HomeMy WebLinkAboutJ5951 Dennis Yarmouth Middle School WE 2022-04-01Summary Report #44
April 4, 2022
Attn:
Job No: 5951
Job Name:Dennis Yarmouth Middle School
296 Station Ave
South Yarmouth, MA 02664
Permit No.:BLD-21-006153
TESTING
INSPECTION
ENGINEERING
GK
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
March 28, 2022
James Descoteaux reported to Nicholas Hull with PMA at the jobsite. Performed structural masonry inspection for grout placement. See attached.
The work observed was, to the best of James knowledge, in accordance with the approved plans, specifications and applicable standards of
workmanship.
March 30, 2022
Roney Nakhoul reported to Nick Hull with PMA at the jobsite. Performed reinforcing steel placement inspection. See attached.
Roney Nakhoul reported to Nick Hull with PMA at the jobsite. Performed structural masonry inspection for grout placement. See attached.
Roney Nakhoul reported to Nick Hull with PMA at the jobsite. Performed steel and welding inspection. See attached.
Exception: WIP BLDG B CFMF
Noncompliance was brought to the attention of Jon Pope with PMA:
The work observed was, to the best of Roney's knowledge, in accordance with the approved plans, specifications and applicable standards of
workmanship, except as noted.
March 31, 2022
James Descoteaux reported to Nicholas Hull with PMA at the jobsite. Performed concrete placement and sampling inspection. Concrete sample(s)
obtained: (5) per set, (3) set(s), (15) total. See attached.
James Descoteaux reported to Nicholas Hull with PMA at the jobsite. Performed structural masonry inspection. See attached.
The work observed was, to the best of James knowledge, in accordance with the approved plans, specifications and applicable standards of
workmanship.
TESTING
INSPECTION
ENGINEERING
GK
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
April 1, 2022
Eric Pittman reported to John Pope with PMA at the Jobsite. Performed CFMF inspection. See attached.
Eric Pittman reported to John Pope with PMA at the jobsite. Performed firestopping observation destructive testing inspection. See attached.
Eric Pittman picked up (15) concrete cylinders from the jobsite.
The work observed was, to the best of Eric's knowledge, in accordance with the approved plans, specifications and applicable standards of
workmanship.
Laboratory test results are enclosed if testing was done during the period covered by this report.
Limitations: These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as
acceptance or guarantee of the work. Even with diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the
code.
Reviewed by:
Jillian Kass
Staff Engineer
04-08-2022
Date
Technical Contact: Bruce Tie, Engineering Manager (btie@fenaghengineering.com)
Administrative Contact: Gabriella Kass (Gkass@fenaghengineering.com)
cc:Fenagh PM – emushi@fenaghengineering.com (email)
Fenagh Technical Reviewer – btie@fenaghengineering.com (email)
TESTING
INSPECTION
ENGINEERING
Project No: 5951
Project Name: Dennis Yarmouth Middle School
Project Location: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: James Descoteaux
Inspection Type: Masonry Grout Placement
Pg. 1 of 1
March 28, 2022
Time In: 07:00 Break: 12:00-12:30 Time Out: 15:30
DFR ID: 32115
Weather: Partly Cloudy
Temperature: 34°F
Permit No. : BLD-21-006153
Plans Dated: 07/02/2021
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable standards
of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
James Descoteaux
Inspector
03-28-2022
Date Jillian Kass
Staff Engineer
03-29-2022
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
James Descoteaux reported to Nicholas Hull with PMA at the jobsite. Observed placement of 12" units, mix design #1-4WET Cape
Cod Ready Mix, 3000 PSI at 28 days, for the 10" CMU wall, high-lift height 1 course from level 3 courses. Cleanouts were used,
cells are clean and acceptable. consolidated by mechanical vibration. wall(s) at Level 3 at gridlines West wall of gynasium B24 / J.7-
N.
