Massachusetts Department of Environmental Provided by MassDEP:
Protection MassDEP File #:083-2303
Bureau of Resource Protection - Wetlands eDEP Transaction #:1317874
WPA Form 5 - Order of Conditions City/Town:YARMOUTH
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
A. General Information
1. Conservation Commission YARMOUTH
2.Issuance a. r OOC
3. Applicant Details
a. First Name PETER/KIM
c. Organization
d. Mailing Address 212 MARINA DRIVE
e. City/Town QUINCY f. State
4. Property Owner
a. First Name PETER/KIM
c. Organization
d. Mailing Address 212 MARINA DRIVE
e. City/Town QUINCY f. State
5. Project Location
a.Street Address 40 MAYFLOWER TERRACE
b.City/Town YARMOUTH
d. Assessors 110
Map/Plat#
f. Latitude 41.69553N
6. Property recorded at the Registry of Deed for:
a. County b. Certificate
BARNSTABLE
7.Dates
b. r Amended OOC
b. Last Name LE
MA g. Zip Code
b. Last Name LE
MA g. Zip Code
c. Book
33476
a. Date NOI Filed: 10/14/2021 b. Date Public Hearing
Closed:
8.17inal Approved Plans and Other Documents
02169
02169
c. Zip Code 02664
e. Parcel/Lot# 33
g. Longitude 70.17685W
d. Page
III
10/21/2021 c. Date Of 10/28/2021
Issuance:
a. Plan Title: b. Plan Prepared by: c. Plan Signed/Stamped by: d. Revised Final Date: e. Scale:
PLAN OF LAND, KIERANHEALY BSC GROUP 10/8/2021 1"=10'
PROPOSED DECK
B. Findings
1.Findings pursuant to the Massachusetts Wetlands Protection Act
Following the review of the the above -referenced Notice of Intent and based on the information provided in this
application and presented at the public hearing, this Commission finds that the areas in which work is proposed is
significant to the following interests of the Wetlands Protection Act.
Check all that apply:
a. r Public Water Supply b. r Land Containing Shellfish c. r Prevention of Pollution
d. r Private Water Supply e. r Fisheries f. r Protection of Wildlife Habitat
g. r Ground Water Supply h. r Storm Damage Prevention i. r Flood Control
Page 1 of 12 * ELECTRONIC COPY
Bk 34730 Pg241 #79802
Massachusetts Department of Environmental
Protection
Bureau of Resource Protection - Wetlands
WPA Form 5 - Order of Conditions
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
2. Commission hereby finds the project, as proposed, is:
Provided by MassDEP:
MassDEP File #:083-2303
eDEP Transaction #:1317874
City/Town:YARMOUTH
Approved subject to:
a. r The following conditions which are necessary in accordance with the performance standards set forth in the
wetlands regulations. This Commission orders that all work shall be performed in accordance with the Notice of
Intent referenced above, the following General Conditions, and any other special conditions attached to this
Order. To the extent that the following conditions modify or differ from the plans, specifications, or other
proposals submitted with the Notice of Intent, these conditions shall control.
Denied because:
b. r The proposed work cannot be conditioned to meet the performance standards set forth in the wetland regulations.
Therefore, work on this project may not go forward unless and until a new Notice of Intent is submitted which
provides measures which are adequate to protect interests of the Act, and a final Order of Conditions is issued. A
description of the performance standards which the proposed work cannot meet is attached to this
Order.
c. r The information submitted by the applicant is not sufficient to describe the site, the work or the effect of the
work on the interests identified in the Wetlands Protection Act. Therefore, work on this project may not go
forward unless and until a revised Notice of Intent is submitted which provides sufficient information and
includes measures which are adequate to protect the interests of the Act , and a final Order of Conditions is
issued. A description of the specific information which is lacking and why it is necessary is attached to
this Order as per 310 CMR 10.05(6)(c).
