HomeMy WebLinkAboutJ5951 Dennis Yarmouth Middle School WE 2021-12-24Summary Report #30
December 27, 2021
Attn:
Job No: 5951
Job Name:Dennis Yarmouth Middle School
296 Station Ave
South Yarmouth, MA 02664
Application No.:
TESTING
INSPECTION
ENGINEERING
SW
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
December 20, 2021
Arsene Ntwali reported to Mitch Miller with PMA at the jobsite. Performed soils compaction testing. No Samples Taken. See attached.
Abdulwahab Abulgasem reported to Mitch Miller with PMA at the jobsite. Performed observation of earthwork activities. No Samples Taken. See
attached.
The work observed was, to the best of Arsene's, Abdulwahab's knowledge, in accordance with the approved plans, specifications and applicable
standards of workmanship.
December 21, 2021
Arsene Ntwali reported to Mitch Miller with PMA at the jobsite. Performed observation of earthwork activities. No Samples Taken. See attached.
Abdulwahab Abulgasem reported to Mitch Miller with PMA at the jobsite. Performed observation of earthwork activities. No Samples Taken. See
attached.
Blake Mullens reported to John with PMA at the jobsite. Performed light gauge metal framing inspection. See attached.
Exception: No.10 screw missing at the inside leg of track connections. Contractor to install inside leg No.10 screws with lift access. Pins at typical
parapet detail within this area not spaced out properly. Pins installed at random locations instead of 5 pins within top 2" and 4 pins within bottom
2".
Non-compliance conditions were brought to the attention of John with PMA. See attached Non-Compliance Report.
The work observed was, to the best of Arsene's, Abdulwahab's, Blake's knowledge, in accordance with the approved plans, specifications and
applicable standards of workmanship.
December 22, 2021
Abdulwahab Abulgasem reported to o Mitch Miller with PMA at the jobsite. Performed structural masonry inspection. Grout sample(s) obtained:
(4) per set, (1) set(s), (4) total. See attached.
TESTING
INSPECTION
ENGINEERING
EM
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Arsene Ntwali reported to Mitch Miller with PMA at the jobsite. Performed soils compaction testing. No Samples Taken. See attached.
Abdulwahab Abulgasem reported to Mitch Miller with PMA at the jobsite. Performed observation of earthwork activities. No Samples Taken. See
attached.
The work observed was, to the best of Abdulwahab's, Arsene's knowledge, in accordance with the approved plans, specifications and applicable
standards of workmanship.
December 23, 2021
Arsene Ntwali reported to Mitch Miller with PMA at the jobsite. Performed soils compaction testing. No Samples Taken. See attached.
Abdulwahab Abulgasem reported to Mitch Miller with PMA at the jobsite. Performed observation of earthwork activities. No Samples Taken. See
attached.
The work observed was, to the best of Arsene's, Abdulwahab's knowledge, in accordance with the approved plans, specifications and applicable
standards of workmanship.
Laboratory test results are enclosed if testing was done during the period covered by this report.
Limitations: These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as
acceptance or guarantee of the work. Even with diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the
code.
Reviewed by:
Enea Mushi
Project Manager
01-05-2022
Date
Technical Contact: Bruce Tie, Engineering Manager (btie@fenaghengineering.com)
Administrative Contact: Gina Salerno (gsalerno@fenaghengineering.com)
TESTING
INSPECTION
ENGINEERING
Soils Compaction
FET Project #: 5951
Project Name: Dennis Yarmouth Middle School TAA #: NA
Inspection Address: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Arsene Ntwali
December 20, 2021
Time In: 07:00 Time Out: 15:00
Weather: Sunny
Temperature: 55°F
Permit No. :
Plans Dated: 09/23/2021
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable
standards of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
Arsene Ntwali
Inspector
12-20-2021
Date Enea Mushi
Project Manager
12-30-2021
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Arsene Ntwali reported to Mitch Miller with PMA at the jobsite. Performed soils compaction testing. Equipment used was Plate
compactor , Excavator. No samples taken.