Referenced Details: 1-4WET Grout
Additional Notes: No samples taken per PMA contractors on this date. Rebar placed at (B24 / J.7 - P.1). No CMU block
placement/mortar.
TESTING
INSPECTION
ENGINEERING
Project No: 5951
Project Name: Dennis Yarmouth Middle School
Project Location: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Roney Nakhoul
Inspection Type: Reinforcing Steel Placement
Pg. 1 of 1
March 30, 2022
Time In: 13:00 Time Out: 15:00
DFR ID: 32264
Weather: Partly Cloudy
Temperature: 50°F
Permit No. : BLD-21-006153
Plans Dated: 08/23/2021
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable standards
of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
Roney Nakhoul
Inspector
03-30-2022
Date Jillian Kass
Staff Engineer
04-01-2022
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Roney Nakhoul reported to Nick Hull with PMA at the jobsite. Observed placement of reinforcing steel for Level 1 Building A
and Monumental stair Bldg B slab on grade at b1-b3/K-L.9, U-R/a2-a12. N.9-N.4/b4-b9, b19-b21/M.3-L.5 . Work complete.
Reference detail R-01, RFI #156, S-1.13B.
Reinforcing Steel and Anchor Bolts
Y N Y N
Rebar Installed Per Approved Details ✓General Notes And Typical Details Reviewed ✓
Rebar The Proper Size ✓Rebar The Proper Type/grade ✓
Rebar Spacing Acceptable ✓Min Clearances Achieved Around Rebar ✓
Min Lap Splice Lengths Achieved ✓Additional Required Rebar Has Been Placed ✓
TESTING
INSPECTION
ENGINEERING
Project No: 5951
Project Name: Dennis Yarmouth Middle School
Project Location: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Roney Nakhoul
Inspection Type: Masonry Grout Placement
Pg. 1 of 1
March 30, 2022
Time In: 11:00 Time Out: 13:00
DFR ID: 32265
Weather: Sunny
Temperature: 30°F
Permit No. : BLD-21-006153
Plans Dated: 07/02/2021
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable standards
of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
Roney Nakhoul
Inspector
03-30-2022
Date Jillian Kass
Staff Engineer
04-01-2022
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Roney Nakhoul reported to Nick Hull with PMA at the jobsite. Observed placement of Cape cod redimix, mix design #1-4 WET
GROUT, 3000 PSI at 28 days, for the 10" CMU wall, high-lift height 31-36 courses. Cleanouts were used, cells are clean and
acceptable. consolidated by mechanical vibration. wall(s) at Level 1 at gridlines West wall of the gymnasium b24/P.1-K.8 and
b27/P.9-P.1.
Referenced Details: S-1.13B
TESTING
INSPECTION
ENGINEERING
Project No: 5951
Project Name: Dennis Yarmouth Middle School
Project Location: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Roney Nakhoul
Inspection Type: Visual inspection of welded clips, Sheet metal framing
Pg. 1 of 1
March 30, 2022
Time In: 11:00 Time Out: 13:00
DFR ID: 32266
Weather: Sunny
Temperature: 30°F
Permit No. : BLD-21-006153
Plans Dated: 01/19/2021
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable standards
of workmanship, except as noted.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
Roney Nakhoul
Inspector
03-30-2022
Date Jillian Kass
Staff Engineer
04-01-2022
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Roney Nakhoul reported to Nick Hull with PMA at the Jobsite. Requested by PMA to visually inspect welded masonry firewall slip
connection to structural steel. Assembly is complaint with the detail provided.
Observed CFMF at Bldg B, exterior sheathing and bracing install compliant. Interior side bracing and bottom screws are missing.
