Loading...
HomeMy WebLinkAboutDYIMS PE Site report 20220106 Architect: Perkins Eastman DPC Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File ARCHITECT’S SITE OBSERVATION REPORT DATE OF VISIT: 01/06/2022 PROJECT: Dennis Yarmouth Intermediate Middle School 286 Station Avenue South Yarmouth, MA 02664 DATE OF ISSUE: 01/19/2022 PROJECT NO: 71011 WEATHER CONDITIONS: Partly cloudy, COLD, low 30s ARCHITECT: Perkins Eastman, DPC 20 Ashburton Street 8th floor Boston, MA The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit. WORK IN PROGRESS: 1) CFMF and interior partition framing 2) CMU at gymnasium 3) Exterior sheathing and parapet insulation installation 4) Window installation and stripping in of windows 5) Fire protection installation 6) AVB installation and prep for window installation 7) Roofing at Area B, and Blocking/prep for roofing at A 8) Underground Electrical; electrical rough-in 9) Underground plumbing 10) HVAC and plumbing overhead rough-in 11) Site work: soil compaction and prep for site retaining walls at upper athletic field 12) GPI is on site for inspection of subgrade prep. (see attached GPI report) FIELD OBSERVATIONS: PE visited the site on Thursday 01 06, to review ongoing progress. 1. At the time of observation, Colony was about 75% with sheathing Area C and was focusing on Areas B and A ahead of Stanley’s roof installation. Rough carpentry for window RO’s in area C appears complete. Colony’s wall and parapet framing and sheathing at Areas B and A high roof appears to be nearly complete, including the stair B bulkhead. 2. Beacon Waterproofing’s AVB installation at Area D appears about 70% complete. 3. Interior partition framing is ongoing at the first and 2nd floors of Area C (see photo on page 3), as well as overhead rough-in for plumbing and HVAC. 4. Colony is installing drywall in isolated locations on the interior of D. Electrical closets etc. 5. Ongoing MEPs 1st and 2nd floor D wing. Arden will be finished with overhead in D this week according to Commodore. 6. Lambrian has commenced window installation in Area D and windows for Area C will be arriving on site next week. Beacon is stripping in the AVB for windows behind Lambrian. (see photo on page 4). 7. At the time of observation Lambrian appeared to have finished framing the CW for the mock up. 8. At the time of observation Stanley was installing the roof insulation and membrane at the last C wing “link,” and at the upper atrium roof in area B; blocking for the skylights is in place and parapets have been sheathed ahead of parapet flashing. 9. The curb for the roof expansion joint at the future gym fire wall has been framed and sheathed and is ready for Stanley (see photo on page 3). The stair bulkhead for stair B has been framed and fireproofed and is ready for stairs to be installed. 10. Lighthouse finished the CMU elevator shaft at area B earlier in the week (see photo) 40s REPORT BY: ABH Page 2 of 4 11. At the time of observation Lighthouse masonry had completed tenting the east and north walls of the gymnasium, heaters had been set up, and the masons were laying the first course of CMU at the east wall perimeter wall of the gymnasium (see photo). 12. Commodore and Silverback are prepping for the slab-on-grade pour at Area B, scheduled for January 18th. At the time of observation the underslab vapor barrier had been put down at Area B and the carpentry for the pour stop was about 90% complete. Steel mesh installation is just starting. 13. The pour for the concrete at the composite deck over the B wing elevator shaft, as well as the auditorium ‘lower bowl’ is scheduled to occur at the same time as the B wing slab on grade. 14. Annese is still continuing to install underground electrical work at area A. 15. RBO has caught up with Annese and Harold Bros., and so has shifted back to site work; RBO is prepping subgrade for retaining wall footings at lower field B, and GPI is back on site to monitor this work. DISCREPANCIES, SPECIAL INSTRUCTIONS 10601. Knee walls at stair curtain wall. PE asked Colony to move the small knee walls under the curtain wall at the academic wing stairs out by approximately 2” so that they will align with the inside-corner sheathing (i.e. the sheathing at the wing walls), in order for the curtain wall to sit squarely on the knee wall. This occurs at each of the two stairs in both C and D wings (see photo on page 4). 10602. Inside curve at auditorium east wall. Colony asked PE about the truncated arc at the inside corner (A wing to B wing) and whether this can be squared off. PE asked colony to follow Lymo shop drawings. 