Density Std (DS):
2476
Moisture Std (MS):
474
Specified Compaction:
95%
Soils Report prepared by:
Fenagh Engineering
Source of Fill:
Native:
General Location of Fill:
Building B L1
Nuclear Gauge:
Humbolt HS-5001EZ 5200
calibration expiration date 02/2022
Soils Report Dated:
06-07-2021
Results Reported to:
Mitch Miller
Equipment Observed:
Compaction: Plate compactor
Excavation: Excavator
Description of material Reference CurveID Lab Log ID Max Dry Density(pcf)Optimum Moisture
Loose glacial 1 S774 115.8 10.0
Test#Test Location Probe
Depth (in)
Test
Elev. (ft)
Ref.
Curve
Used
Test Dry Density
(lbs/cu. ft.)
Test Moisture
(%)
Compaction
(95%)
(%)
Comments
1 N/a29 4 -1 1 111.2 6.3 96 Pass
2 N/a29 4 0 1 110.7 6.5 96 Pass
TESTING
INSPECTION
ENGINEERING
Soils Observation
FET Project #: 5951
Project Name: Dennis Yarmouth Middle School TAA #: N/a
Inspection Address: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Abdulwahab Abulgasem
Subcontractor: Robert B. Our Co
December 20, 2021
Time In: 07:00 Break: 12:00-12:30 Time Out: 15:00
Weather: Cloudy
Temperature: 39°F
Permit No. :
Plans Dated: N/A
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable
standards of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
Abdulwahab Abulgasem
Inspector
12-20-2021
Date Enea Mushi
Project Manager
12-22-2021
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Abdulwahab Abulgasem reported to Mitch Miller with PMA at the jobsite. Performed observation of earthwork activities. Assisted
Arsene with soil observation. No samples taken.
TESTING
INSPECTION
ENGINEERING
Soils Observation
FET Project #: 5951
Project Name: Dennis Yarmouth Middle School TAA #: NA
Inspection Address: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Arsene Ntwali
December 21, 2021
Time In: 07:00 Time Out: 15:00
Weather: Sunny
Temperature: 43°F
Permit No. :
Plans Dated: 09/23/2021
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable
standards of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
Arsene Ntwali
Inspector
12-21-2021
Date Enea Mushi
Project Manager
12-30-2021
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Arsene Ntwali reported to Mitch Miller with PMA at the jobsite. Performed observation of earthwork activities. No samples taken.
Additional Notes: Observed placement and compaction of stones in building B.
TESTING
INSPECTION
ENGINEERING
Soils Observation
FET Project #: 5951
Project Name: Dennis Yarmouth Middle School TAA #: N/a
Inspection Address: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Abdulwahab Abulgasem
Subcontractor: Robert B. Our Co
December 21, 2021
Time In: 07:00 Break: 12:00-12:30 Time Out: 15:00
Weather: Cloudy
Temperature: 42°F
Permit No. :
Plans Dated: N/A
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable
standards of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
Abdulwahab Abulgasem
Inspector
12-21-2021
Date Enea Mushi
Project Manager
12-22-2021
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Abdulwahab Abulgasem reported to Mitch Miller with PMA at the jobsite. Performed observation of earthwork activities. Assisted
Arsene with soil observation. No samples taken.
TESTING
INSPECTION
ENGINEERING
Project No: 5951
Project Name: Dennis Yarmouth Middle School
Project Location: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Blake Mullens
Inspection Type: Light Gauge Metal Framing
Pg. 1 of 2
December 21, 2021
Time In: 08:00 Time Out: 15:00
Weather: Partly Cloudy
Temperature: 35°F
Permit No. :
Plans Dated: 05/08/2021
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable
standards of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
Blake Mullens
Inspector
12-21-2021
Date Enea Mushi
Project Manager
12-30-2021
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Blake Mullens reported to John with PMA at the Jobsite. Performed visual inspection of Light Metal Gauge Framing LMGF at Parapet
locations at building A and B. No. 10 screw missing at inside leg of track connections. Contractor to install inside leg no 10 screws with
lift access. Pins at typical parapet detail within this area not spaced properly. Pins installed at random locations instead of 5 pins within
top 2" and 4 pins within bottom 2".
