HomeMy WebLinkAboutPlan 2.15.202249
y
WETLAND AREA
.r•"
7.8 Sp•
•I1 Tf�r3 .. •4 /
7 �
•S / /r 2.3
7.6 •B rOI
83 �2.5
\ +7
l J EXIST ,, I2.5 .
ll + IU.S GARAGE + 13
`I cessFoof$ / 9
t N
GRASS AREA f I 0 D
+ I GII3 W
TI
14.7
C y
►r� �t m
VZOA
•/6 tl
+IBA •/S 7.4 / \ i.
4
•l3A
14.1
l PROP. LP GAS TANK
\ SILT WATTLE L%Er
\I/. •7 �; \ �
LGE. DIAM. TREES
-SA 4\7 \ PROP. SB.GE'N. \
WETLAND AREA \ \ �k
04A E . I
OJA
w \ !4.3
•2A
LIMIT OF AE FLOOD ZONE
/A EL= 12 NAVD88 (13 N GV D29)
PLAN SCALE - 1 IN. = 30 FT.
GENERAL NOTES
1. ELEVATIONS REFER TO NGVD 29. NAVD88 CONVERSION: EL NGVD29 -1.1= EL NAVD88
2. PORTIONS OF THE SITE ARE WITHIN THE FEMA -MAPPED COASTAL "AE" FLOOD ZONE EL. = 12
NAVD88 (13 NGVD 29 AS INDICATED) SHOWN ON YARMOUTH COMMUNITY PANEL NO.
25001CO5591, JULY 16, 2014
3. PLAN REFERENCE: DEED BOOK 5937, PG. 253; LOT LINE SURVEY BY FRANK WHITING, PLS.
4. WETLAND BOUNDARY AND SITE CONDITIONS VISUALLY CONFIRMED BY CAPE COD
ENGINEERING, INC. TO ACCEPTABLE TOLERANCE FOR PURPOSES OF RDA REVIEW
S. ALL EXISTING UTILITY LINES AND SEPTIC SYSTEM COMPONENTS ON THE BUILDING FRONT AND
SOUTH SIDE SHALL BE MARKED OUT AND PROTECTED PRIOR TO ANY WORK ACTIVITY
6. THE PROPOSED WORK ACTIVITY TO INSTALL THE LP TANK AND GENERATOR WITH TRENCHING
TO THE HOUSE IS WITHIN 100 FT. OF WETLAND AREAS. A WORK LIMIT AS DESIGNATED BY
YARMOUTH CONSERVATION COMMISSION SHALL BE ESTABLISHED WHERE NECESSARY. A 9 IN.
MIN. DIAMTER STRAW WATTLE ON THE DOWN SLOPE SIDE OF THE WORK AREA IS
RECOMMENDED.
7. EXCAVATION FOR LP TANK SHALL MAINTAIN A MIN. DISTANCE OF 10 FT. FROM THE NEAREST
TREE TRUNK.
B. SITE RESTORATION, SMOOTH GRADING, RAKING AND SEEDING SHALL R�TURN THE SITE TO
PRE -CONSTRUCTION CONDITION.
M.
Few
aft
MD.m60
PLAN SHOWING PROPOSED
GENERATOR W/ LP GAS TANK INSTALLATION
57 WHARF LANE, YARMOUTHPORT
ASSESSORS MAP 121, PARCEL 37
FEBRUARY 15, 2022 SCALE - AS NOTED
PREPARED BY
CAPE COD ENGINEERING, INC.
ROBERT M. PERRY, PE
P.O. BOX 1517
EAST DENNIS, MA 02641