Referenced Details: A-1.13B, S-3.04, 3.05, S-3.06
Exception(s): WIP BLDG B CFMF
Non-compliance conditions were brought to the attention of Jon Pope with PMA
TESTING
INSPECTION
ENGINEERING
Project No: 5951
Project Name: Dennis Yarmouth Middle School
Project Location: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: James Descoteaux
Inspection Type: Concrete Placement and Sampling
Pg. 1 of 1
March 31, 2022
Time In: 07:00 Break: 11:00-11:30 Time Out: 15:30
DFR ID: 32381
Weather: Mist
Temperature: 45°F
Permit No. : BLD-21-006153
Plans Dated: 07/30/2021
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable standards
of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
James Descoteaux
Inspector
03-31-2022
Date Jillian Kass
Staff Engineer
04-04-2022
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
James Descoteaux reported to Nicholas Hull with PMA at the jobsite. Observed placement of and performed sampling of concrete
for Level 1, slab on grade at Buidling A and Monumental Stair Building B (B1-B3/K-L.9),(U-R/A2-A12),(N.9-N.4/B4-B9),(B19-
B21/M.3-L.5) (mix no. 4000DNA, design strength of 4000 psi at 28 days, specified slump from 5 to 9 in., specified air content from
0% to 3%, and 121 cubic yards placed). Monitored loads for mix no., slump, temp., and time limit. Prepared 4x8" cylinder test
specimens sampled from Discharge of Chute.
Set
No.
Slump
(in.)
Mix
Temp.
(°F)
Air
Temp.
(°F)
Air
Content
(%)
Unit
Weight
(pcf)
Truck
No.Location Qty. of
Samples
Batch
Time
Sample
Time Subcontractor Ticket
No.
1 7.5 64 42 2.3 150.1 56 N.4/B.9 5 6:24 AM 7:33 AM Silverback Concrete
Construction
2380
1
2 8.25 69 48 1.9 149.9 75 R/A8 5 7:41 AM 8:40 AM Silverback Concrete
Construction
3422
5
3 6.25 70 52 1.7 149,4 61 S.7/A5 5 8:52 AM 10:00 AM Silverback Concrete
Construction
3423
0
15 Total
Additional Notes: Rebar was previously inspected on March 30, 2022.
Referenced Details: R-01, RFI #156, S-1.13B
TESTING
INSPECTION
ENGINEERING
Project No: 5951
Project Name: Dennis Yarmouth Middle School
Project Location: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: James Descoteaux
March 31, 2022
Permit No. :
Mix Design
TESTING
INSPECTION
ENGINEERING
Project No: 5951
Project Name: Dennis Yarmouth Middle School
Project Location: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: James Descoteaux
Inspection Type: Masonry CMU Block Placement
Pg. 1 of 1
March 31, 2022
Time In: 07:00 Break: 11:00-11:30 Time Out: 15:00
DFR ID: 32383
Weather: Cloudy
Temperature: 48°F
Permit No. : BLD-21-006153
Plans Dated: 07/02/2021
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable standards
of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
James Descoteaux
Inspector
03-31-2022
Date Jillian Kass
Staff Engineer
04-04-2022
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
James Descoteaux reported to Nicholas Hull with PMA at the jobsite. Observed placement of 10" units, constructed with Amerimix
Type S mortar, 4 courses, wall(s) at Level 1, gridlines West locker room wall(B24/J-J.7). Work in progress. Reference details
S-1.13B.
Additional Notes: 1 course laid at B24-B27/P.1 and rebar was inspected. No samples were taken per request of PMA.
TESTING
INSPECTION
ENGINEERING
Project No: 5951
Project Name: Dennis Yarmouth Middle School
Project Location: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Eric Pittman
Inspection Type: CFMF at auditorium seating
Pg. 1 of 1
April 1, 2022
Time In: 13:00 Time Out: 15:00
DFR ID: 32471
Weather: Cloudy
Temperature: 55°F
Permit No. : BLD-21-006153
Plans Dated: 03/01/2021
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable standards
of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
Eric Pittman
Inspector
04-01-2022
Date Jillian Kass
Staff Engineer
04-04-2022
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Eric Pittman reported to John Pope with PMA at the Jobsite . Seating tiers 1 thru 4 are completed and decked. Work conforms to SKA-1
shop drawings (9-21-21 approval with notes) and structural plan details. Studs are 16 gauge 50 ksi or 18 gauge 33ksi.