3 r Buffer Zone Impacts -Shortest distance between limit of project disturbance and the wetland 17
resource area specified in 310CMR10.02(I)(a). a. linear feet
Inland Resource Area Impacts:(For Approvals Only):
Resource Area
Proposed
Permitted
Proposed
Permitted
Alteration
Alteration
Replacement
Replacement
4. r Bank
a. linear feet
b. linear feet
c. linear feet
d. linear feet
5. r Bordering Vegetated Wetland
a. square feet
b. square feet
c. square feet
d. square feet
6. r- Land under Waterbodies and Waterways
a. square feet
b. square feet
c. square feet
d. square feet
7. r Bordering Land Subject to Flooding
Cubic Feet Flood Storage
8. r Isolated Land Subject to Flooding
Cubic Feet Flood Storage
e. c/y dredged f, c/y dredged
a. square feet
b. square feet
c. square feet
d. square feet
e. cubic feet
f. cubic feet
g. cubic feet
h. cubic feet
a. square feet b. square feet
c. cubic feet d. cubic feet e. cubic feet ff, cubic feet
Page 2 of 12 * ELECTRONIC COPY
Bk 34730 Pg242 #79802
Massachusetts Department of Environmental
Protection
Bureau of Resource Protection - Wetlands
WPA Form 5 - Order of Conditions
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
9. r Riverfront Area
Provided by MassDEP:
MassDEP File #:083-2303
eDEP Transaction #:1317874
City/Town:YARMOUTH
Sq ft within 100 ft 1
c. square feet d. square feet e. square feet f. square feet
Sq ft between 100-200 ft
g. square feet h. square feet i. square feet j. square feet
Coastal Resource Area Impacts:
Resource Area Proposed Permitted Proposed Permitted
Alteration Alteration Replacement Replacement
10. r Designated Port Areas
Indicate size under Land Under the Ocean, below
11. F- Land Under the Ocean
a. square feet b. square feet
c. c/y dredged d. c/y dredged
12. r Barrier Beaches
Indicate size under Coastal Beaches and/or Coastal Dunes below
13. r Coastal Beaches
a. square feet b. square feet c. c/y nourishment d. c/y nourishment
14. r Coastal Dunes
a. square feet b. square feet c. c/y nourishment d. c/y nourishment
15. F- Coastal Banks
a. linear feet b. linear feet
16. r Rocky Intertidal Shores
a. square feet b. square feet
17. r Salt Marshes
a. square feet b. square feet c. square feet d. square feet
18. r Land Under Salt Ponds
a. square feet b. square feet
c. c/y dredged d. c/y dredged
19. r Land Containing Shellfish
a. square feet b. square feet c. square feet d. square feet
Indicate size under Coastal Banks, inland Bank, Land Under the
20. r Fish Runs
Ocean, and/or inland Land Under Waterbodies and Waterways,
above
c. c/y dredged d. c/y dredged
21. r Land Subject to Coastal Storm Flowage
a. square feet b. square feet
22.
Page 3 of 12 * ELECTRONIC COPY
Bk 34730 Pg243 #79802
Massachusetts Department of Environmental
Protection
Bureau of Resource Protection - Wetlands
WPA Form 5 - Order of Conditions
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
Provided by MassDEP:
MassDEP File #:083-2303
eDEP Transaction #:1317874
City/Town:YARMOUTH
r Restoration/Enhancement (For Approvals Only)
If the project is for the purpose of restoring or enhancing a wetland resource area in addition to the square footage
that has been entered in Section B.5.c & d or B.17.c & d above, please entered the additional amount here.
a. square feet of BVW
23.
F- Streams Crossing(s)
b. square feet of Salt Marsh
If the project involves Stream Crossings, please enter the number of new stream crossings/number of replacement
stream crossings,
a. number of new stream crossings b. number of replacement stream
crossings
C. General Conditions Under Massachusetts Wetlands Protection Act
The following conditions are only applicable to Approved projects
1. Failure to comply with all conditions stated herein, and with all related statutes and other regulatory measures,
shall be deemed cause to revoke or modify this Order.
2. The Order does not grant any property rights or any exclusive privileges; it does not authorize any injury to
private property or invasion of private rights.
3. This Order does not relieve the permittee or any other person of the necessity of complying with all other
applicable federal, state, or local statutes, ordinances, bylaws, or regulations.
4. The work authorized hereunder shall be completed within three years from the date of this Order unless either
of the following apply:
a. the work is a maintenance dredging project as provided for in the Act; or
b. the time for completion has been extended to a specified date more than three years, but less than five
years, from the date of issuance. If this Order is intended to be valid for more than three years, the
extension date and the special circumstances warranting the extended time period are set forth as a
special condition in this Order.
