HomeMy WebLinkAboutDYIMS PE Site report 20220303
Architect: Perkins Eastman DPC
Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File
ARCHITECT’S SITE OBSERVATION REPORT
DATE OF VISIT: 03/03/2022 PROJECT: Dennis Yarmouth Intermediate
Middle School
286 Station Avenue
South Yarmouth, MA 02664
DATE OF ISSUE: 03/09/2022 PROJECT NO: 71011
WEATHER
CONDITIONS:
Clear and Sunny, high 30s ARCHITECT: Perkins Eastman, DPC
20 Ashburton Street
8th floor
Boston, MA
The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit.
WORK IN PROGRESS:
1) Interior partition framing
2) AVB installation and prep for window installation; stripping in of windows and Curtain wall
3) Curtain wall installation
4) Brick masonry at Area D
5) CMU at gymnasium
6) Exterior framing, parapet framing and exterior sheathing
7) Drywall
8) MEP rough-in
9) Fire protection
10) Misc. metals work
11) Site work: installation of the retaining wall for the upper sports field
FIELD OBSERVATIONS:
PE visited the site on Thursday 03-03, to review ongoing progress.
1. Beacon Waterproofing’s membrane AVB installation is nearly complete at C and D. CB reports that next week
they will shift over to liquid applied AVB at CMU walls at gym.
2. Interior partition framing is complete in C and Interior partition detailing (soffits and portals etc.) is ongoing. Basic
wall framing is commencing at Area B
3. HVAC, plumbing and electrical rough in is almost complete in area D
4. HVAC and plumbing and electrical rough-in is ongoing in Area C. Gas piping installation is ongoing. Area C
plumbing rough-in is almost complete.
5. Fire safing inspection is scheduled for today in area D, ahead of sheet rock installation.
6. Lambrian is continuing Curtain Wall installation in Areas C and D (see photo on page 3).
7. Rustic is finished with with fire protection distribution in Area D, and they are ready to commence installing
sprinkler piping in Area C.
8. Spray fireproofing of the steel is complete at the second floor of Area B (i.e. fireproofing the roof and roof
structure.)
9. Anesse is finishing the electric room underground work at Area A, and this area is almost ready to be backfilled.
10. Colony has started framing parapets at the low roof on the north side of the gym, and will continue to the low roof
at south side of gym and media center (canopy roof). Stanley has de-mobilized because they are waiting for
parapet construction to catch up;
11. Brick masonry work has commenced at the SW corner of Area D and they are up to the heads of the windows at
the first floor (see photo on page 2).
12. Ground-faced CMU work at Area B at the gym is about 75% complete (see photo on page 2). At the time of
observation the masons were removing the scaffolding on the east side of the gym. Scaffolding has been moved
to the west side the masons are starting on the freestanding fire wall.
13. Lighthouse is washing down the CMU on the gym walls that are complete.
REPORT BY: ABH Page 2 of 3
14. Most underground work in A is complete and Silverback has almost finished installing the mesh for the slab-on-
grade pour at Area A; the pour is scheduled for next Tuesday 3-08.
15. Site progress: Installation of retaining wall for upper sports field is ongoing
DISCREPANCIES, SPECIAL INSTRUCTIONS
30301. Firestopping at concealed penetrations. PE clarified that per 780 CMR 714.5 all concealed floor
penetrations must be sealed to prevent the spread of smoke and hot gases even at C and D where the floor
is not rated, . Exceptions would be unconcealed annular opening for ductbank penetrations where ceiling-
less electrical rooms stack and the opening is clearly visible. Openings in rated floor assemblies (eg at A
and B) will need to be firestopped with rated material).
30302. Caulk color PE reviewed caulk color options at mockup and gave direction (see photo on page 3)
22401. (from 02 24 site report): Wainscot in corridor B134. PE discussed upcoming change to resolve the current
conflict between the wainscot and the columns on line B24., Update:. Bulletin 29 issued on 03 09; this item
is being closed
11301. (From 01-13 site report): Guard rail welds at D & C stairs - United still needs to grind welds for guards at
academic stairs (see photo). still open
21603. (From the 12-16 site report) OF scuppers. Harold bros has installed the originally-specified ‘lamb’s tounge’
scuppers at the overflow outlets high on the building, in spite of revised (B14) detail, which called for
changing to a square one. still open
Attachments:
· VAV site report for 02-28
SITE PHOTOS
SCAFFOLDING REMOVAL BRICK MAS. PROGRESS-AREA D INSIDE NORTH WALL OF GYM
REPORT BY: ABH Page 3 of 3
CURTAIN WALL INSTALLATION - AREA C
CAULK COLOR OPTIONS AT MOCKUP SHEATING PROGRESS - AREA B
PLUMBING ROUGH-IN – AREA B
VAV International, Inc.
400 W. Cummings Park, Suite 4700 - Woburn, Massachusetts 01801 Tel (781) 935-7228 Fax (781) 935-1822 www.vavint.com
Filename: J:\2018 Jobs Folder\2017-046 (Mattacheese MS) Perkins Eastman\Documents\Site Visit Report #4 \Mattacheese Site
Visit Report 2022-03-04.pdf 1
TO: Andrew Hazelton DATE: March 04, 2022
Perkins Eastman
RE: Mattacheese MS, Site Visit Report PAGES: 4
BY: Frank Stramaglia
SITE VISIT REPORT:
A site visit was made on Monday - February 28th, 2022, to review current progress. While on site no
deficiencies or code issues were observed.
FIRE PROTECTION STATUS
1. Building D fire protection is complete waiting for ceiling to drop heads.
2. No sprinkler piping in A, B or C building.
PLUMBING STATUS
1. Under slab work is complete.
2. All roof drains are installed.
3. Building D plumbing roughed and tested.
4. Building C plumbing rough complete.
5. Building A and B plumbing rough in progress.
Roof Drain piping – Insulation not started.
VAV International, Inc.
400 W. Cummings Park, Suite 4700 - Woburn, Massachusetts 01801 Tel (781) 935-7228 Fax (781) 935-1822 www.vavint.com
Filename: J:\2018 Jobs Folder\2017-046 (Mattacheese MS) Perkins Eastman\Documents\Site Visit Report #4 \Mattacheese Site
Visit Report 2022-03-04.pdf 2
Plumbing Rough
Plumbing Rough
VAV International, Inc.
400 W. Cummings Park, Suite 4700 - Woburn, Massachusetts 01801 Tel (781) 935-7228 Fax (781) 935-1822 www.vavint.com
Filename: J:\2018 Jobs Folder\2017-046 (Mattacheese MS) Perkins Eastman\Documents\Site Visit Report #4 \Mattacheese Site
Visit Report 2022-03-04.pdf 3
Spinkler pipin and flexible heads and insulated RWL piping.
Expansion Loop at Building C/D expansion joint.
VAV International, Inc.
400 W. Cummings Park, Suite 4700 - Woburn, Massachusetts 01801 Tel (781) 935-7228 Fax (781) 935-1822 www.vavint.com
Filename: J:\2018 Jobs Folder\2017-046 (Mattacheese MS) Perkins Eastman\Documents\Site Visit Report #4 \Mattacheese Site
Visit Report 2022-03-04.pdf 4
Roof Drains installed.