Referenced Details: Structural plans, SKA-1 approved shop drawings.
TESTING
INSPECTION
ENGINEERING
Project No: 5951
Project Name: Dennis Yarmouth Middle School
Project Location: 296 Station Ave, South Yarmouth, MA, 02664
Fenagh Representative: Eric Pittman
Inspection Type: Firestopping observation destructive testing
Pg. 1 of 1
April 1, 2022
Time In: 11:00 Break: 12:00-12:30 Time Out: 13:00
DFR ID: 32573
Weather: Cloudy
Temperature: 55°F
Permit No. : BLD-21-006153
Plans Dated: 04/06/2022
Conformance:
The Work observed was, to the best of my knowledge, in accordance with the approved plans, specifications and applicable standards
of workmanship.
Limitations:These inspections were performed in accordance with requirements, but please note this report shall not be relied upon by others, as acceptance or guarantee of the work. Evenwith diligent inspection techniques, the contractor is solely liable for defects or failures to adhere to the code. Information provided herein has not been reviewed by supervisory staff,therefore, should be considered preliminary and subject to change, unless signed by both inspector and engineer below.
Reviewed by:
Eric Pittman
Inspector
04-01-2022
Date Jillian Kass
Staff Engineer
04-04-2022
Date
12 Tech Circle, Natick, MA 01760 | (617) 938-3774 office | (617) 344-0478 fax
Southern California
New England
Arizona
Texas
New York
Eric Pittman reported to John Pope with PMA at the Jobsite. Exterior perimeter wall firestopping was completed on the second level of
building C. At the request of John Pope this inspector destructively tested randomly selected through floor MEP penetrations per ASTM E
2174 guidelines. Penetrations were inspected on the 2nd level wing C. One penetration for each submitted assembly design was
destructively inspected. For plumbing work , design CAJ 12 5091 was inspected with passing results. For electrical work, design CAJ
2647 were destructively tested with passing results. All tested locations were repaired on this same day. Over 2% of each type design
installed to date have been tested.
Additional Notes: At the request of John Pope, In-wall and In-chaise 2nd level wing D floor penetrations were inspected for
completion. Open penetrations were found and marked on the attached plan, which was provided to PMA.
Except for 1-2 mechanical rooms and elevator shaft, the C wing, per "G" project plans, has no fire-rated walls or floors. Work is
ongoing and incomplete at the rated Mechanical rooms. Work is ongoing and incomplete at rooms and closets within the central
corridor.
Referenced Details: Submitted Hilti firestop designs. Project plans and referenced standards.
Daily Pick Up Report
Job Number: Project Name:
Fenagh Representative: Date:
Cylinders
Shotcrete
Grout
Mortar
Grout Cubes
Prisms
PT Cables
Fireproofing Samples
Soil Samples
Rebar Samples
Steel Plates
Other
Additional Comments:
Job Site Shop Batch Plant/Quarry Other: ________
Cure Box Temp: ______ High/Low Temp: ________ Outside Temp: ______
NCR ID#Date Location Inspector Issue RFI/ Submittal