Performed visual inspection of LMGF at building Part C and Part D. Punch list generated and given to contractor for completion. Work
within this area still in progress.
Referenced Details: SK-1 - SK-7
Non-compliance conditions were brought to the attention of John with PMA
See attached Non-Compliance Report.
TESTING
INSPECTION
ENGINEERING
Project No: 5951
Project Name: Dennis Yarmouth Middle School
Project Location: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Blake Mullens
Inspection Type: Notice of Non-Compliance
Pg. 2 of 2
December 21, 2021
Time In: 08:00 Time Out: 15:00
Weather: Partly Cloudy
Temperature: 35°F
Permit No. :
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Person Notified at Jobsite:
Name:John Company:PMA
Inspection Type and Coverage:
Visual LMGF
The items as listed herein have not been accomplished in accordance with the approved documents, plans and specifications:
No. 10 screw missing at inside leg of track connections. Contractor to install inside leg no 10 screws with lift access. Pins at typical
parapet detail within this area not spaced properly. Pins installed at random locations instead of 5 pins within top 2" and 4 pins within
bottom 2".
Limitations: These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance
or guarantee of the work. Even with diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information
provided herein has not been reviewed by supervisory staff, therefore, should be considered preliminary and subject to change, unless signed by both inspector
and engineer below.
Reviewed by:
Blake Mullens (Inspector)
12-21-2021
Date
TESTING
INSPECTION
ENGINEERING
Project No: 5951
Project Name: Dennis Yarmouth Middle School
Project Location: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Abdulwahab Abulgasem
Inspection Type: Masonry CMU Block Placement
Pg. 1 of 1
December 22, 2021
Time In: 07:00 Break: 12:00-12:30 Time Out: 15:00
Weather: Cloudy
Temperature: 41°F
Permit No. :
Abdulwahab Abulgasem reported to o Mitch Miller with PMA at the jobsite. Observed placement of 8" units and rebar, #4" at 48"” O.C.
horizontal and #4" at 48"” O.C. vertical, constructed with space mix Type S mortar, 1-6 courses, wall(s) at Level 1, gridlines A.28-B.23/M.3-
K. Work in progress. Sampled grout, -day design strength of psi. Reference details Area B masonry drawing .
Set No.Slump (in.)Mix Temp (°F)Air Temp (°F)Location Qty. of Samples
1 n/a 55 42 A.28-B.23/M.3-K 4
1 set of Grout Box(s) for a total of 4 samples
Plans Dated: N/A
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable
standards of workmanship.
Limitations: These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or
guarantee of the work. Even with diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein
has not been reviewed by supervisory staff, therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
Abdulwahab Abulgasem
Inspector
12-22-2021
Date Enea Mushi
Project Manager
12-30-2021
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
TESTING
INSPECTION
ENGINEERING
Soils Compaction
FET Project #: 5951
Project Name: Dennis Yarmouth Middle School TAA #: NA
Inspection Address: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Arsene Ntwali
December 22, 2021
Time In: 07:00 Time Out: 15:00
Weather: Sunny
Temperature: 38°F
Permit No. :
Plans Dated: 09/23/2021
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable
standards of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
Arsene Ntwali
Inspector
12-22-2021
Date Enea Mushi
Project Manager
01-05-2022
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Arsene Ntwali reported to Mitch Miller with PMA at the jobsite. Performed soils compaction testing. Equipment used was Plate
compactor , Excavator. No samples taken.
Density Std (DS):
2510
Moisture Std (MS):
482
Specified Compaction:
95%
Soils Report prepared by:
Fenagh Engineering
Source of Fill:
Native:
General Location of Fill:
South of building B
Nuclear Gauge:
Humbolt HS-5001EZ 5200
calibration expiration date 02/2022
Soils Report Dated:
06-07-2021
Results Reported to:
Mitch Miller
Equipment Observed:
Compaction: Plate compactor
Excavation: Excavator
Description of material Reference CurveID Lab Log ID Max Dry Density(pcf)Optimum Moisture
Loose glacial 1 S774 115.8 10.0
Test#Test Location Probe
Depth (in)
Test
Elev. (ft)
Ref.
