ARCHITECT’S SITE OBSERVATION REPORT
DATE OF VISIT: 11/02/2021 and 11/04/2021 PROJECT: Dennis Yarmouth Intermediate
Middle School
286 Station Avenue
South Yarmouth, MA 02664
DATE OF ISSUE: 11/23/2021 PROJECT NO: 71011
WEATHER
CONDITIONS:
SUNNY, CLEAR, 70s ARCHITECT: Perkins Eastman, DPC
20 Ashburton Street
8th floor
Boston, MA
The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit.
WORK IN PROGRESS:
1) Steel roof joist erection and steel deck placement
2) moment frame welding and steel detailing.
3) Concrete Slab on grade and SOG placement
4) Fine grading for future SOG placement
5) Underground electrical and plumbing work
6) Grouting column bases; painting column bases with mastic
7) General Site work including water main installation
8) Ongoing survey work by Brennan
9) Fenagh is on site for FF/FL and welding inspections.
FIELD OBSERVATIONS:
PE visited the site on 11-02 and 11-04, in order to review ongoing progress with the work on site and to attend the 11-04
topping off ceremony.
1. Primary steel erection including the south side of Area A (music wing) was completed as of 11-01.
2. The slab-on-grade at the west side of Area D was placed on 11-02, including leveling, cutting the control
joints, etc. The placement of the SOG at the east side is scheduled for Friday 11-05, and the preparation of
the vapor barrier, wire mesh etc. for the east side SOG was in progress on 11-02 and was mostly completed
by 11-04.
3. As of 11-02 the wet cure for the slab on deck on level 2 of Area D was complete and the slab had been
stripped.
4. All underground plumbing and electrical work in C was complete as of 11-02 and RBO was completing fine
grading of the crushed stone in preparation for an upcoming SOG placement in Area C.
5. Column base preparation was complete at Area C as of 11-02.
6. On 11-02 the Stellar Steel crew was installing the roof joists at area A and placing floor deck at the auditorium
main stage area, and was continuing to install moment welds (see photo).
7. As of 11-02 Stellar had installed the roof deck at the north part of area A and had detailed the roof deck of
Area C, and by 11-04 had finished installing the roof deck at most of Area B (including the acoustical metal
deck at the gymnasium and the future adaptive PE space).
8. On 11-02 Stellar installed roof decking at the auditorium stage area.
9. As of 11-04 the moment welds and the detailing for the deck for the SOD at area B level had been completed.
10. The ceremonial beam for the topping off of steel was lifted into place on 11-04.
11. PE observed that stellar steel corrected the out-of-plumb column that was noted during the 10-29 site visit.
12. Site work: water main installation was almost complete as of 11-04.
REPORT BY: ABH Page 2 of 3
SITE PHOTOS
SOG PLACEMENT (AREA D)
FINE GRADING (AREA C)
FLOOR DECK PLACEMENT (AREA A)
REPORT BY: ABH Page 3 of 3
INSTALLED MUSIC WING FRAME AND ONGOING ROOF JOIST INSTALLATION (AREA A)
ROOF DECK INSTALLATION (AREA A)
MOMENT WELDING (AREA A)