5. This Order may be extended by the issuing authority for one or more periods of up to three years each upon
application to the issuing authority at least 30 days prior to the expiration date of the Order.
6. If this Order constitutes an Amended Order of Conditions, this Amended Order of Conditions does not exceed
the issuance date of the original Final Order of Conditions.
7. Any fill used in connection with this project shall be clean fill. Any fill shall contain no trash, refuse, rubbish,
or debris, including but not limited to lumber, bricks, plaster, wire, lath, paper, cardboard, pipe, tires, ashes,
refrigerators, motor vehicles, or parts of any of the foregoing.
8. This Order is not final until all administrative appeal periods from this Order have elapsed, or if such an appeal
has been taken, until all proceedings before the Department have been completed.
9. No work shall be undertaken until the Order has become final and then has been recorded in the Registry of
Deeds or the Land Court for the district in which the land is located, within the chain of title of the affected
property. In the case of recorded land, the Final Order shall also be noted in the Registry's Grantor Index under
the name of the owner of the land upon which the proposed work is to be done. In the case of the registered
land, the Final Order shall also be noted on the Land Court Certificate of Title of the owner of the land upon
which the proposed work is done. The recording information shall be submitted to the Conservation
Commission on the form at the end of this Order, which form must be stamped by the Registry of Deeds, prior
to the commencement of work..
10. A sign shall be displayed at the site not less then two square feet or more than three square feet in size bearing
the words,
Page 4 of 12 * ELECTRONIC COPY
Bk 34730 Pg244 #79802
Massachusetts Department of Environmental
Protection
Bureau of Resource Protection - Wetlands
WPA Form 5 - Order of Conditions
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
Provided by MassDEP:
MassDEP File #:083-2303
eDEP Transaction #:1317874
City/Town:YARMOUTH
" Massachusetts Department of Environmental Protection"
[or'MassDEP"]
File Number :"083-2303"
11. Where the Department of Environmental Protection is requested to issue a Superseding Order, the
Conservation Commission shall be a party to all agency proceedings and hearings before Mass DER
12. Upon completion of the work described herein, the applicant shall submit a Request for Certificate of
Compliance (WPA Form 8A) to the Conservation Commission.
13. The work shall conform to the plans and special conditions referenced in this order.
14. Any change to the plans identified in Condition #13 above shall require the applicant to inquire of the
Conservation Commission in writing whether the change is significant enough to require the filing of a new
Notice of Intent.
15. The Agent or members of the Conservation Commission and the Department of Environmental Protection shall
have the right to enter and inspect the area subject to this Order at reasonable hours to evaluate compliance with
the conditions stated in this Order, and may require the submittal of any data deemed necessary by the
Conservation Commission or Department for that evaluation.
16. This Order of Conditions shall apply to any successor in interest or successor in control of the property subject
to this Order and to any contractor or other person performing work conditioned by this Order.
17. Prior to the start of work, and if the project involves work adjacent to a Bordering Vegetated Wetland, the
boundary of the wetland in the vicinity of the proposed work area shall be marked by wooden stakes or flagging.
Once in place, the wetland boundary markers shall be maintained until a Certificate of Compliance has been
issued by the Conservation Commission.
18. All sedimentation barriers shall be maintained in good repair until all disturbed areas have been fully stabilized
with vegetation or other means. At no time shall sediments be deposited in a wetland or water body. During
construction, the applicant or his/her designee shall inspect the erosion controls on a daily basis and shall
remove accumulated sediments as needed. The applicant shall immediately control any erosion problems that
occur at the site and shall also immediately notify the Conservation Commission, which reserves the right to
require additional erosion and/or damage prevention controls it may deem necessary. Sedimentation barriers
shall serve as the limit of work unless another limit of work line has been approved by this Order.