10603. Vertical control joint vs horizontal control joint misalignment (at links). After being asked about this issue, PE told Colony that lack of perfect alignment in plan is due to the sheathing location and is per contract documents. Wall CJ will hit the floor CJ cover—just not in the exact center. (this item is being closed) 21603. (From the 12-16 site report) OF scuppers. Harold Bros. has installed the originally-specified ‘lamb’s tounge’ scuppers at the overflow outlets high on the building, in spite of revised (B14) detail, which had called for changing to a square one. Update: still open 12401. (From 11-24 site report): Sunshade outrigger discrepancies: Update: It was observed that there are actually four four windows (or window pairs) where the steel is within the rough opening. PE asked Colony / CB to pad out the jambs until the steel is at least flush or slightly inside the edge of the R.O. This can be done with minimal impact to window locations (1/4 or 3/8” impact, worst case), and Lymo will have to make adjustments with the exact spacing of HPC panels. Attachments: · RKK field report -- 12-29-21 · RJK field report -- 01-06-22 SITE PHOTOS SHEATHING PROGRESS AT AREA C SOUTH WEST * GPI field report -- 01-06-22· REPORT BY: ABH Page 3 of 4 PARAPET FRAMING PROGRESS AND SHEATHING INSTALLATION AT UPPER AUDITORIUM (AREA A) COMPLETED ELEVATOR SHAFT WALL (AREA B) CURB AND ROOF DECK AT AREA B WEST OF GYM. INTERIOR FRAMING AT AREA C LEVEL 2 REPORT BY: ABH Page 4 of 4 WINDOW INSTALLED AT AREA D LEVEL 2 WINDOW INSTALLATION AT AREA D NORTH 2ND COURSE OF BLOCK AT GYMNASIUM EAST WALL KNEE WALL AT EAST STAIR (AREA C) FIELD REPORT All issues were discussed with PMA, CB and SRC prior to leaving the site. Work Observed/Procedure • Under-Slab Vapor Retarder Installation • Air and Vapor Barrier Membrane (AVB) Installation • Roofing Installation- Area Designated as Part C Observations • Stego Wrap Vapor Retarder is being installed at Part B with a minimum 6-inch laps, as required. Laps were taped utilizing Stego Tape, as required. (Figures 1 - 2) • Under-slab penetrations are detailed utilizing Stego Tape, as required. (Figure 3) • At Part D, north elevation, Gridlines D1-D15, GCP Perm-A-Barrier Aluminum AVB was installed by Beacon Waterproofing and Restoration Inc (Beacon) prior to RJK’s observations. Primer/adhesive was applied to the DensGlass Sheathing. The membrane was installed in a water shedding fashion, with a minimum 2-inch side lap and 10-inch lap around outside corners. (Figures 9 - 10) • At window rough openings, metal angle was installed at the sills fastened utilizing screws. The metal was then stripped in with a piece of AVB lapping from the rough opening sill onto the metal angles horizontal and vertical legs. The strip of membrane was sealed with sealant along three edges. (Figures 11 - 13) • Sika Sarnafil Sarnatherm CG polyisocyanurate insulation was installed loose laid over the vapor retarder in two layers with offsets between rows and layers, as required. (Figure 14) • Sika Sarnafil Sarnatherm High Density coverboard was installed over insulation with a field fastening pattern of 16-plates and fasteners per 4-foot by 8-foot board and a perimeter fastening pattern of 24- plates and fasteners per 4-foot by 8-foot board and corner fastening pattern, as required in the Sika assembly letter. (Figures 15 - 16) Project: Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School Report Number: FR-3 Property Address: 276 Station Avenue, South Yarmouth, MA 02664 Client: Perkins Eastman Date of Site Visit: December 27, 2021 Report Date: December 28, 2021 Weather: Mostly Cloudy 41 °F Purpose of Visit: Observe Building Enclosure Construction On-Site During Visit: Michael Groome - R. J. Kenney Associates, Inc. (RJK) Walter Hartley - PMA Consultants (PMA) Ryan DiRico - Commodore Builders (CB) Juan - Stanley Roofing Company, Inc (SRC) Report By: Michael Groome Report Attachments: Detailed Photographs Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School FR-3 Field Report R. J. Kenney Associates, Inc. Page 2 of 2 • Sika Sarnacol-2170 VC Adhesive was roller applied to the coverboard and allowed to flash off prior to adhesion of the membrane, as required. • The Sika Sarnafil G 410-80 EnergySmart PVC Roof Membrane was cut to size and allowed time to relax prior to adhesion. Sika Sarnacol-2170 VC Adhesive was roller applied to the back of the membrane and immediately the membrane was rolled onto the coverboard and rolled in utilizing a 100-pound roller, per the manufacturer’s requirements. (Figure 17) • A test weld was taken utilizing the walk welder and scrap membrane. The first test resulted in a failure; a second was taken and resulted in a scrim tearing bond. (Figures 18 - 20) • PVC membrane seams were welded utilizing the walk welder. (Figure 21) Discussions Below-Slab Vapor Barrier Installation 3.1 Voids/Fish Mouth in Laps - Part B- Folds in the membrane near laps has created fish mouths and voids in the vapor retarder under the tape. The areas should be cleaned, dried, and new tape applied. (Figure 8) 3.2 Voids in Penetration Detailing - Part B - Voids in the applied tape must be filled with new tape or Stego Mastic as required. (Figures 4 - 5) 3.3 Tape Unadhered to Column Footing - Part B - Stego Tape does not adhere to concrete. Detail column footings into the vapor retarder utilizing Stego Mastic or other manufacturer approved product (Figures 6 - 7) Roofing Installation 3.4 Wet Polyisocyanurate Insulation and Coverboard Installed - Part C - Insulation and coverboard has become wet in storage and SRC