Curve
Used
Test Dry Density
(lbs/cu. ft.)
Test Moisture
(%)
Compaction
(95%)
(%)
Comments
1 Fiber optic line 6 -1 1 110.9 6.6 96 Pass
2 Fiber optic line 6 0 1 110.5 6.4 95 Pass
TESTING
INSPECTION
ENGINEERING
Soils Observation
FET Project #: 5951
Project Name: Dennis Yarmouth Middle School TAA #: N/a
Inspection Address: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Abdulwahab Abulgasem
Subcontractor: Robert B. Our Co
December 22, 2021
Time In: 07:00 Break: 12:00-12:30 Time Out: 15:00
Weather: Cloudy
Temperature: 34°F
Permit No. :
Plans Dated: N/A
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable
standards of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
Abdulwahab Abulgasem
Inspector
12-22-2021
Date Enea Mushi
Project Manager
12-30-2021
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Abdulwahab Abulgasem reported to Mitch Miller with PMA at the jobsite. Performed observation of earthwork activities. Assisted
Arsene with soil observation. No samples taken.
TESTING
INSPECTION
ENGINEERING
Soils Compaction
FET Project #: 5951
Project Name: Dennis Yarmouth Middle School TAA #: NA
Inspection Address: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Arsene Ntwali
December 23, 2021
Time In: 07:00 Time Out: 15:00
Weather: Sunny
Temperature: 43°F
Permit No. :
Plans Dated: 09/23/2021
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable
standards of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
Arsene Ntwali
Inspector
12-23-2021
Date Enea Mushi
Project Manager
01-05-2022
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Arsene Ntwali reported to Mitch Miller with PMA at the jobsite. Performed soils compaction testing. Equipment used was Plate
compactor , Excavator. No samples taken.
Density Std (DS):
2476
Moisture Std (MS):
474
Specified Compaction:
95%
Soils Report prepared by:
Fenagh Engineering
Source of Fill:
Native:
General Location of Fill:
Athletic field
Nuclear Gauge:
Humbolt HS-5001EZ 5200
calibration expiration date 02/2022
Soils Report Dated:
06-07-2021
Results Reported to:
Mitch Miller
Equipment Observed:
Compaction: Plate compactor
Excavation: Excavator
Description of material Reference CurveID Lab Log ID Max Dry Density(pcf)Optimum Moisture
Loose glacial 1 S774 115.8 10.0
Test#Test Location Probe
Depth (in)
Test
Elev. (ft)
Ref.
Curve
Used
Test Dry Density
(lbs/cu. ft.)
Test Moisture
(%)
Compaction
(95%)
(%)
Comments
1 Light pole 6 -2 1 111.5 6.1 96 Pass
2 Light pole 6 -1 1 110.2 6.0 95 Pass
TESTING
INSPECTION
ENGINEERING
Soils Observation
FET Project #: 5951
Project Name: Dennis Yarmouth Middle School TAA #: N/a
Inspection Address: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Abdulwahab Abulgasem
Subcontractor: Robert B. Our Co
December 23, 2021
Time In: 07:00 Break: 12:00-12:30 Time Out: 15:00
Weather: Sunny
Temperature: 38°F
Permit No. :
Plans Dated: N/A
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable
standards of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
Abdulwahab Abulgasem
Inspector
12-23-2021
Date Enea Mushi
Project Manager
12-30-2021
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Abdulwahab Abulgasem reported to Mitch Miller with PMA at the jobsite. Performed observation of earthwork activities. Assisted
Arsene with soil observation. No samples taken.
