Loading...
HomeMy WebLinkAboutDYIMS PE Site report 20220210 Architect: Perkins Eastman DPC Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File ARCHITECT’S SITE OBSERVATION REPORT DATE OF VISIT: 02/10/2022 PROJECT: Dennis Yarmouth Intermediate Middle School 286 Station Avenue South Yarmouth, MA 02664 DATE OF ISSUE: 02/14/2022 PROJECT NO: 71011 WEATHER CONDITIONS: Partly cloudy, high 40s ARCHITECT: Perkins Eastman, DPC 20 Ashburton Street 8th floor Boston, MA The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit. WORK IN PROGRESS: 1) Interior partition framing 2) AVB installation and prep for window installation; stripping in of windows 3) Window installation 4) Drywall 5) PCC base installation and CMU at gymnasium 6) Exterior sheathing and parapet insulation installation 7) MEP rough-in 8) HVAC and plumbing overhead rough-in 9) Fire protection installation 10) Roofing 11) Misc. metals work 12) Site work: installation of the retaining wall for the upper sports field FIELD OBSERVATIONS: PE visited the site on Thursday 02-10, to review ongoing progress. 1. Beacon Waterproofing’s AVB installation at Area C is ongoing. At the time of observation, Area C appeared to be about 60% complete. 2. Stanley is installing the aluminum coping at the mockup (see photo on page 5). 3. Lymo Construction (cladding subcontractor) is in the process of installing the standoffs for the framing for the oko skin at the north and west sides of Area D (see photo on page 2). 4. Interior partition detailing (soffits and portals etc.) is ongoing framing is ongoing at the first and 2nd floors of Area D; Basic wall framing is ongoing at Area C (see photos on page 3). 5. Electrical and mechanical rough-in is ongoing at Area C and is almost completed for Area D classrooms. CB reports that full sheet rock installation at Area D will commence next week assuming inspections are completed. 6. HVAC and plumbing overhead roughing is ongoing in 1st and 2nd floor C wing. 7. Lambrian is continuing window installation in Area C; and Beacon is continuing to strip in the windows; Lambrian will be commencing curtain wall in Area D next week. 8. Rustic is installing fire protection mains and distribution in C 9. At the time of observation Stanley was installing the roof membrane at the lower roof of area B. 10. United has installed the framing for the light shelf at the SE side of Area C, with an extra knife plate in the middle for panel support. (see photo on page 3) 11. Lighthouse masonry has a second crew on site and they have started on the PCC base installation at area D, which is about 15% complete. Ground-faced CMU work at Area B is ongoing and at the time of observation the masons were working on the north wall of the gymnasium; work is about ¼ complete at the south wall of the gym and about ½ complete at the east. (photos on pages 3 and 4) REPORT BY: ABH Page 2 of 5 12. Silverback installed the second pour for the main area of B earlier in the week and silverback cut the control joints on Wednesday. Preparation work for the slab-on-grade pour at Area A has commenced as far as fine grading and crushed stone installation. 13. Stanley is still in the process of roofing the lower part of Area B. 14. Robert B. Our completed the subgrade prep for the PCC retaining wall for the upper field, and they are in the process of installing the retaining wall (see photo) DISCREPANCIES, SPECIAL INSTRUCTIONS 21001. Coping at the mockup. CB observed that Stanley was installing the coping without the ¾” gap for vent space that is required by Reider per shop drawings (for venting the top of the wall cavity at the GRFC panels). CB will instruct Stanley to correct this on the actual building. 11301. (from the 1-13 site report) Conflict between light shelf framing and radiant panels. Update: Per RFI response, United framed the outriggers for the light shelves in about four different typical classrooms in Area D, however Arden/CB now say that two steel plates are required at the point where two radiant panels come together. CB will consult with Arden about ways to make the original north-south steel dimensions work. 11302. (From 01-13 site report): Guard rail welds at D & C stairs - United still needs to grind welds for guards at academic stairs (see photo). still open 10601. (From 01-06 site report): Inside curve at auditorium east wall. Update: this work was completed. This item is being closed. 21603. (From the 12-16 site report) OF scuppers. Harold bros has installed the originally-specified ‘lamb’s tounge’ scuppers at the overflow outlets high on the building, in spite of revised (B14) detail, which called for changing to a square one. still open Attachments: · GPI earthwork report for 2-09 · GPI earthwork report for 2-10 SITE PHOTOS MOCK-UP PROGRESS AREA D EXTERIOR PROGRESS PCC BASE AT AREA D REPORT BY: ABH Page 3 of 5 TYPICAL NORTH ‘PORTAL’ FRAMING - AREA D TYPICAL CROSS-CONNECTION ‘PORTAL - AREA C TYPICAL SOUTH PORTAL - AREA D LIGHT SHELF FRAMING AT TYPICAL SOUTH CLASSROOM (AREA D) REPORT BY: ABH Page 4 of 5 VIEW FROM WEST WITH RETAINING WALL FOR FIELD B MASON CUTTING CMU FOR GYM MASONS LAYING BLOCK AT NORTH WALL OF GYM REPORT BY: ABH Page 5 of 5 PROGRESS AT SOUTH WALL OF GYM GRADE FOR WALL FOOTING AT KITCHEN (AREA B) COPING DETAIL AT MOCKUP    Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 2/9/22 Overcast, low 40’s                                                                                                               Caseyville, Il 62232                 _________________________________________________________________________________________________      This Report is in reference to the proposed Retaining Wall installation that is located Due East of Athletic Field # 2.                                          Construction Notes:  The earthwork construction procedures, (foundation preparation) for this installation were  performed in accordance with the design documents submitted  by  COWEESET ENGINEERING, of West Bridgewater,  Massachusetts – Segmental Retaining Wall # 2, Orientation Plan dated: June 7, 2021. References to Wall Location,  orientation, stationing and other ancillary construction specifications that are not directly linked to Foundation  Preparation are also included in this submittal. The aforementioned documents are not included in this Earthwork  Monitoring Daily Field Report.     