HomeMy WebLinkAboutDYIMS PE Site report 20220224
Architect: Perkins Eastman DPC
Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File
ARCHITECT’S SITE OBSERVATION REPORT
DATE OF VISIT: 02/24/2022 PROJECT: Dennis Yarmouth Intermediate
Middle School
286 Station Avenue
South Yarmouth, MA 02664
DATE OF ISSUE: 03/09/2022 PROJECT NO: 71011
WEATHER
CONDITIONS:
Cloudy, high 30s ARCHITECT: Perkins Eastman, DPC
20 Ashburton Street
8th floor
Boston, MA
The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit.
WORK IN PROGRESS:
1) Interior partition framing
2) Exterior framing and sheathing; parapet framing
3) AVB installation and prep for window installation; stripping in of Curtain wall
4) Curtain wall installation
5) PCC Base at Area D and CMU at gymnasium
6) Roofing
7) Drywall
8) MEP rough-in
9) HVAC and plumbing overhead rough-in
10) Fire protection installation
11) Misc. metals work
FIELD OBSERVATIONS:
PE visited the site on Thursday 02-24, to review ongoing progress.
1. PE walked the site in the morning to review site progress with Eric Wilhelmsen of CDW, and also made
observations at the service area where there are pending layout changes.
2. Colony is continuing to install exterior framing and sheathing at the south side of Area B.
3. At the time of observation, Waterproofing membrane AVB installation was proceeding at the south façade of area
C and at the north façade of area B (see photo on page 3).
4. At the time of observation, Lymo had commenced installing mineral wool on the north façade of D.
5. and Interior partition detailing (soffits and portals etc.) is ongoing in area C.
6. Rough in is almost complete at Area D. CB is pushing to complete plumbing rough-in in Area D.
7. HVAC, plumbing and electrical rough-in ongoing in Area C, including gas piping installation and plumbing
overhead rough installation; plumbing rough-in has commenced at area B.
8. At the time of observation, Colony was installing blocking for roof ladders.
9. Lambrian is continuing Curtain Wall installation in Areas C and D.
10. Rustic is almost finished with protection distribution in Area D.
11. Spray fireproofing of the steel has commenced at the second floor of Area B (i.e. fireproofing the roof and roof
structure.)
12. At the time of observation, Stanley was installing roof membrane at the music wing (Area A south).
13. Lighthouse has installed about 80% of the PCC base for Area D, and the ground-faced CMU work is almost up to
the top course at the south façade of the gym. The staging has come down at the North wall of the gym and the
CMU wall is ready for United to begin installing the seismic clips at the top of the wall (see photo on page 3).
14. Building A is getting prepped for a 3-08 slab-on-grade pour at the music wing (south side) as well as the lobby
through to the main atrium area; the edges have been formed and Silverback is almost ready to begin installing
the mesh (see photo on page 3).
REPORT BY: ABH Page 2 of 3
DISCREPANCIES, SPECIAL INSTRUCTIONS
22401. Wainscot in corridor B134. PE discussed upcoming change to resolve the current conflict between the
wainscot and the columns on line B24, by eliminating the furring layer that is currently shown on the wall
along B24. This will create a 4” jog in the tile wainscot at the expansion joint with the main building (where
the CMU terminates). Pertinent details will be re-issued in bulletin 29.
11301. (From 01-13 site report): Guard rail welds at D & C stairs - United still needs to grind welds for guards at
academic stairs (see photo). still open
21603. (From the 12-16 site report) OF scuppers. Harold bros has installed the originally-specified ‘lamb’s tounge’
scuppers at the overflow outlets high on the building, in spite of revised (B14) detail, which called for
changing to a square one. still open
Attachments:
· CDW field report for 02-24
SITE PHOTOS
UNDERSLAB INSULATION PREP AREA D INTERIOR PROGRESS ROOF PARAPET AT AREA B
REPORT BY: ABH Page 3 of 3
NORTH WALL OF GYM COMPLETE
AVB PROGRESS - AREA C
PREPPING FOR SLAB ON GRADE PLACEMENT - AREA A
CDW CONSULTANTS, INC
CIVIL & ENVIRONMENTAL ENGINEERS
Memorandum
6 Huron Drive, Natick, MA 01760 P: 508-875-2657 FAX: 508-875-6617
www.cdwconsultants.com
To: Perkins Eastman
From: Eric Wilhelmsen
Subject: Field Report
Date: February 24, 2022
Project: Dennis Yarmouth Intermediate Middle School, South Yarmouth MA
On February 24, 2022, CDW visited the site to review the current site construction progress.
Weather
Partially cloudy, 35 degrees
Observations
The main parking area has been partially paved, with some of the rain garden areas roughed in, and is
being used for much of the construction parking. The athletic field (lower field) to the immediate east of
the new building is the main soil stockpile area, while the other easterly field (upper field), has been
partially graded out, including the partial construction of the upper field’s associated retaining walls.
Near southeast corner of new building, looking toward paved main parking area
6 Huron Drive, Natick, MA 01760 P: 508-875-2657 FAX: 508-875-6617
www.cdwconsultants.com
Soil stockpiles on lower field
South of stockpile area looking towards the new building
6 Huron Drive, Natick, MA 01760 P: 508-875-2657 FAX: 508-875-6617
www.cdwconsultants.com
South of stockpile area look towards the upper field
Along upper field looking north
6 Huron Drive, Natick, MA 01760 P: 508-875-2657 FAX: 508-875-6617
www.cdwconsultants.com
Along upper field looking east, showing portion of new retaining wall
Along upper field, looking south, showing portions of new retaining wall