NOTICE OF STORMWATER CONTROL AND MAINTENANCE REQUIREMENTS
19. The work associated with this Order(the "Project") is (1) F- is not (2)r subject to the Massachusetts
Stormwater Standards. If the work is subject to Stormwater Standards, then the project is subject to the
following conditions;
a) All work, including site preparation, land disturbance, construction and redevelopment, shall be implemented
in accordance with the construction period pollution prevention and erosion and sedimentation control plan
and, if applicable, the Stormwater Pollution Prevention Plan required by the National Pollutant Discharge
Elimination System Construction General Permit as required by Stormwater Standard 8. Construction period
erosion, sedimentation and pollution control measures and best management practices (BMPs) shall remain
in place until the site is fully stabilized.
b) No stormwater runoff may be discharged to the post -construction stormwater BMPs unless and until a
Registered Professional Engineer provides a Certification that: i. all construction period BMPs have been
removed or will be removed by a date certain specified in the Certification. For any construction period
BMPs intended to be converted to post construction operation for stormwater attenuation, recharge, and/or
treatment, the conversion is allowed by the MassDEP Stormwater Handbook BMP specifications and that the
BMP has been properly cleaned or prepared for post construction operation, including removal of all
construction period sediment trapped in inlet and outlet control structures; ii.. as -built final construction
BMP plans are included, signed and stamped by a Registered Professional Engineer, certifying the site is
Page 5 of 12 * ELECTRONIC COPY
Bk 34730 Pg245 #79802
Massachusetts Department of Environmental
Protection
Bureau of Resource Protection - Wetlands
WPA Form 5 - Order of Conditions
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
Provided by MassDEP:
MassDEP File #:083-2303
eDEP Transaction #:1317874
City/Town:YARMOUTH
fully stabilized; iii. any illicit discharges to the stormwater management system have been removed, as per
the requirements of Stormwater Standard 10; iv. all post -construction stormwater BMPs are installed in
accordance with the plans (including all planting plans) approved by the issuing authority, and have been
inspected to ensure that they are not damaged and that they are in proper working condition; v. any vegetation
associated with post -construction BMPs is suitably established to withstand erosion.
c) The landowner is responsible for BMP maintenance until the issuing authority is notified that another party
has legally assumed responsibility for BMP maintenance. Prior to requesting a Certificate of Compliance, or
Partial Certificate of Compliance, the responsible party (defined in General Condition 19(e)) shall execute
and submit to the issuing authority an Operation and Maintenance Compliance Statement ("O&M Statement")
for the Stormwater BMPs identifying the party responsible for implementing the stormwater BMP Operation
and Maintenance Plan ("O&M Plan") and certifying the following: i.) the O&M Plan is complete and will be
implemented upon receipt of the Certificate of Compliance, and ii.) the future responsible parties shall be
notified in writing of their ongoing legal responsibility to operate and maintain the stormwater management
BMPs and implement the Stormwater Pollution Prevention Plan.
d) Post -construction pollution prevention and source control shall be implemented in accordance with the long-
term pollution prevention plan section of the approved Stormwater Report and, if applicable, the Stormwater
Pollution Prevention Plan required by the National Pollutant Discharge Elimination System Multi -Sector
General Permit.
e) Unless and until another party accepts responsibility, the landowner, or owner of any drainage easement,
assumes responsibility for maintaining each BMP. To overcome this presumption, the landowner of the
property must submit to the issuing authority a legally binding agreement of record, acceptable to the issuing
authority, evidencing that another entity has accepted responsibility for maintaining the BMP, and that the
proposed responsible party shall be treated as a permittee for purposes of implementing the requirements of
Conditions 19(f) through 19(k) with respect to that BMP. Any failure of the proposed responsible party to
implement the requirements of Conditions 19(f) through 19(k) with respect to that BMP shall be a violation
of the Order of Conditions or Certificate of Compliance. In the case of stormwater BMPs that are serving
more than one lot, the legally binding agreement shall also identify the lots that will be serviced by the
stormwater BMPs. A plan and easement deed that grants the responsible party access to perform the required
operation and maintenance must be submitted along with the legally binding agreement.
f) The responsible party shall operate and maintain all stormwater BMPs in accordance with the design plans,
the O&M Plan, and the requirements of the Massachusetts Stormwater Handbook.