is installing the insulation and coverboard into the roofing system prior to allowing the insulation to fully dry and checking for delamination. Multiple moisture tests were performed to confirm elevated moisture content of the glass facers, as well as to show standing moisture on the insulation and coverboard. A Delmhorst BD-2100 Moisture Meter was utilized to check the moisture content resulting in readings up to “97.8” on the reference scale (0-100 range). Insulation set in the first layer exposed at the edge of the area of work was found to be wet hours of being left out. Juan (SRC) explained they were waiting to glue membrane until the coverboard dried, although the weather did not promote drying. (Figures 22 - 30) 3.5 Incomplete Night Tie-In - Part C - The northeast corner of the night tie-in was left open, exposing the polyisocyanurate insulation and coverboard. Moisture readings of the facers, utilizing a Delmhorst BD-2100 Moisture Meter, showed readings up to “33.9” showing some moisture gain, likely from humidity. The night tie-in should be made watertight to prevent moisture from entering the roofing system in case of rain, snow, or heavy fog. (Figures 33-35) End of Report G:\RJK\WORD\31258 Q504 Mattacheese DYIMS Yarmouth FR3 Rpt 12-28-21.docx RJK has no contractual responsibility in the design or actual construction of the project and is acting solely in a consultant and/or in an advisory capacity to the Client. Any and all modifications, changes, recommendations, suggestions, etc., relating to the design and/or construction, should be forwarded, reviewed, and approved by the designer of record prior to implementation. RJK reserves the right to change or amend this report as new information becomes available. Q504 - Mattacheese, DYIMS FR-3 Author: MPG Report Date:12-28-21 Detailed Photographs G:\RJK\WORD\31258 Q504 Mattacheese DYIMS Yarmouth FR3 DP 12-27-21.docx Page 1 of 18 Figure 1 Callouts: Comments: 1227001 R. J. Kenney Associates, Inc Title: Vapor Retarder Overview at Part B Figure 2 Callouts: Comments: Stego Wrap was installed with 6-inch laps and taped utilizing Stego Tape at laps and penetration. 1227004 R. J. Kenney Associates, Inc. Title: Vapor Retarder Laps Q504 - Mattacheese, DYIMS FR-3 Author: MPG Report Date:12-28-21 Detailed Photographs G:\RJK\WORD\31258 Q504 Mattacheese DYIMS Yarmouth FR3 DP 12-27-21.docx Page 2 of 18 Figure 3 Callouts: 1. Stego Tape 2. Stego Wrap Comments: 1227007 R. J. Kenney Associates, Inc. Title: Penetration Detailing Figure 4 Callouts: 1. Voids in detailing below Comments: 1227012 R. J. Kenney Associates, Inc. Title: Voids in Penetration Detailing 1 2 1 1 Q504 - Mattacheese, DYIMS FR-3 Author: MPG Report Date:12-28-21 Detailed Photographs G:\RJK\WORD\31258 Q504 Mattacheese DYIMS Yarmouth FR3 DP 12-27-21.docx Page 3 of 18 Figure 5 Callouts: 1. Penetration as shown in Figure 4 Comments: Voids in the applied tape are to be filled with new tape or Stego Mastic, as required. 1227014 R. J. Kenney Associates, Inc. Title: Voids in Penetration Detailing Figure 6 Callouts: 1. Unadhered tape Comments: Stego Tape does not adhere to concrete. 1227008 R. J. Kenney Associates, Inc. Title: Tape Unadhered to Column Footing 1 1 Q504 - Mattacheese, DYIMS FR-3 Author: MPG Report Date:12-28-21 Detailed Photographs G:\RJK\WORD\31258 Q504 Mattacheese DYIMS Yarmouth FR3 DP 12-27-21.docx Page 4 of 18 Figure 7 Callouts: 1. Unadhered Tape Comments: 1227009 R. J. Kenney Associates, Inc. Title: Tape Unadhered to Column Footing Figure 8 Callouts: 1. Voids in the lap Comments: 1227033 R. J. Kenney Associates, Inc. Title: Voids/Fish Mouth in Laps 1 1 1 1 1 Q504 - Mattacheese, DYIMS FR-3 Author: MPG Report Date:12-28-21 Detailed Photographs G:\RJK\WORD\31258 Q504 Mattacheese DYIMS Yarmouth FR3 DP 12-27-21.docx Page 5 of 18 Figure 9 Callouts: Comments: 1227187 R. J. Kenney Associates, Inc. Title: Part B North Elevation Figure 10 Callouts: Comments: GCP Perm-A-Barrier Aluminum AVB was installed by Beacon Waterproofing and Restoration Inc (Beacon) prior to RJK’s observations. Primer/adhesive was applied to the DensGlass Sheathing. The membrane was installed in a water shedding fashion, with a minimum 2-inch side lap and 10-inch lap around outside corners. 1227204 R. J. Kenney Associates, Inc. Title: AVB Laps Q504 - Mattacheese, DYIMS FR-3 Author: MPG Report Date:12-28-21 Detailed Photographs G:\RJK\WORD\31258 Q504 Mattacheese DYIMS Yarmouth FR3 DP 12-27-21.docx Page 6 of 18 Figure 11 Callouts: 1. Comments: The AVB extends up the metal angle. 