HomeMy WebLinkAboutDYIMS PE Site report 20211005 Architect: Perkins Eastman DPC Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File ARCHITECT’S SITE OBSERVATION REPORT DATE OF VISIT: 10/05/2021 PROJECT: Dennis Yarmouth Intermediate Middle School 286 Station Avenue South Yarmouth, MA 02664 DATE OF ISSUE: 10/14/2021 PROJECT NO: 71011 WEATHER CONDITIONS: CLOUDY AND OVERCAST ARCHITECT: Perkins Eastman, DPC 20 Ashburton Street 8th floor Boston, MA The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit. WORK IN PROGRESS: 1) Steel erection, deck installation, and detailing, moment welding 2) Drainage structure installation in building courtyards 3) Concrete placement and placement preparation 4) Underground plumbing work and electrical work in Area B. 5) Damproofing and backfill; crushed stone placements inside footprint 6) Ongoing survey and layout work by Brennan 7) Fenagh is on site for 3rd party rebar inspections, steel inspections, and welding inspections. FIELD OBSERVATIONS: PE visited the site on 10-04, in order to review ongoing progress with the steel erection, deck installation, site work, foundation installation, insulation installation, etc. 1. RBO completed the all of the footing prep work and GPI is off site, and was in the process of installing catch basins and drainage lines in the Mattacheese courtyard, i.e. the courtyard between B and C (see photo). Dense grading is in place at the Wixon courtyard (see photo). 2. Damproofing is ongoing; has commenced at north wall of auditorium lower bowl area. 3. Marguerite has completed the last wall pour at the auditorium lower bowl area, and is in the process of preparing for the wall placement on line B14 (auditorium lobby corridor foundation wall), and adjacent interior piers in Area A. Foundation work in areas A and B is almost complete. 4. Marguerite is in the process of prepping formwork and rebar for the pour of the padding detail (4” brick shelf) at the Mattacheese entrance (Bulletin 18). Rebar was installed per GAC detail. (see photo). 5. Stellar Steel has completed steel erection at areas C and D and part of B, and is in the process of installing bar joists for the roof framing on both D and C. At the time of observation, bar joists were placed in bundles of 2-5 prior to spacing them out and attaching them. The first girder truss for the gym (Girder truss GT-1) was placed starting at around 4 pm. 6. At the time of observation the Stellar welding crew was completing the moment welding in C working at the NE corner of area C (see photo). Stellar was also in the process of detailing the metal deck area C.Commodore reports decking and detailing should be complete for both C and D by the end of the week. . 7. Backfilling of areas A and B interior (up to structural fill level) is ongoing ahead of steel erection. Crushed stone has been placed in locker room area and gym area. Gym is being used as laydown area for trusses. 8. At area B, Electrical room underground conduit placement is complete and Annese is getting ready to start underground electrical work back in area C now that it is framed. REPORT BY: ABH Page 2 of 4 PROGRESS PHOTOS FORMWORK FOR UPCOMING FOUNDATION WALL PLACEMENT AT AUDITORIUM LOBBY (AREA A) FOUNDATION PLACEMENT PREP AT LINE V (AREA A) PLACED WALL AT LINE W (AREA A) BACKFILLING IN AREA B NEXT TO ELECTRICAL RM CRUSHED STONE FOR SOG AT LOCKER AREA (AREA B) REPORT BY: ABH Page 3 of 4 PREP FOR BRICK SHELF CORRECTION (BULLETIN 18) LOOKING EAST TOWARD WIXON COURTYARD DRAINAGE STRUCTURE INSTALLATION AT MATTACHEESE COURTYARD REPORT BY: ABH Page 4 of 4 UNDERGROUND CONDUIT AT AREA B ELECTRICAL ROOM MOMENT WELDING AT AREA C GIRDER TRUSSES POSITIONED FOR ERECTION GIRDER TRUSS GT-1 BEING ERECTED