Excavate to design subgrade elevation using best practices   Place a 12” thick layer of Compacted ¾” Crushed Stone upon subgrade   Retaining Wall Blocks may now be placed upon the Crushed Stone surface    In‐Situ Native Sand Preparation Detail :  The soil matrix encountered at subgrade elevation largely consists of uniform medium to fine sands and fine sands with  scant traces of non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the  relative moisture content of the soil. Since the encountered materials are of native, (natural) deposition the water  content can vary from location to location. Each situation must be evaluated to determine that the proper soil  compaction techniques are utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to  moisten some areas with supplied water in order to certify proper compaction of the native sand subgrade in these  circumstances.    THE FOOTING LINES AND/OR  SPECIFIC FOOTINGS, ACCORDING TO THE DESIGN SCHEDULE, PRERARED THIS DAY  Activity for Wednesday, February 9th, 2022:     Excavated and prepared subgrade from Station # 1+10 to Station # 1+40   Placed Compacted Crushed Stone Mat upon prepared subgrade from Station # 1+10 to Station # 1+40   Placed first course of wall segments upon the compacted crushed stone base    Photos Included:       Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 2/9/22 Overcast, low 40’s                                                                                                               Caseyville, Il 62232                 _________________________________________________________________________________________________        Compacting subgrade between station # 1+10 to station # 1+40      Placing crushed stone upon same     Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 2/9/22 Overcast, low 40’s                                                                                                               Caseyville, Il 62232                 _________________________________________________________________________________________________        Grading crushed stone between station 1+10 to station 1+40      Compacting crushed stone @ same location     Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 2/10/22, Clear, High 40’s                                                                                                                 Caseyville, Il 62232                 _________________________________________________________________________________________________    This Report is in reference to the proposed Retaining Wall installation that is located Due South of Athletic Field # 2.                                          Construction Notes:  The earthwork construction procedures, (foundation preparation) for this installation were  performed in accordance with the design documents submitted  by  COWEESET ENGINEERING, of West Bridgewater,  Massachusetts – Segmental Retaining Wall # 1, Orientation Plan dated: June 7, 2021. References to Wall Location,  orientation, stationing and other ancillary construction specifications that are not directly linked to Foundation  Preparation are also included in this submittal. The aforementioned documents are not included in this Earthwork  Monitoring Daily Field Report.     Excavate to design subgrade elevation using best practices   Place a 12” to 18” thick layer of Compacted ¾” Crushed Stone upon subgrade   Retaining Wall Blocks may now be placed upon the Crushed Stone surface    In‐Situ Native Sand Preparation Detail :  The soil matrix encountered at subgrade elevation largely consists of uniform medium to finesands and fine sands with  scant traces of non‐plastic silt. Therefore, the proper in‐situ compaction of this material is largely dependent on the  relative moisture content of the soil. Since the encountered materials are of native, (natural) deposition the water  content can vary from location to location. Each situation must be evaluated to determine that the proper soil  compaction techniques are utilized vis‐à‐vis the moisture content of the soil. In other words, it may be necessary to  moisten some areas with supplied water in order to certify proper compaction of the native sand subgrade in these  circumstances.    THE FOOTING LINES AND/OR  SPECIFIC FOOTINGS, ACCORDING TO THE DESIGN SCHEDULE, PRERARED THIS DAY  Activity for Thursday, February 10th, 2022:     Excavated and prepare subgrade from Station # 0+00 to Station # 0+52   Placed Compacted Crushed Stone Mat upon prepared subgrade from Station # 0+00 to Station # 0+52   Placed first course of wall segments upon the compacted crushed stone base    Photos Included:       Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 2/10/22, Clear, High 40’s                                                                                                                 Caseyville, Il 62232                 _________________________________________________________________________________________________        Preparing subgrade from Station 0+52 to Station 0+00      Placing crushed stone upon same     Earthwork Monitoring, Daily Field Report                                                                                      Geotechnical Partnership, Inc.  Dennis‐Yarmouth Intermediate School                                                                                                                      File No. 1814‐02   Field Representative: Francis E. Sviokla                                                                    Earthwork Contractor: Robert B Our Co., Inc  General Contractor: Commodore Builders                                                                 24 Great Western Rd., Harwich, MA 02645  404 Wyman St.,    Suite 400, Waltham, MA 02451                                       Pier Installer: CNC Foundations, 8251 Bunkum Rd.               Date on site: 2/10/22, Clear, High 40’s                                                                                                                 Caseyville, Il 62232                 _________________________________________________________________________________________________        Grading crushed stone from Station # 0+52 to Station # 0+00      Compacting crushed stone at same location