1227189 R. J. Kenney Associates, Inc. Title: Metal Angle at Sills with AVB Strip and Sealant Figure 12 Callouts: 1. Metal Angle Comments: 1227190 R. J. Kenney Associates, Inc. Title: Metal Angle at Sills 1 Q504 - Mattacheese, DYIMS FR-3 Author: MPG Report Date:12-28-21 Detailed Photographs G:\RJK\WORD\31258 Q504 Mattacheese DYIMS Yarmouth FR3 DP 12-27-21.docx Page 7 of 18 Figure 13 Callouts: Comments: 1227094 R. J. Kenney Associates, Inc. Title: Sealant at Rough Opening membrane Figure 14 Callouts: Comments: 1227035 R. J. Kenney Associates, Inc. Title: Part C Roof Q504 - Mattacheese, DYIMS FR-3 Author: MPG Report Date:12-28-21 Detailed Photographs G:\RJK\WORD\31258 Q504 Mattacheese DYIMS Yarmouth FR3 DP 12-27-21.docx Page 8 of 18 Figure 15 Callouts: Comments: 1227086 R. J. Kenney Associates, Inc. Title: Field Fastening Patter Figure 16 Callouts: Comments: 1227089 R. J. Kenney Associates, Inc. Title: Perimeter Fastening Pattern Q504 - Mattacheese, DYIMS FR-3 Author: MPG Report Date:12-28-21 Detailed Photographs G:\RJK\WORD\31258 Q504 Mattacheese DYIMS Yarmouth FR3 DP 12-27-21.docx Page 9 of 18 Figure 17 Callouts: Comments: 1227084 R. J. Kenney Associates, Inc. Title: Membrane Adhesion Figure 18 Callouts: Comments: 1227164 R. J. Kenney Associates, Inc. Title: Test Weld with Walk Welder Q504 - Mattacheese, DYIMS FR-3 Author: MPG Report Date:12-28-21 Detailed Photographs G:\RJK\WORD\31258 Q504 Mattacheese DYIMS Yarmouth FR3 DP 12-27-21.docx Page 10 of 18 Figure 19 Callouts: Comments: 1227167 R. J. Kenney Associates, Inc. Title: Failed Test Weld #1 Figure 20 Callouts: Comments: 1227169 R. J. Kenney Associates, Inc. Title: Passing Test Weld #2 Q504 - Mattacheese, DYIMS FR-3 Author: MPG Report Date:12-28-21 Detailed Photographs G:\RJK\WORD\31258 Q504 Mattacheese DYIMS Yarmouth FR3 DP 12-27-21.docx Page 11 of 18 Figure 21 Callouts: Comments: 1227171 R. J. Kenney Associates, Inc. Title: Walk Welder Figure 22 Callouts: Comments: 1227060 R. J. Kenney Associates, Inc. Title: Wetted Materials Installed in System Q504 - Mattacheese, DYIMS FR-3 Author: MPG Report Date:12-28-21 Detailed Photographs G:\RJK\WORD\31258 Q504 Mattacheese DYIMS Yarmouth FR3 DP 12-27-21.docx Page 12 of 18 Figure 23 Callouts: 1. “75.1” on Reference Scale Comments: Insulation set in the first layer, exposed at the edge of the area of work, was found wetted even after hours of being left out. 1227114 R. J. Kenney Associates, Inc. Title: First layer of Insulation Figure 24 Callouts: 1. “89.3” on the Reference Scale Comments: Note that the display has one bar missing. 1227077 R. J. Kenney Associates, Inc. Title: Elevated Moisture Reading 1 1 Q504 - Mattacheese, DYIMS FR-3 Author: MPG Report Date:12-28-21 Detailed Photographs G:\RJK\WORD\31258 Q504 Mattacheese DYIMS Yarmouth FR3 DP 12-27-21.docx Page 13 of 18 Figure 25 Callouts: 1. “97.8” on the Reference Scale Comments: Note that the Delmhorst BD- 2100 Moisture Meter has one bar missing on the display. Knowing the apparent “3” from a “9” is looking at the colored light below. Standard settings on the moisture meter will shine the red light when numbers read “95” and up. 1227104 R. J. Kenney Associates, Inc. Title: Elevated Moisture Readings Figure 26 Callouts: Comments: Stored insulation is wet. 1227090 R. J. Kenney Associates, Inc. Title: Wetted Stored Insulation Q504 - Mattacheese, DYIMS FR-3 Author: MPG Report Date:12-28-21 Detailed Photographs G:\RJK\WORD\31258 Q504 Mattacheese DYIMS Yarmouth FR3 DP 12-27-21.docx Page 14 of 18 Figure 27 Callouts: 1. Moisture Finding Paper (Dry) Comments: 1227092 R. J. Kenney Associates, Inc. Title: Dry/Unused Moisture Finding Paper Figure 28 Callouts: 1. Moisture Finding Paper (Wet) Comments: The moisture finding paper turns color when exposed to moisture. 1227094 R. J. Kenney Associates, Inc. Title: Wetted Moisture Finding Paper 1 1 Q504 - Mattacheese, DYIMS FR-3 Author: MPG Report Date:12-28-21 Detailed Photographs G:\RJK\WORD\31258 Q504 Mattacheese DYIMS Yarmouth FR3 DP 12-27-21.docx Page 15 of 18 Figure 29 Callouts: 1. Standing Water Comments: Stored coverboard is wet. 1227137 R. J. Kenney Associates, Inc. Title: Standing Water on Packaged Coverboard Figure 30 Callouts: 1. Standing Water Comments: Moisture beaded and ran along the coverboard when lifted. 1227139 R. J. Kenney Associates, Inc. Title: Standing Water on Packaged Coverboard 1 1 Q504 - Mattacheese, DYIMS FR-3 Author: MPG Report Date:12-28-21 Detailed Photographs G:\RJK\WORD\31258 Q504 Mattacheese DYIMS Yarmouth FR3 DP 12-27-21.docx Page 16 of 18 Figure 31 Callouts: Comments: A torch was utilized to dry in the coverboard and insulation with no success. 1227153 R. J. Kenney Associates, Inc. Title: Torch Drying Attempt Figure 32 Callouts: Comments: A gas leaf blower was utilized to dry the coverboard and insulation with no success. 1227155 R. J. Kenney Associates, Inc. Title: Gas Leaf Blower Drying Attempt Q504 - Mattacheese, DYIMS FR-3 Author: MPG Report Date:12-28-21 Detailed Photographs G:\RJK\WORD\31258 Q504 Mattacheese DYIMS Yarmouth FR3 DP 12-27-21.docx Page 17 of 18 Figure 33 Callouts: 1. Incomplete Area Comments: 1227037 R. J. Kenney Associates, Inc. Title: Incomplete Night Tie-In Figure 34 Callouts: Comments: 1227038 R. J. Kenney Associates, Inc. Title: Incomplete Night Tie-In 1 Q504 - Mattacheese, DYIMS FR-3 Author: MPG Report Date:12-28-21 Detailed Photographs G:\RJK\WORD\31258 Q504 Mattacheese DYIMS Yarmouth FR3 DP 12-27-21.docx Page 18 of 18 Figure 35 Callouts: Comments: 1227040 R. J. Kenney Associates, Inc. Title: Moisture Readings at Incomplete Night Tie-In FIELD REPORT RJK discussed the issues with PE, PMA, CB and SRC prior to leaving the site. Work