No.Resolved? (Y/N)Sub/ Contractor Date Resolved Comment
1 7/21/2021 Wall : C /d3 Arsene Ntwali
Low break:
Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content
from 4.5% to 7.5%
Y Marguerite
Tuesday, January
18, 2022 12:53
PM
EOR to Advise
7 day break 08/10/2021
Set 1 = 1,860 psi
28 day break 08/31/2021
Set 1 = 2,800 psi
Set 1 = 2,900 psi
Set 1 = 3,480 psi
28 day average = 3,060 psi
2 7/28/2021 Footing : C16/E Arsene Ntwali
Low break:
Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content
from 4.5% to 7.5% : Lab Log No.: 15519 (2744-2745)
Y Marguerite
Tuesday, January
18, 2022 12:53
PM
EOR to Advise
28 day break 08/31/2021
Set 1 = 3,350 psi
Set 1 = 3,500 psi
Set 1 = 3,620 psi
56 day break 09/22/2021
Set 1 = psi
3 7/30/2021
Footings Set # 1 :Column
line/Row: D.3/c116 Set # 2
Columm line / Row c5/H
Arsene Ntwali
Low break:
Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content
from 4.5% to 7.5%
Y Marguerite
Tuesday, January
18, 2022 12:53
PM
EOR to Advise
28 day break 08/27/2021
Set 1 = 3,070 psi
Set 1 = 3,330 psi
Set 1 = 3,430 psi
Set 2 = 3,330 psi
Set 2 = 3,520 psi
Set 2 = 3,580 psi
56 day break 09/24/2021
Set # 1 = 3,720 psi
Set #2 = 3,670 psi
4 8/3/2021 Footings: Elevator pit
foundation Arsene Ntwali
Low break:
Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content
from 4.5% to 7.5%
Y Marguerite
Tuesday, January
18, 2022 12:53
PM
EOR to Advise
7 day break 08/10/2021
Set 1 = 2,610 psi
28 day break 08/31/2021
Set 1 = 3,170 psi
56 day break 9/28/2021
Set 1 = 3,330 psi
Set 1 = 3,490 psi
Set 1 = 3,700 psi
56 day average set 1 = 3,510 psi
5 8/6/2021 Level 1 Wall at Building C
and B - E/c2 Arsene Ntwali
Low break:
Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content
from 4.5% to 7.5%
Y Marguerite
Tuesday, January
18, 2022 12:53
PM
EOR to Advise
7 day break 08/13/2021
Set 1 = 2,980 psi
28 day break 09/3/2021
Set 1 = 3,170 psi
56 day break 10/8/2021
Set 1 = 3,230 psi
Set 1 = 3,400 psi
56 day average set 1 = 3,320 psi
6 8/6/2021 Level 1 Wall at Building C and
B - J.7/b25 Arsene Ntwali
Low break:
Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content
from 4.5% to 7.5%
Y Marguerite
Tuesday, January
18, 2022 12:53
PM
EOR to Advise
7 day break 08/13/2021
Set 2= 2,390 psi
28 day break 09/3/2021
Set 2 = 3380 psi
56 day break 10/8/2021
Set 1 = psi
7 8/13/2021 Level 1 Footings at Building
B: P.1/b33 Arsene Ntwali
Low break:
Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content
from 4.5% to 7.5%
Y Marguerite
Tuesday, January
18, 2022 12:53
PM
EOR to Advise
17 day break 08/30/2021
Set 1 = 3,090 psi
28 day break 09/10/2021
Set 1 = 3,460 psi
Set 1 = 3,510 psi
56 day break 10/08/2021
Set 1 = psi
Set 1 = psi
8 8/13/2021 Level 1 Footings at Building
B: J.3/b24 Arsene Ntwali
Low break:
Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content
from 4.5% to 7.5%
Y Marguerite
Tuesday, January
18, 2022 12:53
PM
EOR to Advise
7 day break 08/20/2021
Set 1 = 2,320 psi
28 day break 09/10/2021
Set 1 = 2,840 psi
56 day break 10/08/2021
Set 1 = psi