g) The responsible party shall:
1. Maintain an operation and maintenance log for the last three (3) consecutive calendar years of
inspections, repairs, maintenance and/or replacement of the stormwater management system or any part
thereof, and disposal (for disposal the log shall indicate the type of material and the disposal location);
2. Make the maintenance log available to MassDEP and the Conservation Commission ("Commission")
upon request; and
3. Allow members and agents of the MassDEP and the Commission to enter and inspect the site to evaluate
and ensure that the responsible party is in compliance with the requirements for each BMP established in
the O&M Plan approved by the issuing authority.
h) All sediment or other contaminants removed from stormwater BMPs shall be disposed of in accordance with
all applicable federal, state, and local laws and regulations.
i) Illicit discharges to the stormwater management system as defined in 310 CMR 10.04 are prohibited.
j ) The stormwater management system approved in the Order of Conditions shall not be changed without the
prior written approval of the issuing authority.
Page 6 of 12 * ELECTRONIC COPY
Bk 34730 Pg246 #79802
Massachusetts Department of Environmental
Protection
Bureau of Resource Protection - Wetlands
WPA Form 5 - Order of Conditions
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
Provided by MassDEP:
MassDEP File #:083-2303
eDEP Transaction #:1317874
Citytrown:YARMOUTH
k) Areas designated as qualifying pervious areas for the purpose of the Low Impact Site Design Credit (as
defined in the MassDEP Stormwater Handbook, Volume 3, Chapter 1, Low Impact Development Site Design
Credits) shall not be altered without the prior written approval of the issuing authority.
1) Access for maintenance, repair, and/or replacement of BMPs shall not be withheld. Any fencing constructed
around stormwater BMPs shall include access gates and shall be at least six inches above grade to allow for
wildlife passage.
Special Conditions:
D. Findings Under Municipal Wetlands Bylaw or Ordinance
1.Is a municipal wetlands bylaw or ordinance applicable? r Yes r No
2.The Conservation Commission hereb check one that applies):
a. F- DENIES the proposed work which cannot be conditioned
to meet the standards set forth in a municipal ordinance
or bylaw specifically:
1. Municipal Ordinance or Bylaw
2. Citation
Therefore, work on this project may not go forward unless and until a revised Notice of Intent is submitted which
provides measures which are adequate to meet these standards, and a final Order or Conditions is issued. Which
are necessary to comply with a municipal ordinance or bylaw:
b'r APPROVES the proposed work, subject to the
following additional conditions.
1. Municipal Ordinance or YARMOUTH
Bylaw WETLAND BY-LAW 2. Citation CHAPTER 143
3 The Commission orders that all work shall be performed in accordance with the following conditions and with the
Notice of Intent referenced above. To the extent that the following conditions modify or differ from the plans,
specifications, or other proposals submitted with the Notice of Intent, the conditions shall control.
The special conditions relating to municipal ordinance or bylaw are as follows:
SC#1. THIS ORDER SHALL APPLY TO ANY SUCCESSORS AND ASSIGNS IN INTEREST OR CONTROL
AND ANY OTHER PERSON ENGAGING IN ACTIVITY ON THE PROPERTY IDENTIFIED IN THE NOTICE
OF INTENT.
SC#2. THE APPLICANT/OWNER SHALL BE RESPONSIBLE FOR HAVING A COPY OF THE "ORDER OF
CONDITIONS" ON THE JOB SITE AT ALL TIMES AND SHALL BE RESPONSIBLE FOR INSURING THAT
ALL PERSONS PERFORMING THE PERMITTED ACTIVITY ARE FULLY AWARE OF ITS TERMS AND
CONDITIONS. FAILURE TO DO SO MAY RESULT IN THE REVOCATION OF THESE "ORDERS", A FINE OR
BOTH.
SC#3. THE CONSERVATION COMMISSION, ITS AGENT(S) OR ASSIGNED(S) SHALL HAVE THE EXPRESS
RIGHT OF ENTRY UPON THE JOB SITE AT ALL REASONABLE T M ES FOR THE PURPOSES OF
Page 7 of 12 * ELECTRONIC COPY
Bk 34730 Pg247 #79802
Massachusetts Department of Environmental
Protection
Bureau of Resource Protection - Wetlands
WPA Form 5 - Order of Conditions
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
Provided by MassDEP:
MassDEP File #:083-2303
eDEP Transaction #:1317874
City/Town:YARMOUTH
ESTABLISHING COMPLIANCE WITH THE "ORDER OF CONDITIONS", 'BY-LAWS" AND "REGULATIONS".