Observed/Procedure • Under-Slab Vapor Retarder Installation at Area Designated as Part B • Air and Vapor Barrier Membrane (AVB) Installation • Window Installation - Area Designated as Part D • Roofing Installation - Areas Designated as Part C and Part B (Figures 14, 15) Observations • Stego Wrap Vapor Retarder is being installed on prepared grade with a minimum 6-inch lap, as required. Laps were taped utilizing Stego Tape, as required. (Figure 1) • Under-slab penetrations are detailed utilizing Stego Tape, as required. (Figure 2) • Stego Mastic was applied to the concrete footing and metal column and the Stego Wrap lapped into the mastic. Stego tape was utilized at multiple locations around the perimeter of the column, although it is only needed at the seams in this detail. (Figure 3) • At Part C, south elevation, GCP Perm-A-Barrier Aluminum AVB was installed by Beacon Waterproofing and Restoration Inc. (Beacon) prior to RJK’s observations. Primer/adhesive was applied to the DensGlass Sheathing. The membrane was installed in a water shedding fashion, with a minimum 2-inch side lap and 10-inch lap around outside corners. (Figure 4) • At window rough openings, a strip of AVB was installed extending past the jamb and onto the exterior sheathing. The horizontal field sheets were run into the jambs in water shedding fashion. A head strip was then installed lapping over the jamb strips, as required. (Figure 5) Project: Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School Report Number: FR-4 Property Address: 276 Station Avenue, South Yarmouth, MA 02664 Client: Perkins Eastman Date of Site Visit: January 6, 2022 Report Date: January 10, 2022 Weather: Partly Cloudy, 45 °F Purpose of Visit: Observe Building Enclosure Construction On-Site During Visit: Michael Groome - R. J. Kenney Associates, Inc. (RJK) Andrew Hazelton - Perkins Eastman (PE) Jon Pope - PMA Consultants (PMA) Nick - PMA Paul Genereux - Commodore Builders (CB) Juan - Stanley Roofing Company, Inc. (SRC) Report By: Michael Groome Report Attachments: Detailed Photographs Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School FR-4 Field Report R. J. Kenney Associates, Inc. Page 2 of 3 • Various shims are set on rough opening sills set in sealant prior to installation of window frames. (Figure 6) • Windows are fastened utilizing screws through the interior fin of the window frame. (Figure 7) • Voids in coverage of the roofing vapor barrier are patched utilizing new patches of the vapor barrier membrane, as required by the manufacturer. (Figure 10) • Sika Sarnafil Sarnatherm CG polyisocyanurate insulation was installed loose laid over the vapor retarder, in two layers, with offsets between rows and layers, as required. (Figure 11) • Gaps in the insulation exceeding the maximum 1/4-inch requirement are filled utilizing new polyisocyanurate insulation. (Figures 12, 13) • Sika Sarnafil Sarnatherm High Density cover board was installed over insulation at Part C, with a field fastening pattern of 16-plates and fasteners per 4-foot by 8-foot board, a perimeter fastening pattern of 24 plates and fasteners per 4-foot by 8-foot board, and corner fastening pattern, as required in the Sika assembly letter. (Figure 14) • Georgia-Pacific DensDeck Prime coverboard and USG Securock was installed over insulation at Part B, with a field fastening pattern of 16-plates and fasteners per 4-foot by 8-foot board, a perimeter fastening pattern of 24 plates and fasteners per 4-foot by 8-foot board, and corner fastening pattern, as required in the Sika assembly letter. (Figures 15, 16) • Prefabricated outside corners are heat welded at outside corner transitions of the thermoplastic polyolefin membrane baseflashing. (Figure 17) Discussions Below-Slab Vapor Barrier Installation 4.1 Unadhered/Missing Stego Tape - Part B - Tape was not fully adhered and some laps were missing tape. (Figure 18) Window Installation 4.2 Knife Plates in Rough Opening - Parts D & C - Knife plates run into the rough openings, impeding installation of the window and interior sealant joints. (Figures 19 - 21) 4.3 Interior Air Barrier Seal at Windows - Part D - Shims utilized to offset the window from the rough opening are set close to the interior face of the window frame, creating a gap inadequate for proper backer rod and sealant joint detailing. If the shims cannot be moved deeper into the frame, as to not interfere with the backer rod and sealant, then backer rod should be cut between shims and bond breaker tape applied to shims prior to application of sealant which is to be dry tooled only. (Figure 22) 4.4 Window Fastening - Part D - Screws fastened through the interior fin penetrate the AVB without sealant. Although the membrane passes ASTM D 1970, it is recommended as best practice to add sealant at the screw location for wet setting each screw, specifically at the sill. (Figure 23) Roofing Installation 4.5 Wet Polyisocyanurate Insulation and Cover Board Is Installed - Part C & Part B - Insulation and cover board has become wet in storage. Multiple boards were set aside that were wetted, although multiple