Architect: Perkins Eastman DPC
Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File
ARCHITECT’S SITE OBSERVATION REPORT
DATE OF VISIT: 12/09/2021 PROJECT: Dennis Yarmouth Intermediate
Middle School
286 Station Avenue
South Yarmouth, MA 02664
DATE OF ISSUE: 12/13/2021 PROJECT NO: 71011
WEATHER
CONDITIONS:
SUNNY, CLEAR, low 50s ARCHITECT: Perkins Eastman, DPC
20 Ashburton Street
8th floor
Boston, MA
The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit.
WORK IN PROGRESS:
1) CFMF and interior partition framing
2) Exterior sheathing and parapet insulation installation
3) Blocking/prep for roofing
4) CMU masonry at elevator bulkhead in C
5) Steel detailing by Norgate/stellar
6) Underground Electrical
7) Underground plumbing
8) HVAC at auditorium lower seating area
9) HVAC, and plumbing overhead rough-in
10) Building earthwork: backfilling
11) Site work: Data bank installation
12) Fenagh is on site for welding inspections
FIELD OBSERVATIONS:
PE visited the site on Thursday 12-09, to review ongoing progress with the light-gage/CFMF installation, concrete slab
placement, roofing, building earthwork, site utility work, etc.
1. At the time of observation, Colony had most completed framing of exterior walls at C, and was installing window
blocking and detailing some areas in Area C; Colony was continuing to frame interior partitions on the first floor of
Area D. CFMF framing is commencing in areas A and B, beginning with the upper atrium walls in B.
2. Arden and Harold Bros are continuing with the overhead rough-in for Area D, now on both levels.
3. The roof membrane / insulation installation for Area D by Stanley appears to be complete; they are substantially
complete with sheathing parapets and setting blocking, drains etc. for Area C roof work (see photo); roofing
materials for Area C roof due 12-10 according to Commodore. Pour of elevator bulkhead roof deck scheduled for
12-10.
4. SOG is complete at the gymnasium area of B; wet cure is still in place
5. Lighthouse masonry are in the process of completing the Area C elevator shaft; they were laying the top course at
the roof bulkhead at the time of observation (see photo).
6. Annese and Harold Brothers are continuing to install underground electrical work at both areas A and B; most of
the trenching for plumbing in Area A has been backfilled by RBO (see photos).
7. Arden is in the process of installing the under-seat displacement ventilation at the auditorium (see photo).
8. Norgate/Stellar steel are back on site to complete detailing. At the time of observation they were installing curtain
wall sill angles in the B-C west “link.”
9. Building earthwork: Robert B. Our is continuing to install stone and backfill underslab utilities.
10. Site utility work: Communication ductbank has been roughed in and appears ready for concrete to be poured (see
photo).
11. Site electrical work: Annese is continuing to set light pole bases on the site.
REPORT BY: ABH Page 2 of 4
DISCREPANCIES, SPECIAL INSTRUCTIONS
· ‘Design intent’ questions from Lighthouse: PE had a discussion with Commodore and the Lighthouse masonry
foreman regarding details such as brick cutting at non-coursing (atypical) brick piers.
· (from 12-02 site report): EOS discrepancies. Update: At the time of observation, Silverback had formed out the
EOS extensions at the Area D north “bump-outs.”
· (From 11-24 site report): Sunshade outrigger discrepancies: Update: It was observed that the “as built”
coordination of outrigger installation with window jambs appears to be more precise for C than for D (see photo).
SITE PHOTOS
SHEATHING PROGRESS – SW CORNER (AREA D) EOS CONDITION AT TYPICAL COL BASE (AREA D)
CFMF INFILL @ LINK CW SILL (AREA C) LEVEL 1 OUTRIGGER OFFSET (AREA D)
REPORT BY: ABH Page 3 of 4
ROOFING PREP AND SOUTH FAÇADE CFM FRAMING (AREA C)
MASONRY WORK AT ELEVATOR SHAFT BULKHEAD (AREA C)
UNDERSLAB DIFFISION VENTILATION DUCTWORK (AREA A) COMMUNICATIONS DUCTBANK (AREA A)
REPORT BY: ABH Page 4 of 4
OUTRIGGER ALIGNMENT (AREA C) PLUMBING TRENCH AT ADMIN AREA (AREA B)
FUTURE ELECTRICAL ROOM (AREA A) UG COMMUNICATIONS LINES INSTALLATION (AREA B)
PLACED SLAB ON GRADE AT GYMNASIUM (AREA B)