HomeMy WebLinkAboutBLD-19-001159Sched Date Inspection Type Status Insp Date Department Inspector Result Comment Request Date Request Comment Requestor's Phone Number Required/Optional Record ID InspID
6/3/2019 Building Final Passed 6/3/2019 Building Tim Sears 5/31/2019 door code 13579 N 18CAP-00000-005BY 25150710
5/20/2019 Building Final Improvement Required 5/20/2019 Building Tim Sears Guards needed at top of attic stairway 5/20/2019 door code #13579 N 18CAP-00000-005BY 25081346
5/15/2019 Set Backs Passed 5/15/2019 Building Tim Sears as built submitted 5/15/2019 N 18CAP-00000-005BY 25056192
5/15/2019 Other Passed 5/15/2019 Building Tim Sears air & duct testing results submitted 5/15/2019 N 18CAP-00000-005BY 25056193
5/13/2019 Building Final Improvement Required 5/13/2019 Building Brad Inkley "13579code front door
Door to garage needs to close by its self
Attic needed more indomcent paint" 5/8/2019 N 18CAP-00000-005BY 25010915
5/2/2019 Building Final Cancelled Building Brad Inkley 5/1/2019 N 18CAP-00000-005BY 24972766
2/4/2019 Insulation Partial 2/4/2019 Building Tim Sears "Date: 2/4/2019
Intumescent paint needs to be touched up over garage area
Ok to Sheetrock" 2/1/2019 N 18CAP-00000-005BY 24466488
2/1/2019 Insulation Improvement Required 2/1/2019 Building Brad Inkley "Date: 2/1/2019
Intumescent paint needs to be done better to many voids
Spray foam behind all outer wall receptacle boxes" 1/31/2019 N 18CAP-00000-005BY 24457629
1/28/2019 Frame Passed 1/28/2019 Building Tim Sears 1/28/2019 N 18CAP-00000-005BY 24437548
1/24/2019 Rough Frame Improvement Required 1/24/2019 Building Tim Sears "Date: 1/24/2019
Fill all wall plate penetrations
Need plumbing sign off
Insulate all duct terminations and seal at floor
Front porch deck needs support to foundation" 1/22/2019 N 18CAP-00000-005BY 24407117
12/28/2018 Sheathing/Nailing Passed 12/28/2018 Building Jim Brandolini Note: Several wall and roof areas missing nails and not driven into studs & rafters. Corrections made while on
site. 12/26/2018 N 18CAP-00000-005BY 24276210
10/16/2018 Foundation Passed 10/17/2018 Building Brad Inkley "Date: 10/17/2018
Footing undermined/washed out, engineered fix needed/FIX HAS BEEN RECIVED AND INSTALLED 10/24/18
October 23, 2018--Received Cert. from Michele Cudilo, PE---high strength concrete 6,500 psi poured under washed out area." 10/16/2018 N 18CAP-00000-005BY 23928975