boards are observed installed with staining. Due to the multiple areas with questionable moisture levels, testing at the end of installation of the roofing system is recommended to check for unacceptable levels of moisture within the system. (Figures 24, 25) Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School FR-4 Field Report R. J. Kenney Associates, Inc. Page 3 of 3 4.6 Pitch Pocket Detail - Part C - A Sarnastack prefabricated pipe flashing is utilized as the pitch pocket to contain the Sarnafiller pourable sealant. Sarnafil details show Sika Sarnafil Sarnaclad PVC-coated sheet metal pitch pockets, a minimum of 2-inches from the penetrations, as the only way to detail this condition. The condition should be reviewed with the manufacturer for approval, or the detail must be installed per the manufacturer’s published details. (Figures 26, 27) 4.7 Uncut Clamping Rings - Part C - Multiple clamping rings installed at pipe penetrations were left uncut. This condition can allow the long metal ring to strike the membrane in windy conditions. (Figure 28) 4.8 No Clamping Ring - Part C - A penetration did not have a clamping ring installed. Since the sealant has dried, new sealant must be applied prior to installation of a clamping ring. (Figure 29) End of Report G:\RJK\WORD\31272 Q504 Mattacheese DYIMS Yarmouth FR4 Rpt 1-6-22.docx RJK has no contractual responsibility in the design or actual construction of the project and is acting solely in a consultant and/or in an advisory capacity to the Client. Any and all modifications, changes, recommendations, suggestions, etc., relating to the design and/or construction, should be forwarded, reviewed, and approved by the designer of record prior to implementation. RJK reserves the right to change or amend this report as new information becomes available. Q504 - Mattacheese DYIMS FR-4 Author: MPG Report Date: 01-10-2022 Detailed Photographs G:\RJK\WORD\31272 Q504 Mattacheese DYIMS Yarmouth FR4 DP 1-6-22.docx Page 1 of 15 Figure 1 Callouts: Comments: Stego Wrap Below-Slab Vapor Barrier was being installed on prepared grade with a minimum 6-inch laps, as required. Laps were taped utilizing Stego Tape, as required. 0106024 R. J. Kenney Associates, Inc Title: Below-Slab Vapor Barrier Laps Figure 2 Callouts: Comments: Under-slab penetrations are detailed utilizing Stego Tape, as required. 0106014 R. J. Kenney Associates, Inc. Title: Below-Slab Vapor Barrier Penetrations Q504 - Mattacheese DYIMS FR-4 Author: MPG Report Date: 01-10-2022 Detailed Photographs G:\RJK\WORD\31272 Q504 Mattacheese DYIMS Yarmouth FR4 DP 1-6-22.docx Page 2 of 15 Figure 3 Callouts: 1. Column 2. Black marks depict Stego Mastic below Stego Wrap Comments: Stego Mastic was applied to the concrete footing and metal column and the Stego Wrap lapped into the mastic. Stego tape was utilized at multiple locations around the perimeter of the column, although it is only needed at the seams in this detail. 0106031 R. J. Kenney Associates, Inc. Title: Below-Slab Vapor Barrier at Column Footings Figure 4 Callouts: 1. Primer Comments: GCP Perm-A-Barrier Aluminum AVB was installed by Beacon prior to RJK’s observations. Primer/adhesive was applied to the DensGlass Sheathing. The membrane was installed in a water shedding fashion, with a minimum 2-inch side lap and 10- inch lap around outside corners. 0106132 R. J. Kenney Associates, Inc. Title: Perm-A-Barrier Primer and Laps 1 2 1 Q504 - Mattacheese DYIMS FR-4 Author: MPG Report Date: 01-10-2022 Detailed Photographs G:\RJK\WORD\31272 Q504 Mattacheese DYIMS Yarmouth FR4 DP 1-6-22.docx Page 3 of 15 Figure 5 Callouts: Comments: At window rough openings, a strip of AVB was installed extending past the jamb and onto the exterior sheathing. The horizontal field sheets were run into the jambs in water shedding fashion. A head strip was then installed lapping over the jamb strips, as required. 0106126 R. J. Kenney Associates, Inc. Title: Rough Opening AVB Figure 6 Callouts: 1. Back Angle 2. Shims Comments: Various shims are set on rough opening sills set in sealant prior to installation of window frames. 0106143 R. J. Kenney Associates, Inc. Title: Back Angle and Shims 1 2 Q504 - Mattacheese DYIMS FR-4 Author: MPG Report Date: 01-10-2022 Detailed Photographs G:\RJK\WORD\31272 Q504 Mattacheese DYIMS Yarmouth FR4 DP 1-6-22.docx Page 4 of 15 Figure 7 Callouts: Comments: Windows are fastened utilizing screws through the interior flange of the window frame. 0106149 R. J. Kenney Associates, Inc. Title: Window Frame Fastening at Jamb Figure 8 Callouts: Comments: 0106049 R. J. Kenney Associates, Inc. Title: Area of Roof Work at Building A Q504 - Mattacheese DYIMS FR-4 Author: MPG Report Date: 01-10-2022 Detailed Photographs G:\RJK\WORD\31272 Q504 Mattacheese DYIMS Yarmouth FR4 DP 1-6-22.docx Page 5 of 15 Figure 9 Callouts: Comments: 0106092 R. J. Kenney Associates, Inc. Title: Area of Roof Work at Building C Figure 10 Callouts: Comments: Voids in coverage of the roofing vapor barrier are patched utilizing new patches of the vapor barrier. 