COMMISSION MEMBERS AND THE CONSERVATION ADMINISTRATOR MAY ACQUIRE ANY
INFORMATION, MEASUREMENTS, PHOTOGRAPHS, OBSERVATIONS AND/OR MATERIALS OR MAY
REQUIRE THE SUBMITTAL OF ANY DATA/INFORMATION DEEMED NECESSARY BY THIS COMMISSION
FOR THAT EVALUATION.
SC#4. A PRECONSTRUCTION REVIEW SHALL BE ARRANGED BY THE CONTRACTOR WITH THE
CONSERVATION ADMINISTRATOR AND SHALL OCCUR PRIOR TO THE COMMENCEMENT OF ANY
WORK.
SC#5. ANY CHANGE IN THE APPROVED PLAN(S) SHALL REQUIRE THE APPLICANT TO FILE, IN
WRITING, A NOTICE OF PROJECT CHANGE WITH THIS COMMISSION. THE COMMISSION WILL
DETERMINE THE SIGNIFICANCE OF THE CHANGE AND DETERMINE WHETHER ADMINISTRATIVE
APPROVAL OR AN "AMENDED ORDER OF CONDITIONS" IS REQUIRED. SHOULD THE PROJECT BE
CHANGED WITHOUT PERMISSION, OR FOUND BY THE YARMOUTH CONSERVATION COMMISSION TO
BE ALTERED IN ANY WAY FROM THE APPROVED PLAN(S), ALL WORK WILL IMMEDIATELY CEASE
UNTIL THE PROJECT IS REAPPROVED BY THE COMMISSION.
SC#6. THE "ORDER OF CONDITIONS" IS VALID FOR THREE YEARS FROM THE DATE OF ISSUANCE
UNLESS OTHERWISE SPECIFICALLY NOTED IN THE "ORDERS". EXTENSION PERMIT REQUESTS MUST
BE APPLIED FOR AT LEAST 30 CALENDAR DAYS PRIOR TO THE EXPIRATION DATE OF THE ORIGINAL
ORDERS". FAILURE TO DO SO WILL RESULT IN A NEW 'NOTICE OF INTENT" FILING.
SC#7. NONCOMPLIANCE WITH THESE CONDITIONS SHALL CONSTITUTE GROUNDS FOR AN
ENFORCEMENT ORDER AND POSSIBLE FINES. FINES SHALL NOT EXCEED $300.00 PER DAY/PER
VIOLATION.
SC#8. DEBRIS, INCLUDING LITTER, SHALL BE PICKED UP IMMEDIATELY. ANY EXCESS MATERIAL
THAT IS EXCAVATED FROM THE JOB SITE SHALL BE DISPOSED OF AT A LOCATION APPROVED BY
THE CONSERVATION ADMINISTRATOR OR IN A COVERED DUMPSTER. NO DEBRIS SHALL BE
ALLOWED IN A WETLAND OR WATERWAY.
SC#9. WASHING OF EQUIPMENT/TOOLS SHALL BE DONE OFF -SITE OR HANDLED IN A MANNER
APPROPRIATE BY THE CONSERVATION ADMINISTRATOR
SC#10. NO EQUIPMENT SHALL BE REFUELED, NOR SHALL FUEL BE STORED WITHIN 100 FEET OF A
RESOURCE AREA.
SC#11. ANY AREA THAT IS DISTURBED DURING CONSTRUCTION SHALL BE REVEGETATED
IMMEDIATELY OR AS SOON AFTER AS THE GROWING SEASON COMMENCES, WITH APPROPRIATE
NATIVE PLANTINGS. PERMANENT STABILIZATION SHALL BE CARRIED OUT IN ORDER TO MINUV=
EROSION.