Set 1 = psi
9 8/20/2021 Level 1 Footings at
Foundation: Wall: H/c5 Arsene Ntwali
Low break:
Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content
from 4.5% to 7.5% : Lab Log No.: 15860 (3024)
Y Marguerite
Tuesday, January
18, 2022 12:53
PM
EOR to Advise
7 day break 08/27/2021
Set 1 = 2,810 psi
28 day break 09/17/2021
Set 1 = 3,440 psi
Set 1 = 3,500 psi
56 day break 10/15/2021
Set 1 = 3,920 psi
Set 1 = 4,020 psi
10 9/3/2021 Level 1 Wall; U/a5 Arsene Ntwali
Low break:
Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content
from 4.5% to 7.5% ; Lab Log No.: 16067 (3123)
Y Marguerite
Tuesday, January
18, 2022 12:53
PM
EOR to Advise
7 day break 09/10/2021
Set 1 = 2,050 psi
28 day break 10/01/2021
Set 1 = 3,100 psi
56 day break 10/29/2021
Set 1 = 3,510 psi
Set 1 = 3,630 psi
Set 1 = 3,660 psi
11 9/9/2021 Level 1 Footing: M.5/b17 Arsene Ntwali
Low break:
Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content
from 4.5% to 7.5% ; Lab Log No.: 16132 (3175)
Y Marguerite
Tuesday, January
18, 2022 12:53
PM
EOR to Advise
7 day break 09/16/2021
Set 1 = 2,400 psi
28 day break 10/07/2021
Set 1 = 3,480 psi
Set 1 = 3,490 psi
56 day break 11/04/2021
Set 1 = 4,050 psi
Set 1 = 4,240 psi
12 9/10/2021 Level 1 Footing: L.9/b2 Arsene Ntwali
Low break:
Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content
from 4.5% to 7.5% ; Lab Log No.: 16133 (3176)
Y Marguerite
Tuesday, January
18, 2022 12:53
PM
EOR to Advise
7 day break 09/17/2021
Set 1 = 2,330 psi
28 day break 10/08/2021
Set 1 = 3,450 psi
Set 1 = 3,450 psi
Set 1 = 3,490 psi
56 day break 11/05/2021
Set 1 = 4,060 psi
13 8/13/2021
Level 1 Footings at Building
B: Set # 1
P.1/b33 Set # 2
J.3/b24
Arsene Ntwali
Low break:
Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content
from 4.5% to 7.5% ; Lab Log No.: 15745 (2945-2946)
Y Marguerite
Tuesday, January
18, 2022 12:53
PM
EOR to Advise
7 day break 08/20/2021
Set 2 = 2,320 psi
28 day break 09/10/2021
Set 1 = 3,460 psi
Set 1 = 3,510 psi
Set 2 = 2,840 psi
56 day break 10/08/2021
Set 1 = 3,760 psi
Set 1 = 3,850 psi
Set 2 = 3,260 psi
Set 2 = 3,030 psi
Set 2 = 3,150 psi
Set 2 = 3,260 psi
14 8/17/2021 Level 1 Footings at Building
B: S.1/b27 Arsene Ntwali
Low break:
Mix Desing 3500D, design strength of 3500 psi at 28 days, specified slump from 4 to 6 in., specified air content
from 4.5% to 7.5% ; Lab Log No.: 15745 (2945-2946)
Y Marguerite
Tuesday, January
18, 2022 12:53
PM
EOR to Advise
7 day break 08/24/2021
Set 1 = 2,510 psi
28 day break 09/14/2021
Set 1 = 3,280 psi
Set 1 = 3,430 psi
56 day break 10/12/2021
Set 1 = 4,070 psi
Set 1 = 4,110 psi
15 9/23/2021 Level 1 Footings at Building
B: P7/a18 Arsene Ntwali
Low break:
Mix Desing 5000D, design strength of 5,000 psi at 28 days, specified slump from 5 to 8 in., specified air content
from 4% to 7% ; Lab Log No.: 16288 (3264)
Y Marguerite
Tuesday, January
18, 2022 12:53
PM
EOR to Advise
7 day break 09/30/2021
Set 1 = 3,510 psi
28 day break 10/21/2021
Set 1 = 4,470 psi
56 day break 11/18/2021
Set 1 = 4,880 psi
Set 1 = 5,120 psi
Set 1 = 5,210 psi