NCR ID# Date Location Inspector IssueRFI/ Submittal No.Resolved? (Y/N) Sub/ Contractor Date Resolved Comment1 7/21/2021 Wall : C /d3 Arsene NtwaliLow break: Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content from 4.5% to 7.5%N MargueriteEOR to Advise 7 day break 08/10/2021 Set 1 = 1,860 psi 28 day break 08/31/2021 Set 1 = 2,800 psi Set 1 = 2,900 psi Set 1 = 3,480 psi 28 day average = 3,060 psi 2 7/28/2021 Footing : C16/E Arsene NtwaliLow break: Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content from 4.5% to 7.5% : Lab Log No.: 15519 (2744‐2745)N MargueriteEOR to Advise 28 day break 08/31/2021 Set 1 = 3,350 psi Set 1 = 3,500 psi Set 1 = 3,620 psi 56 day break 09/22/2021 Set 1 = psi3 7/30/2021Footings Set # 1 :Column line/Row: D.3/c116 Set # 2 Columm line / Row c5/H Arsene NtwaliLow break: Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content from 4.5% to 7.5%N MargueriteEOR to Advise 28 day break 08/27/2021 Set 1 = 3,070 psi Set 1 = 3,330 psi Set 1 = 3,430 psi Set 2 = 3,330 psi Set 2 = 3,520 psi Set 2 = 3,580 psi 56 day break 09/24/2021 Set # 1 = 3,720 psi Set #2 = 3,670 psi4 8/3/2021Footings: Elevator pit foundationArsene NtwaliLow break: Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content from 4.5% to 7.5%N MargueriteEOR to Advise 7 day break 08/10/2021 Set 1 = 2,610 psi 28 day break 08/31/2021 Set 1 = 3,170 psi 56 day break 9/28/2021 Set 1 = 3,330 psi Set 1 = 3,490 psi Set 1 = 3,700 psi 56 day average set 1 = 3,510 psi5 8/6/2021 Level 1 Wall at Building C and B ‐ E/c2Arsene NtwaliLow break: Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content from 4.5% to 7.5%N MargueriteEOR to Advise 7 day break 08/13/2021 Set 1 = 2,980 psi 28 day break 09/3/2021 Set 1 = 3,170 psi 56 day break 10/8/2021 Set 1 = 3,230 psi Set 1 = 3,400 psi 6 8/6/2021Level 1 Wall at Building C and B ‐ J.7/b25Arsene NtwaliLow break: Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content from 4.5% to 7.5%N MargueriteEOR to Advise 7 day break 08/13/2021 Set 2= 2,390 psi 28 day break 09/3/2021 Set 2 = 3380 psi 56 day break 10/8/2021 Set 1 = psi7 8/13/2021Level 1 Footings at Building B: P.1/b33Arsene NtwaliLow break: Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content from 4.5% to 7.5%N MargueriteEOR to Advise 17 day break 08/30/2021 Set 1 = 3,090 psi 28 day break 09/10/2021 Set 1 = 3,460 psi Set 1 = 3,510 psi 56 day break 10/08/2021 Set 1 = psi Set 1 = psi8 8/13/2021Level 1 Footings at Building B: J.3/b24Arsene NtwaliLow break: Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content from 4.5% to 7.5%N MargueriteEOR to Advise 7 day break 08/20/2021 Set 1 = 2,320 psi 28 day break 09/10/2021 Set 1 = 2,840 psi 56 day break 10/08/2021 Set 1 = psi Set 1 = psi
9 8/20/2021Level 1 Footings at Foundation: Wall: H/c5Arsene NtwaliLow break: Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content from 4.5% to 7.5% : Lab Log No.: 15860 (3024)N MargueriteEOR to Advise 7 day break 08/27/2021 Set 1 = 2,810 psi 28 day break 09/17/2021 Set 1 = 3,440 psi Set 1 = 3,500 psi 56 day break 10/15/2021 Set 1 = 3,920 psi Set 1 = 4,020 psi10 9/3/2021 Level 1 Wall; U/a5 Arsene NtwaliLow break: Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content from 4.5% to 7.5% ; Lab Log No.: 16067 (3123)N MargueriteEOR to Advise 7 day break 09/10/2021 Set 1 = 2,050 psi 28 day break 10/01/2021 Set 1 = 3,100 psi 56 day break 