SC#12. 310 CMR 10.30(3) PROMULGATED UNDER MGL C. 131, S. 40, REQUIRES THAT NO COASTAL
STRUCTURE, SUCH AS A BULKHEAD, REVETMENTS OR SEAWALL SHALL BE PERMITTED ON AN
ERODING BANK AT ANY TIME IN THE FUTURE TO PROTECT THE PROJECT ALLOWED BY THIS
ORDER OF CONDITIONS. THIS CONDITION SHALL BE AN ONGOING IN PERPETUITY AND DOES NOT
Page 8 of 12 * ELECTRONIC COPY
Bk 34730 Pg248 #79802
Massachusetts Department of Environmental
Protection
Bureau of Resource Protection - Wetlands
WPA Form 5 - Order of Conditions
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
Provided by MassDEP:
MassDEP File #:083-2303
eDEP Transaction #:1317874
City/Town:YARMOUTH
EXPIRE WITH THE ISSUANCE OF THE CERTIFICATE OF COMPLIANCE. (WORK ON A COASTAL BANK
ONLY)
SC#13. NATIVE BUFFER VEGETATION SHALL BE PLANTED PER THE APPROVED PLAN. IN ADDITION,
PLANTING AREA NUMBER 2 SHALL BE EXPANDED TO INCLUDE THE ACCESS AREA TO THE PRE-
EXISTING DOCK, ONCE THE DOCK IS RELOCATED TO ITS NEW LOCATION. THE BUFFER VEGETATION
SHALL BE LEFT UNDISTURBED. THIS IS AN ON -GOING CONDITION, IN -PERPETUITY, THAT DOES NOT
EXPIRE WITH THE ISSUANCE OF A CERTIFICATE OF COMPLIANCE. THE APPLICANT MUST WAIT
UNTIL THE SECOND GROWING SEASON IS COMPLETE BEFORE THE REQUEST FOR A CERTIFICATE
OF COMPLIANCE IS SUBMITTED. DURING THIS TIME PERIOD, THE COMMISSION/CONSERVATION
ADMINISTRATOR MAY REQUIRE ADDITIONAL PLANTINGS IF IT IS DETERMINED THAT ANY
SPECIMENS ARE DEAD OR DYING AND NEED REPLACEMENT.
SC#14. LANDSCAPE DEBRIS, INCLUDING LEAVES, GRASS CLIPPINGS, BRUSH, OR OTHER SHALL
NOT BE ALLOWED WITHIN THE WETLAND RESOURCE AREA. THIS IS AN ON -GOING CONDITION
THAT DOES NOT EXPIRE WITH THE ISSUANCE OF A CERTIFICATE OF COMPLIANCE.
SC#15. A STAMPED "AS BUILT PLAN' SHALL BE CERTIFIED BY THE DESIGN ENGINEER
(MASSACHUSETTS REGISTERED PROFESSIONAL ENGINEER OR LAND SURVEYOR) AND WILL
CERTIFY THAT THIS PROJECT HAS BEEN COMPLETED IN ACCORDANCE WITH THE "ORDER OF
CONDITIONS" BEFORE A CERTIFICATE OF COMPLIANCE WILL BE ISSUED. THE AS -BUILT PLAN
SHALL INDICATE THE STRUCTURE LOCATION, GRADIENTS, DISTANCES TO THE RESOURCE AREAS,
AND OTHER PERTINENT INFORMATION DESCRIBED IN THE APPLICATION AND APPROVED PLANS.
ANY DEVIATION FROM THE APPROVED PLAN SHALL BE IDENTIFIED.
SC#16. UPON COMPLETION OF THE PROJECT, A "REQUEST FOR A "CERTIFICATE OF COMPLIANCE"
SHALL BE SUBMITTED BY THE APPLICANT TO THE CONSERVATION COMMISSION FOR REVIEW. THE
"ORDER OF CONDITIONS" SHALL BE CONSIDERED INCOMPLETE UNTIL THE "CERTIFICATE OF
COMPLIANCE" IS ISSUED BY THE CONSERVATION COMMISSION AND RECORDED AT THE REGISTRY
OF DEEDS.
Page 9 of 12 * ELECTRONIC COPY
Bk 34730 Pg249 #79802
Massachusetts Department of Environmental
Protection
Bureau of Resource Protection - Wetlands
WPA Form 5 - Order of Conditions
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
Provided by MassDEP:
MassDEP File #:SE83-2303
eDEP Transaction #:1317874
City/Town:YARMOUTH
E. Signatures
This Order is valid for three years from the date of issuance, unless otherwise
specified pursuant to General Condition #4. If this is an Amended Order of
Conditions, the Amended Order expires on the same date as the original Order of 1. Date of Original Order
Conditions.
