HomeMy WebLinkAboutDYIMS PE Site report 20211202 Architect: Perkins Eastman DPC Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File ARCHITECT’S SITE OBSERVATION REPORT DATE OF VISIT: 12/02/2021 PROJECT: Dennis Yarmouth Intermediate Middle School 286 Station Avenue South Yarmouth, MA 02664 DATE OF ISSUE: 12/13/2021 PROJECT NO: 71011 WEATHER CONDITIONS: SUNNY, CLEAR, cold, low 40s ARCHITECT: Perkins Eastman, DPC 20 Ashburton Street 8th floor Boston, MA The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit. WORK IN PROGRESS: 1) Misc metals installation 2) CFMF and interior partition framing 3) Exterior sheathing and parapet insulation installation 4) Roofing and blocking/prep for roofing 5) Concrete slab-on-grade placement 6) CMU masonry at elevator shaft in C 7) Underground Electrical 8) Underground plumbing 9) HVAC, and plumbing overhead rough-in 10) Annese electrical site work: utility pole bases 11) General site utility work FIELD OBSERVATIONS: PE visited the site on Thursday 12-02, to review ongoing progress with the light-gage/CFMF installation, misc metals, concrete slab placement, roofing, building earthwork, site utility work, etc. 1. United is installing the two stairs at the east/west ends of Area C, as well as the outriggers for the sun shades on the C south façade. 2. Colony has commenced framing of interior walls on the first floor of Area D, is completing the 2nd floor, and continuing to work on framing exterior walls at C, behind the misc, metals outrigger installation by United. Colony is in the process of blocking the windows on D ahead of the sheathing installation, as well as installing sheathing and parapet insulation the north façade of D. Also, CFMF framing at exterior walls is ongoing at Area C and the C-D links. 3. Arden and Harold Bros are continuing with the overhead rough-in for Area D (see photo). 4. The roof membrane / insulation installation for Area D is substantially complete and Stanley has almost finished sheathing parapets and setting blocking, drains etc. in Area C; just waiting for materials. 5. Silver back placed the 2nd floor SOD at Area B earlier in the week, and at the time of observation was in the process of pouring/placing the level 1 SOG at the Area B gymnasium and ancillary areas, including leveling and burnishing the slab (see photos). Saw cutting joints, where needed, was scheduled for late in the day/evening on 12-02. 6. Lighthouse masonry are starting work at the Area C elevator shaft; the masonry at the lower tier of the auditorium at Area A is substantially complete (see photo). 7. Winter protection methods are in place by both silverback and Lighthouse. Tenting and temporary heat for the elevator shaft is in place. 8. Annese and Harold Brothers are continuing to install underground electrical work at both areas A and B. 9. Arden has stockpiled ductwork for the under-seat displacement ventilation at the auditorium, and will be installing that next week. REPORT BY: ABH Page 2 of 4 10. Site utility work: Eversource has been on site and “permanent temporary power” is on as of 12-01; water main installation is complete. 11. Site electrical work: Annese is setting light pole bases (see photo). 12. Lambrian has delivered curtain wall frames for the mockup. DISCREPANCIES, SPECIAL INSTRUCTIONS · EOS discrepancies at Area D. Sheathing placement on the north side of Area D highlights an “inboard” mis- location of the EOS at the north side “bump outs,” as Ryan Dirico had pointed out to PE earlier (see photo top of p. 4). The 8” framing channels are protruding over the EOS; Commodore’s plan is to make new pour stops and fill in a concrete sliver on 3 sides of the bump-outs in order to facilitate the AVB seal at the bottom of the wall. · (From 11-24 site report): sunshade outrigger discrepancies at Area D: PE had a further discussion on this subject with the Commodore Superintendent and the Colony Foreman, and assured Colony to ignore the outriggers and just frame the ROs as dimensioned. The issue is minor and the cladding will have to accommodate it, either by notching brick jamb surround or asymmetrically notching HPCP (see photo at bottom of p. 4). Attachments · structural field report from 12-01 (GAC) · plumbing field report from 11-30 (VAV) SITE PHOTOS ROOF INSTALLATION AT FUTURE RTU (AREA D) PARAPET FLASHING (AREA D) SHEATHING IN PROGRESS, NORTH FACADE (AREA D) 29 REPORT BY: ABH Page 3 of 4 SO. FAÇADE WINDOW BLOCKING (AREA D) WEST MP STAIR AND GUARD (AREA D) HVAC OVERHEAD ROUGH, LEVEL 2 (AREA D) BLOCKING R.O.s ON LEVEL 2 (AREA D) REPORT BY: ABH Page 