Architect: Perkins Eastman DPC
Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File
ARCHITECT’S SITE OBSERVATION REPORT
DATE OF VISIT: 11/10/2021 PROJECT: Dennis Yarmouth Intermediate
Middle School
286 Station Avenue
South Yarmouth, MA 02664
DATE OF ISSUE: 11/23/2021 PROJECT NO: 71011
WEATHER
CONDITIONS:
CLOUDY, OVERCAST, 50s ARCHITECT: Perkins Eastman, DPC
20 Ashburton Street
8th floor
Boston, MA
The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit.
WORK IN PROGRESS:
1) Steel deck detailing
2) Concrete Slab on grade and slab on deck placement and preparation
3) CFMF parapet and exterior backup wall framing
4) Light gage interior partition layout
5) Misc metals
6) Grouting column bases
7) Underground electrical and plumbing work
8) Site work; water main testing
9) Fenagh is on site for ongoing FF/FL inspections and steel and welding inspections.
FIELD OBSERVATIONS:
PE visited the site on 11-10, for roofing kickoff meeting and in order to review ongoing progress of work on site.
1. The drywall contractor, Colony, has mobilized on the second floor of Area D, and are installing CFMF for the
perimeter backup wall, as well as starting to lay track for interior partitions; Colony has finished framing the roof
parapets at Area D and will continue on to Area C with the parapet framing.
2. Stanley, the roofing contractor, was on site for kickoff meeting and is in the process of mobilizing on site, they will
start work on the roof of Area D later in the week.
3. Slab on grade at level 1 of Area D (installed last week) has been stripped; fine grading at C wing is complete and
VB and under-slab insulation are placed. C wing slab on grade placement is scheduled for next week.
Commodore reports that Silverback is planning on using laser instruments for leveling for better FF/FL results.
4. Commodore reports that United steel will be installing stairs in Area C next week.
5. Column bases are grouted at area C and Silverback is in the process of installing wire mesh in preparation for an
upcoming slab on deck (composite deck) installation at level 2 C
6. The underground electrical work and underground plumbing work are finishing up at Area B. When complete at
Area B, Annese and Harold Bros. will be moving over to Area A, in same the sequence as SOG placement.
7. Steel inspections by Fenagh are ongoing.
8. Stellar Steel is in the process of installing deck studs, puddle welds and other steel detailing at areas A and B.
9. Site work: water main installation is complete; water main is being tested on 11-10 or 11-11 according to
Commodore.
10. Commodore has finished preparing the mockup for the window test that is scheduled for 11-11.
REPORT BY: ABH Page 2 of 2
SITE PHOTOS
WEST FAÇADE CFMF FRAMING (AREA D) WINDOW FRAMING AT NORTH FACADE (AREA D)
NORTH PARAPET FRAMING AT ROOF (AREA D) RTU PAD AND FRAMING FOR ACOUSTICAL (AREA D)
DEFLECTION HEAD AND SOUTH PARAPET FRAMING (AREA D) STEEL ANGLE BRACE AT P’PET