Please indicate the number of members who will sign this form. This Order must
be signed by a majority of the Conservation Commission.
7
Number of Signers
The Order must be mailed by certified mail (return receipt requested) or hand delivered to the applicant. A copy also
must be mailed or hand delivered at the same time to the appropriate Department of Environmental Protection
Regional Office, if not filing electronically, and the property owner, ifd V91V ,nerj'ni, - j3vli�t.
Signatures:
I— by hand delivery on
Date
F. Appeals
P by certified mail, return receipt requested, on
Date / ()/ 28 / Z0 2—
The applicant, the owner, any person aggrieved by this Order, any owner of land abutting the land subject to this Order,
or any ten residents of the city or town in which such land is located, are hereby notified of their right to request the
appropriate MassDEP Regional Office to issue a Superseding Order of Conditions. The request must be made by
certified mail or hand delivery to the Department, with the appropriate filing fee and a completed Request for
Departmental Action Fee Transmittal Form, as provided in 310 CMR 10.03(7) within ten business days from the date
of issuance of this Order. A copy of the request shall at the same time be sent by certified mail or hand delivery to the
Conservation Commission and to the applicant, if he/she is not the appellant.
Any appellants seeking to appeal the Department's Superseding Order associated with this appeal will be required to
demonstrate prior participation in the review of this project. Previous participation in the permit proceeding means
the submission of written information to the Conservation Commission prior to the close of the public hearing,
requesting a Superseding Order, or providing written information to the Department prior to issuance of a
Superseding Order.
The request shall state clearly and concisely the objections to the Order which is being appealed and how the Order
does not contribute to the protection of the interests identified in the Massachusetts Wetlands Protection Act
Page 10 of 12 * ELECTRONIC COPY
Bk 34730 Pg250 #79802
Massachusetts Department of Environmental
Protection
Bureau of Resource Protection - Wetlands
WPA Form 5 - Order of Conditions
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
Provided by MassDEP:
MassDEP File #:083-2303
eDEP Transaction #:1317874
City/Town:YARMOUTH
(M.G.L. c. 131, § 40), and is inconsistent with the wetlands regulations (310 CMR 10.00). To the extent that the
Order is based on a municipal ordinance or bylaw, and not on the Massachusetts Wetlands Protection Act or
regulations, the Department has no appellate jurisdiction.
G. Recording Information
This Order of Conditions must be recorded in the Registry of Deeds or the Land Court for the district in which the
land is located, within the chain of title of the affected property. In the case of recorded land, the Final Order shall
also be noted in the Registry's Grantor Index under the name of the owner of the land subject to the Order. In the case
of registered land, this Order shall also be noted on the Land Court Certificate of Title of the owner of the land
subject to the Order of Conditions. The recording information on this page shall be submitted to the Conservation
Commission listed below.
YARMOUTH
Conservation Commission
Detach on dotted line, have stamped by the Registry of Deeds and submit to the Conservation Commission.
To:
YARMOUTH
Conservation Commission
Please be advised that the Order of Conditions for the Project at:
40 MAYFLOWER TERRACE
0 8 3 -23 03
Project Location
MassDEP File Number
Has been recorded at the Registry of Deeds of:
County Book
Page
for:
Property Owner PETER/KIMLE
and has been noted in the chain of title of the affected property in:
Book
Page
In accordance with the Order of Conditions issued on:
Date
If recorded land, the instrument number identifying this transaction is:
Instrument Number
If registered land, the document number identifying this transaction is:
Document Number
Page 11 of 12 * ELECTRONIC COPY
Bk 34730 Pg251 #79802
Massachusetts Department of Environmental Provided by MassDEP:
Protection MassDEP File #:083-2303
Bureau of Resource Protection - Wetlands eDEP Transaction #:1317874
WPA Form 5 - Order of Conditions City/Ibwn:YARMOUTH
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
Signature of Applicant
Rev. 4/1/2010
Page 12 of 12 * ELECTRONIC COPY