10/29/2021 Set 1 = 3,510 psi Set 1 = 3,630 psi Set 1 = 3,660 psi11 9/9/2021 Level 1 Footing: M.5/b17 Arsene NtwaliLow break: Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content from 4.5% to 7.5% ; Lab Log No.: 16132 (3175)N MargueriteEOR to Advise 7 day break 09/16/2021 Set 1 = 2,400 psi 28 day break 10/07/2021 Set 1 = 3,480 psi Set 1 = 3,490 psi 56 day break 11/04/2021 Set 1 = 4,050 psi Set 1 = 4,240 psi12 9/10/2021 Level 1 Footing: L.9/b2 Arsene NtwaliLow break: Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content from 4.5% to 7.5% ; Lab Log No.: 16133 (3176)N MargueriteEOR to Advise 7 day break 09/17/2021 Set 1 = 2,330 psi 28 day break 10/08/2021 Set 1 = 3,450 psi Set 1 = 3,450 psi Set 1 = 3,490 psi 56 day break 11/05/2021 Set 1 = 4,060 psi 13 8/13/2021 Level 1 Footings at Building B: Set # 1 P.1/b33 Set # 2 J.3/b24Arsene NtwaliLow break: Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content from 4.5% to 7.5% ; Lab Log No.: 15745 (2945‐2946)N MargueriteEOR to Advise 7 day break 08/20/2021 Set 2 = 2,320 psi 28 day break 09/10/2021 Set 1 = 3,460 psi Set 1 = 3,510 psi Set 2 = 2,840 psi 56 day break 10/08/2021 Set 1 = 3,760 psi Set 1 = 3,850 psi Set 2 = 3,260 psi Set 2 = 3,030 psi Set 2 = 3,150 psi Set 2=3,260 psi14 8/17/2021 Level 1 Footings at Building B: S.1/b27Arsene NtwaliLow break: Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content from 4.5% to 7.5% ; Lab Log No.: 15745 (2945‐2946)N MargueriteEOR to Advise 7 day break 08/24/2021 Set 1 = 2,510 psi 28 day break 09/14/2021 Set 1 = 3,280 psi Set 1 = 3,430 psi 56 day break 10/12/2021 Set 1 = 4,070 psi Set 1 = 4,110 psi 15 9/23/2021 Level 1 Footings at Building B: P7/a18Arsene NtwaliLow break: Mix Desing 5000D, design strength of 5,000 psi at 28 days, specified slump from 5 to 8 in., specified air content from 4% to 7% ; Lab Log No.: 16288 (3264)N MargueriteEOR to Advise 7 day break 09/30/2021 Set 1 = 3,510 psi 28 day break 10/21/2021 Set 1 = 4,470 psi 56 day break 11/18/2021 Set 1 = 4,880 psi Set 1 = 5,120 psi Set 1 = 5,210 psi 16 11/2/2021 Level 1 Slab at Building D: Line A‐D1, Row D1‐before D16 Enea Mushi Measured Floor Flatness, Levelness (34.7 and 18.3) did not meet overall project requirement (35 and 25) N Marguerite EOR to Advise
17 9/27/2021 Level 1 Wall at Q‐P.7/a18, a18‐24/WD17 : Sampled @ N.4/b5Arsene NtwaliLow break: Mix Desing 5000D, design strength of 5,000 psi at 28 days, specified slump from 5 to 8 in., specified air content from 4% to 7% ; Lab Log No.: 16339 (3323)N MargueriteEOR to Advise 7 day break 10/04/2021 Set 1 = 3,510 psi 28 day break 10/25/2021 Set 1 = 4,170 psi 56 day break 11/22/2021 Set 1 = 4,700 psi 90 day break 12/26/2021 Set 1 = psi Set 1 = psi 18 12/16/2021Level 1, area A @ S.1‐S.5/b11 bottoms only: Level 16 @ K.9‐N/b33 steel girts: Level low roof/high roof @ N.9‐K/b1, K/b1‐b22,L+P.7/a17‐b21, LP.7/a17+b21, V‐V.9/a15, W/a1‐a14, W‐V/a1, V/a1‐a2, V‐U/a2Tony ParadisWPSs not available for review for Stellar Steel Erectors or United Steel. Stellar Steel Used FCAW process in the 2F, 4F, 2G and 3G possitions. United Steel used the SMAW process in the 2F possition. rnWPQRs recieved for Stellar Steel Erectors show no welders qualified for FCAW welds in the 4F or 3G positions.N PMA EOR to Advise 19 12/17/2021 top and bottom plates Tony ParadisContractor has failed to maintain 3/4" minimum distance from screw