February 4, 2022
Yarmouth Conservation Commission
1146 Route 28
South Yarmouth, MA 02664
Re: Request for Certificate of Compliance
SE 83-1289
Dear Commission Members:
On July 14, 1994, the Commission issued an Order
construction of a wood bulkhead and to permit a
and floats.
tel. (508) 362-4541
fax(508)362-9880
Daniel A. Ojala, P.E., P.L.S.
Arne H. Ojala, RE., P.L.S.
Daniel E. Gonsalves, RE., S.E
Craig J. Ferrari, E.I.T., S.E.
of
Conditions
platform with
for
ramp
A site visit was made for the purpose of closing out the Order of
Conditions. Although the plan stated a proposed 15'wide planting
border abutting the bulkhead, the final Order stated that there be
no lawn within 10' of the bulkhead - and that is the case here.
There is a 10' wide strip of gravel directly abutting the
bulkhead. In 1995 Down Cape Engineering certified the piling
Locations (certified attached). The bulkhead and platform have
been measured and located and found to be installed as proposed.
This is to certify, to the best of my knowledge and belief, that
the work was performed in substantial compliance with the approved
plan and Order of Conditions. We hereby request the issuance of a
Certificate of Compliance at this time.
Thank you for your consideration.
Very truly yours,
Daniel A. Ojala, PE, PLS
Down Cape Engineering, Inc.
Daniel A. Ojala, P.E., P.L.S.
Arne H. Ojala, RE., P.L.S.
Daniel E. Gonsalves, RE., S.E
Craig J. Ferrari, E.I.T., S.E.
of
Conditions
platform with
for
ramp
A site visit was made for the purpose of closing out the Order of
Conditions. Although the plan stated a proposed 15'wide planting
border abutting the bulkhead, the final Order stated that there be
no lawn within 10' of the bulkhead - and that is the case here.
There is a 10' wide strip of gravel directly abutting the
bulkhead. In 1995 Down Cape Engineering certified the piling
Locations (certified attached). The bulkhead and platform have
been measured and located and found to be installed as proposed.
This is to certify, to the best of my knowledge and belief, that
the work was performed in substantial compliance with the approved
plan and Order of Conditions. We hereby request the issuance of a
Certificate of Compliance at this time.
Thank you for your consideration.
Very truly yours,
Daniel A. Ojala, PE, PLS
Down Cape Engineering, Inc.
939 main street rl 6a
yarmouth port
mass 02675
structural design
land court
surveys
site planning
sewage system
designs
inspections
permits
down cape engineering
civil engineers & land surveyors
June 28, 1995
Brad
Ha11
Yarmouth
1146
ConserJ.-at i o i i Commission
Route 28
South
Yarmouth, 11h 0266"1
tel. (508) 362-4541
fax (508) 362-9880
Arne H. Ojala P.E., P.L.S.
Timothy H. Covell, P.L.S.
David C. Thulin, P.E.
ke; Certification of piling installation at 1] S��ordfis;;
Drive South Yarmouth
Dear Brad Halle
This is to certify that. the pilings at. the above mentioned
property have been installed in the proper location and
are evenly spaced.
OTriY
H*241
u,
G ; I COVE LL
o h�° C o ell , P.L.S. 0 No, 38035� �
+gin Cape Engineering, Inc, f�
cc: Charlotte Lizak