0106079 R. J. Kenney Associates, Inc. Title: Roofing Vapor Barrier Patches Q504 - Mattacheese DYIMS FR-4 Author: MPG Report Date: 01-10-2022 Detailed Photographs G:\RJK\WORD\31272 Q504 Mattacheese DYIMS Yarmouth FR4 DP 1-6-22.docx Page 6 of 15 Figure 11 Callouts: Comments: Sika Sarnafil Sarnatherm CG polyisocyanurate insulation was installed loose laid over the vapor retarder, in two layers, with offsets between rows and layers, as required. 0106052 R. J. Kenney Associates, Inc. Title: Polyisocyanurate Insulation Installation Figure 12 Callouts: Comments: 0106082 R. J. Kenney Associates, Inc. Title: Gaps in Insulation Q504 - Mattacheese DYIMS FR-4 Author: MPG Report Date: 01-10-2022 Detailed Photographs G:\RJK\WORD\31272 Q504 Mattacheese DYIMS Yarmouth FR4 DP 1-6-22.docx Page 7 of 15 Figure 13 Callouts: Comments: Gaps in the insulation exceeding the maximum 1/4-inch requirement are filled utilizing new polyisocyanurate insulation. 0106085 R. J. Kenney Associates, Inc. Title: Large Gaps Filled in Polyisocyanurate Insulation Figure 14 Callouts: Comments: Sika Sarnafil Sarnatherm High Density cover board was installed over insulation with a field fastening pattern of 16- plates and fasteners per 4-foot by 8-foot board, a perimeter fastening pattern of 24 plates and fasteners per 4-foot by 8- foot board, and corner fastening pattern, as required in the Sika assembly letter. 0106099 R. J. Kenney Associates, Inc. Title: Cover Board at Building C Q504 - Mattacheese DYIMS FR-4 Author: MPG Report Date: 01-10-2022 Detailed Photographs G:\RJK\WORD\31272 Q504 Mattacheese DYIMS Yarmouth FR4 DP 1-6-22.docx Page 8 of 15 Figure 15 Callouts: Comments: Georgia-Pacific DensDeck Prime cover board was installed over insulation with a field fastening pattern of 16-plates and fasteners per 4-foot by 8- foot board, a perimeter fastening pattern of 24 plates and fasteners per 4-foot by 8-foot board, and corner fastening pattern, as required in the Sika assembly letter. 0106087 R. J. Kenney Associates, Inc. Title: Cover Board at Building B Figure 16 Callouts: Comments: 0106056 R. J. Kenney Associates, Inc. Title: Cover Board at Building B Q504 - Mattacheese DYIMS FR-4 Author: MPG Report Date: 01-10-2022 Detailed Photographs G:\RJK\WORD\31272 Q504 Mattacheese DYIMS Yarmouth FR4 DP 1-6-22.docx Page 9 of 15 Figure 17 Callouts: Comments: Prefabricated outside corners are heat welded at outside corner transitions of the thermoplastic polyolefin membrane baseflashing. 0106114 R. J. Kenney Associates, Inc. Title: Outside Corner Detail Figure 18 Callouts: 1. Missing Tape 2. Unadhered tape Comments: Tape was not fully adhered, and some laps were missing tape. 0106003 R. J. Kenney Associates, Inc. Title: Unadhered Stego Tape 1 2 Q504 - Mattacheese DYIMS FR-4 Author: MPG Report Date: 01-10-2022 Detailed Photographs G:\RJK\WORD\31272 Q504 Mattacheese DYIMS Yarmouth FR4 DP 1-6-22.docx Page 10 of 15 Figure 19 Callouts: Comments: At Part D, knife plates run into the rough openings, impeding installation of the window and interior sealant joints. 0106035 R. J. Kenney Associates, Inc. Title: Knife Plates in Rough Opening at Part D Figure 20 Callouts: Comments: At Part D, knife plates run into the rough openings, impeding installation of the window and interior sealant joints. 0106037 R. J. Kenney Associates, Inc. Title: Knife Plate in Rough Opening Q504 - Mattacheese DYIMS FR-4 Author: MPG Report Date: 01-10-2022 Detailed Photographs G:\RJK\WORD\31272 Q504 Mattacheese DYIMS Yarmouth FR4 DP 1-6-22.docx Page 11 of 15 Figure 21 Callouts: Comments: At Part C, knife plates run into the rough openings, impeding installation of the window and interior sealant joints. 0106047 R. J. Kenney Associates, Inc. Title: Knife Plates in Rough Opening Figure 22 Callouts: Comments: 0106151 R. J. Kenney Associates, Inc. Title: Shims at Interior Sealant Joint Q504 - Mattacheese DYIMS FR-4 Author: MPG Report Date: 01-10-2022 Detailed Photographs G:\RJK\WORD\31272 Q504 Mattacheese DYIMS Yarmouth FR4 DP 1-6-22.docx Page 12 of 15 Figure 23 Callouts: Comments: Screws fastened through the interior fin penetrate the AVB without sealant. Though the membrane passes ASTM D1970 it is recommended as best practice to add sealant at the screw location for wet setting each screw. In case of water intrusion into the rough opening, this can prevent water going past the cavity into the interior any further. 0106154 R. J. Kenney Associates, Inc. Title: Fasteners Through AVB at Rough Opening Figure 24 Callouts: Comments: 0106104 R. J. Kenney Associates, Inc. Title: Set Aside Wet Polyisocyanurate Insulation Q504 - Mattacheese DYIMS FR-4 Author: MPG Report Date: 01-10-2022 Detailed Photographs G:\RJK\WORD\31272 Q504 Mattacheese DYIMS Yarmouth FR4 DP 1-6-22.docx Page 13 of 15 Figure 25 Callouts: Comments: 0106097 R. J. Kenney Associates, Inc. Title: Installed Polyisocyanurate with Staining Figure 26 Callouts: Comments: A Sarnastack prefabricated pipe flashing is utilized as the pitch pocket to contain the Sarnafiller pourable sealant. Sanafil details show Sika Sarnafil Sarnaclad PVC-coated sheet metal pitch pockets, a minimum of 2-inches from the penetrations, as the only way to detail this condition. The condition should be reviewed with the manufacturer for approval, or the detail must be installed per the manufacturer’s published details. 