to edge of light gauge surfaces as called for in General Note 4 on SK‐3.N PMA EOR to Advise 20 12/18/2021 Level 1 Metal pan stairs at Building DTony ParadisLow Break : Mix #: 4000DGRNA : Slump 5‐9 air 0‐3 Design Strength (psi): 4,000 @28 days : Lab Log No.: 17282 (3681)N PMAEOR to Advise 7 day break 11/25/2021 Set 1 = 2,060 psi 28 day break 12/16/2021 Set 1 = 2,580 psi 56 day break 01/13/2021 Set 1 = psi 21 12/21/2021 locations at building A and B Blake MullensThe items as listed herein have not been accomplished in accordance with the approved documents, plans and specifications: No. 10 screw missing at inside leg of track connections. Contractor to install inside leg no 10 screws with lift access. Pins at typical parapet detail within this area not spaced properly. Pins installed at random locations instead of 5 pins within top 2" and 4 pins within bottom 2".N PMA EOR to Advise Status: Work‐in‐ProgressLegend:Status: ClosedStatus: Open
TESTING
INSPECTION
ENGINEERING
Field Number: 5 Laboratory Compression Test (4x8)
Project Name: Dennis Yarmouth Middle School Permit No.:
Project No.:5951 Sampled by: Arsene Ntwali Report Date: 12/23/2021
Client: PMA Consultants, LLC
Date of Sampling: 12/10/2021 Lab Log No.: 17375 (3800)
Reviewed by: CJ Martens
12/23/2021
Date
ASTM Standards Used: Unless noted, material was sampled and tested in accordance with ASTM C172, C31, C143, C231, C470, C511, C1077,
C1231,C1064, C138 and E4. Compressive strength tests per ASTM C39.
Testing was performed by qualifed personnel in accordance with generally accepted industry practice, material testing consultants procedures and the above reference standards. This report is
applicable only to the items listed herein. The test performed and in this report are not intended to be considered as any guarantee or warranty of suitability for service or fitness of use of itemstested and it should not be relied on as such. The report has been prepared for the exclusive use of the client and any partial or whole reproduction without the consent of the client is prohibited.Pg. 1 of 1
Information provided by Field Technician
Mix #: 3000DNA Supplier: Cape Cod Mix Contractor: Silverback
Set: 1 of 1 Truck #: 67
Design Strength (psi): 3,000 @28
days Ticket#: 32889
Sample Material/Shape: ASTM C39 Compressive Strength of Cylindrical
Concrete Specimens (4x8)Type of Structure: Slab on Metal Deck
Location: Onsite
Location for overall pour: Level 2 Slab on Metal Deck at Building A low roof
Location when sampled: T.8/a4
Concrete Quality Actual Req'ment Actual Req'ment Actual Req'ment
Mix Temperature (ºF): 63 50-90 Slump or Spread (in.): 6.75 5-9 Unit Wt (#cu ft): 149.2 148.2
Air Temperature (ºF): 45 >40 Air Content (%): 1.3 0-3 Time Sampled: 9:10 AM
Aggregate Size (in): 3/4 3/4 Batch Time: 8:36 AM Time in Truck: 34 minutes <90 Mins
Information supplied by Laboratory Technician
Date Received: 12/13/2021 Technician that received: MN
Test #
Age of
Test
(Days)
Date Technician Diameter Length Area (in²) Cure Loc
Ultimate Load
(lbs)
Compressive
Strength (psi)
Type of
Fracture
A 7 12/17/2021 Luis Soto Soldevilla 4.00 8.00 12.57 Fld 49,274 3,920 psi Type 2
B 28 01/07/2022 4.00 8.00 12.57 Fld
C 28 01/07/2022 4.00 8.00 12.57 Fld
D 28 01/07/2022 4.00 8.00 12.57 Fld
E H H 4.00 8.00 12.57 Fld
7 Day Avg.:3,920 psi
Remarks: Received Sample Condition: Acceptable and/or Satisfactory