4 of 4 BASE OF NORTH ‘BUMP OUT’ (AREA D) SLAB ON GRADE INSTALLATION (AREA B) NEWLY PLACED SLAB AT GYM AND ADAPTIVE PE (AREA B) UNDERGROUND DRAIN PIPE INSTALLATION (AREA A) SITE ELECTRICAL LIGHT POLE BASE INSTALLATION COMPANY LLP 10 Waterchase Rocky Hill, Office: Fax: Drive CT 06067 (860) 563-3820 (860) 563-3860 GIRARD AND STRUCTURAL ENGINEERS girardco.com Field Observation Report - 07 December 7, 2021 Attn: Daniel Colli, AIA Perkins Eastman Boston, MA 02110 Re: Site Visit – December 1, 2021 Dennis Yarmouth Intermediate Middle School Yarmouth, MA On Wednesday, December 1, 2021, our office visited the job site to observe the construction progress for the Dennis Yarmouth Intermediate Middle School. The Construction trades working this day included concrete, masonry, cold- form, plumbing, electrical, and site contractors. During the visit, I spoke with representatives from Commodore Builders and the owner’s project manager. Building earthwork continues with the installation of stone and backfilling of under slab utilities in areas A and B. Concrete installation for walls and footings is substantially complete. Elevated floor slabs in areas D, C, and B have been placed. The slab-on-grade in areas D and C are completed, and final preparation for placement of the slab on grade in area B is in progress. Winter protection methods are employed with blankets covering slabs and temporary enclosures around the masonry elevator. Steel erection is substantially complete. Miscellaneous steel is ongoing with the installation of stairs and railings. The repairs to the incorrectly fabricated steel beam at the area C East stair are completed. The cold-form metal framing in area D is in progress, and the exterior sheathing is being installed along the North wall. Masonry walls at the auditorium seating are installed, and work is progressing on the Area C elevator shaft. In general, the work observed appears in conformance with standard industry practice, and there were no apparent deficiencies noted. Respectfully, Girard and Company, LLP Kenneth P. Anderson, PE Field observations performed by Girard and Company, LLP are not detailed inspections and do not relieve the contractor from their obligations under the construction contract, including but not limited to the construction means and methods and job site safety. The purpose of the field observations is to verify that the progress of work is in general conformance with the contract documents. file: H:\2017\17-030 Dennis Yarmouth MS\Construction Control\OR\17030_OR007.docx Field Observation Report - 07 Dennis Yarmouth Intermediate Middle School Yarmouth, MA Page: 2 of 3 Girard and Company, LLP December 7, 2021 Photographs – 12/1/2021 Area B Gym Slab-on-Grade prep work Area A Cafeteria Area A – Masonry Walls under the auditorium seating Area B – Main Atrium space Field Observation Report - 07 Dennis Yarmouth Intermediate Middle School Yarmouth, MA Page: 3 of 3 Girard and Company, LLP December 7, 2021 Blankets for winter protection on site. Area C Second floor CFM stud framing storage Area D – East Stair Area D – North Wall VAV International, Inc.  400 W. Cummings Park, Suite 4700 - Woburn, Massachusetts 01801 Tel (781) 935-7228 Fax (781) 935-1822 www.vavint.com Filename: J:\2018 Jobs Folder\2017-046 (Mattacheese MS) Perkins Eastman\Documents\Site Visit Report #3 \Mattacheese Site Visit Report 2021-12-10.pdf 1 TO: Andrew Hazelton DATE: December 10, 2021 Perkins Eastman RE: Mattacheese MS, Site Visit Report PAGES: 3 BY: Frank Stramaglia SITE VISIT REPORT: A site visit was made on Monday - November 29th, 2021, to review current progress. While on site no deficiencies or code issues were observed. FIRE PROTECTION STATUS 1. No fire protection work completed other than sprinkler service. PLUMBING STATUS 1. 95% of all under slab work was complete. 2. Waste and vent risers started. 3. No roof drains or risers installed. 4. Water piping not started. Framing for roof drains. VAV International, Inc.  400 W. Cummings Park, Suite 4700 - Woburn, Massachusetts 01801 Tel (781) 935-7228 Fax (781) 935-1822 www.vavint.com Filename: J:\2018 Jobs Folder\2017-046 (Mattacheese MS) Perkins Eastman\Documents\Site Visit Report #3 \Mattacheese Site Visit Report 2021-12-10.pdf 2 Interceptor VAV International, Inc.  400 W. Cummings Park, Suite 4700 - Woburn, Massachusetts 01801 Tel (781) 935-7228 Fax (781) 935-1822 www.vavint.com Filename: J:\2018 Jobs Folder\2017-046 (Mattacheese MS) Perkins Eastman\Documents\Site Visit Report #3 \Mattacheese Site Visit Report 2021-12-10.pdf 3 Underslab storm piping