0106107 R. J. Kenney Associates, Inc. Title: Pitch Pocket with Sarnastack Q504 - Mattacheese DYIMS FR-4 Author: MPG Report Date: 01-10-2022 Detailed Photographs G:\RJK\WORD\31272 Q504 Mattacheese DYIMS Yarmouth FR4 DP 1-6-22.docx Page 14 of 15 Figure 27 Callouts: Comments: A Sarnastack prefabricated pipe flashing is utilized as the pitch pocket to contain the Sarnafiller pourable sealant. Sanafil details show Sika Sarnafil Sarnaclad PVC-coated sheet metal pitch pockets, a minimum of 2-inches from the penetrations, as the only way to detail this condition. The condition should be reviewed with the manufacturer for approval, or the detail must be installed per the manufacturer’s published details. 0106111 R. J. Kenney Associates, Inc. Title: Pitch Pocket with Sarnastack Figure 28 Callouts: Comments: Multiple clamping rings installed at pipe penetrations were left uncut. This condition can allow for the long metal ring to strike the membrane in windy conditions. 0106116 R. J. Kenney Associates, Inc. Title: Uncut Clamping Ring Q504 - Mattacheese DYIMS FR-4 Author: MPG Report Date: 01-10-2022 Detailed Photographs G:\RJK\WORD\31272 Q504 Mattacheese DYIMS Yarmouth FR4 DP 1-6-22.docx Page 15 of 15 Figure 29 Callouts: Comments: A penetration did not have a clamping ring installed. Since the sealant has dried, new sealant must be applied prior to installation of a clamping ring. 0106120 R. J. Kenney Associates, Inc. Title: No Clamping Ring    Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.                Date on site: 1/6/22, Overcast, low 40’s                                                                                                               Caseyville, Il 62232                _________________________________________________________________________________________________    This Report is in reference to the proposed Retaining Wall installation that is located Due South of Athletic Field # 2.                                          Construction Notes:  The earthwork construction procedures, (foundation preparation) for this installation were  performed in accordance with the design documents submitted  by  COWEESET ENGINEERING, of West Bridgewater,  Massachusetts – Segmental Retaining Wall # 1, Orientation Plan dated: June 7, 2021. References to Wall Location,  orientation, stationing and other ancillary construction specifications that are not directly linked to Foundation  Preparation are also included in this submittal. The aforementioned documents are not included in this Earthwork  Monitoring Daily Field Report.     Excavate to design subgrade elevation using best practices   Place a 12” thick layer of Compacted ¾” Crushed Stone upon subgrade   Retaining Wall Blocks may now be placed upon the Crushed Stone surface    In‐Situ Native Sand Preparation Detail :  The soil matrix encountered at subgrade elevation largely consists of uniform sands and fine sands with scant traces of  non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the relative moisture  content of the soil. Since the encountered materials are of native, (natural) deposition the water content can vary from  location to location. Each situation must be evaluated to determine that the proper soil compaction techniques are  utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to moisten some areas with  supplied water in order to certify proper compaction of the native sand subgrade in these circumstances.    THE FOOTING LINES AND/OR  SPECIFIC FOOTINGS, ACCORDING TO THE DESIGN SCHEDULE, PRERARED THIS DAY  Activity for Thursday, January 6th, 2022:     Placed the Compacted Crushed Stone Mat upon previously prepared subgrade from Station # 0+52 to Station  # 2+10   Excavated and prepared subgrade from Station # 2+10 to Station # 2+70   Placed Compacted Crushed Stone Mat upon prepared subgrade from Station # 2+10 to Station # 2+70   Placed Insulation Blankets upon all prepared areas from Station # 0+52 to Station # 2+70    Photos Included:       Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.                Date on site: 1/6/22, Overcast, low 40’s                                                                                                               Caseyville, Il 62232                _________________________________________________________________________________________________    Previously Prepared Footing Trench looking West from Sta. 1+50 +/‐                           Placing Crushed Stone Sta. 0+70         Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.                Date on site: 1/6/22, Overcast, low 40’s                                                                                                               Caseyville, Il 62232                _________________________________________________________________________________________________      Grading Crushed Stone Sta. 0+70        Compaction Crushed Stone  Sta. 0+70