Loading...
HomeMy WebLinkAboutDYIMS PE Site report 20211209 Architect: Perkins Eastman DPC Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File ARCHITECT’S SITE OBSERVATION REPORT DATE OF VISIT: 12/09/2021 PROJECT: Dennis Yarmouth Intermediate Middle School 286 Station Avenue South Yarmouth, MA 02664 DATE OF ISSUE: 12/13/2021 PROJECT NO: 71011 WEATHER CONDITIONS: SUNNY, CLEAR, low 50s ARCHITECT: Perkins Eastman, DPC 20 Ashburton Street 8th floor Boston, MA The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit. WORK IN PROGRESS: 1) CFMF and interior partition framing 2) Exterior sheathing and parapet insulation installation 3) Blocking/prep for roofing 4) CMU masonry at elevator bulkhead in C 5) Steel detailing by Norgate/stellar 6) Underground Electrical 7) Underground plumbing 8) HVAC at auditorium lower seating area 9) HVAC, and plumbing overhead rough-in 10) Building earthwork: backfilling 11) Site work: Data bank installation 12) Fenagh is on site for welding inspections FIELD OBSERVATIONS: PE visited the site on Thursday 12-09, to review ongoing progress with the light-gage/CFMF installation, concrete slab placement, roofing, building earthwork, site utility work, etc. 1. At the time of observation, Colony had most completed framing of exterior walls at C, and was installing window blocking and detailing some areas in Area C; Colony was continuing to frame interior partitions on the first floor of Area D. CFMF framing is commencing in areas A and B, beginning with the upper atrium walls in B. 2. Arden and Harold Bros are continuing with the overhead rough-in for Area D, now on both levels. 3. The roof membrane / insulation installation for Area D by Stanley appears to be complete; they are substantially complete with sheathing parapets and setting blocking, drains etc. for Area C roof work (see photo); roofing materials for Area C roof due 12-10 according to Commodore. Pour of elevator bulkhead roof deck scheduled for 12-10. 4. SOG is complete at the gymnasium area of B; wet cure is still in place 5. Lighthouse masonry are in the process of completing the Area C elevator shaft; they were laying the top course at the roof bulkhead at the time of observation (see photo). 6. Annese and Harold Brothers are continuing to install underground electrical work at both areas A and B; most of the trenching for plumbing in Area A has been backfilled by RBO (see photos). 7. Arden is in the process of installing the under-seat displacement ventilation at the auditorium (see photo). 8. Norgate/Stellar steel are back on site to complete detailing. At the time of observation they were installing curtain wall sill angles in the B-C west “link.” 9. Building earthwork: Robert B. Our is continuing to install stone and backfill underslab utilities. 10. Site utility work: Communication ductbank has been roughed in and appears ready for concrete to be poured (see photo). 11. Site electrical work: Annese is continuing to set light pole bases on the site. REPORT BY: ABH Page 2 of 4 DISCREPANCIES, SPECIAL INSTRUCTIONS · ‘Design intent’ questions from Lighthouse: PE had a discussion with Commodore and the Lighthouse masonry foreman regarding details such as brick cutting at non-coursing (atypical) brick piers. · (from 12-02 site report): EOS discrepancies. Update: At the time of observation, Silverback had formed out the EOS extensions at the Area D north “bump-outs.” · (From 11-24 site report): Sunshade outrigger discrepancies: Update: It was observed that the “as built” coordination of outrigger installation with window jambs appears to be more precise for C than for D (see photo). SITE PHOTOS SHEATHING PROGRESS – SW CORNER (AREA D) EOS CONDITION AT TYPICAL COL BASE (AREA D) CFMF INFILL @ LINK CW SILL (AREA C) LEVEL 1 OUTRIGGER OFFSET (AREA D) REPORT BY: ABH Page 3 of 4 ROOFING PREP AND SOUTH FAÇADE CFM FRAMING (AREA C) MASONRY WORK AT ELEVATOR SHAFT BULKHEAD (AREA C) UNDERSLAB DIFFISION VENTILATION DUCTWORK (AREA A) COMMUNICATIONS DUCTBANK (AREA A) REPORT BY: ABH Page 4 of 4 OUTRIGGER ALIGNMENT (AREA C) PLUMBING TRENCH AT ADMIN AREA (AREA B) FUTURE ELECTRICAL ROOM (AREA A) UG COMMUNICATIONS LINES INSTALLATION (AREA B) PLACED SLAB ON GRADE AT GYMNASIUM (AREA B)