FROM WIXON COURTYARD LOOKING EAST)
COLUMNS BEING ERECTED AT SOUTH SIDE OF GYM (LINE J.7) PLACING COLUMN J/B25 ON ANCHOR BOLTS
DECK INSTALLATION IN PROCESS AT C-D WEST LINK INSTALLED DECK STUDS AT AREA D
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 9/27/21, Sunny, High 60’s Caseyville, Il 62232
_________________________________________________________________________________________________
FOOTING PREPARATION:
THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:
Excavate to six inches below proposed Bottom of Footing Elevation
Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor
Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade
Compact said Crushed Stone
Crushed Stone Base now ready for Footing installation
Activity for Monday, September 27th, 2021, Area “ A “
Footing Subgrade Compaction / Preparation Detail :
The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of
non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture
content of the soil. Since the encountered materials are of native, (natural) deposition the water content can vary from
location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are
utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with
supplied water in order to certify proper compaction in these circumstances.
THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:
FOOTING LINE
FROM – TO
FOOTING
COORDINATE
FOOTING
SIZE and TYPE
BOTTOM
ELEVATION
COMMENTS
Isolated a10.8/S.4 F 4.0 24.2 Complete
Photos refer to Footing # a10.8/S.4
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 9/27/21, Sunny, High 60’s Caseyville, Il 62232
_________________________________________________________________________________________________
Excavating
Preparing Subgrade
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 9/27/21, Sunny, High 60’s Caseyville, Il 62232
_________________________________________________________________________________________________
Placing Crushed Stone
Compacting Crushed Stone
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 9/28/21, Overcast, Mid 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
FOOTING PREPARATION:
THE SEQUENCE OF PROCEDURES ARE IDENTICAL FOR ALL INSTANCES OF PREPARATION, AND ARE AS FOLLOWS:
Excavate to six inches below proposed Bottom of Footing Elevation
Compact the exposed subgrade, Piers now revealed – with a heavy vibratory plate compactor
Place six inches of 3/4” Crushed Stone upon the Prepared Subgrade
Compact said Crushed Stone
Crushed Stone Base now ready for Footing installation
Activity for Tuesday, September 28th, 2021, Area “ A “
Footing Subgrade Compaction / Preparation Detail :
The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of
non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture
content of the soil. Since the encountered materials are of native, (natural) deposition the water content can vary from
location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are
utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with
supplied water in order to certify proper compaction in these circumstances.
THE FOOTING LINES AND SPECIFIC FOOTINGS, ACCORDING TO THE SCHEDULE BELOW WERE PREPARED THIS DAY:
FOOTING LINE
FROM – TO
FOOTING
COORDINATE
FOOTING
SIZE and TYPE
BOTTOM
ELEVATION
COMMENTS
b14/P – b14/V b14/S.1 F 5.0 23.2 Complete
b14/P – b14/V b14/S.5 F 5.0 23.2 Complete
b14/P – b14/V b14/S.8 F 5.0 23.2 Complete
b14/P – b14/V b14/T.2 F 5.0 23.2 Complete
b14/P – b14/V b14/U.2 F 6.0 23.2 Complete
Isolated b12/S.1 F 10.0 23.0 Complete
Isolated b12/S.5 F 9.0 23.0 Complete
Isolated b10/S.8 F 5.0 23.2 Complete
Construction Note: Footing Preparation for Buildings A, B, C, and D is now complete.
Photos refer to Footing # b12/S.1
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 9/28/21, Overcast, Mid 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
Excavating
Compacting Subgrade
Earthwork Monitoring, Daily Field Report Geotechnical Partnership, Inc.
Dennis‐Yarmouth Intermediate School File No. 1814‐02
Field Representative: Francis E. Sviokla Earthwork Contractor: Robert B Our Co., Inc
General Contractor: Commodore Builders 24 Great Western Rd., Harwich, MA 02645
404 Wyman St., Suite 400, Waltham, MA 02451 Pier Installer: CNC Foundations, 8251 Bunkum Rd.
Date on site: 9/28/21, Overcast, Mid 70’s Caseyville, Il 62232
_________________________________________________________________________________________________
Placing Crushed Stone
Compacting Crushed Stone