16 11/2/2021
Level 1 Slab at Building D:
Line A-D1, Row D1-before
D16
Enea Mushi Measured Floor Flatness, Levelness (34.7 and 18.3) did not meet overall project requirement (35 and 25)N Marguerite
Tuesday, January
18, 2022 12:53
PM
EOR to Advise
17 9/27/2021
Level 1 Wall at Q-P.7/a18,
a18-24/W
D17 : Sampled @ N.4/b5
Arsene Ntwali
Low break:
Mix Desing 5000D, design strength of 5,000 psi at 28 days, specified slump from 5 to 8 in., specified air content
from 4% to 7% ; Lab Log No.: 16339 (3323)
Y Marguerite
Tuesday, January
18, 2022 12:53
PM
EOR to Advise
7 day break 10/04/2021
Set 1 = 3,510 psi
28 day break 10/25/2021
Set 1 = 4,170 psi
56 day break 11/22/2021
Set 1 = 4,700 psi
90 day break 12/26/2021
Set 1 = psi
Set 1 = psi
18 12/16/2021
Level 1, area A
@ S.1-S.5/b11 bottoms only:
Level 16
@ K.9-N/b33 steel girts: Level
low roof/high roof
@ N.9-K/b1, K/b1-b22,
L+P.7/a17-b21,
LP.7/a17+b21, V-V.9/a15,
W/a1-a14, W-V/a1, V/a1-a2,
V-U/a2
Tony Paradis
WPSs not available for review for Stellar Steel Erectors or United Steel. Stellar Steel Used FCAW process in the 2F,
4F, 2G and 3G possitions. United Steel used the SMAW process in the 2F possition. rnWPQRs recieved for Stellar
Steel Erectors show no welders qualified for FCAW welds in the 4F or 3G positions.
N PMA EOR to Advise
19 12/17/2021 top and bottom plates Tony Paradis Contractor has failed to maintain 3/4" minimum distance from screw to edge of light gauge surfaces as called for
in General Note 4 on SK-3.Y PMA Wed 3/9/2022
12:46 PM EOR to Advise
20 11/18/2021 Level 1 Metal pan stairs at
Building D Arsene Ntwali Low Break :
Mix #: 4000DGRNA : Slump 5-9 air 0-3 Design Strength (psi): 4,000 @28 days : Lab Log No.: 17282 (3681)N PMA
EOR to Advise
7 day break 11/25/2021
Set 1 = 2,060 psi
28 day break 12/16/2021
Set 1 = 2,580 psi
56 day break 01/13/2022
Set 1 = 3,220 psi
90 day break 02/16/2022
Set 1 = 3,350 psi
21 12/21/2021 locations at building A and B Blake Mullens
The items as listed herein have not been accomplished in accordance with the approved documents, plans and
specifications: No. 10 screw missing at inside leg of track connections. Contractor to install inside leg no 10 screws
with lift access. Pins at typical parapet detail within this area not spaced properly. Pins installed at random
locations instead of 5 pins within top 2" and 4 pins within bottom 2".
N PMA EOR to Advise
22 1/10/2022 Level 1, gridlines P.1-
J.1/B.33
Abdulwahab
Abulgasem
CMU blocks the Vertical #7 by 16” not reaching overlap requirements, and may getting conflict with other
structures as going up.Y PMA 1/13/2022 EOR to Advise
23 11/8/2021 Level 2 Salb on metal deck at
Building C: E/C4 Arsene Ntwali Low Break :
Mix #: 4000DGRNA : Slump 5-9 air 0-3 Design Strength (psi): 4,000 @28 days : Lab Log No.: 16995 N PMA
EOR to Advise
7 day break 11/15/2021
Set 1 = 2,880 psi
28 day break 12/06/2021
Set 1 = 3,820 psi
56 day break 01/03/2022
Set 1 = 4,160 psi
Set 1 = 4,250 psi
Set 1 = 4,300 psi
24 12/2/2021 Building C : F-G/C7-9 Arsene Ntwali Low Break :
Mix #: 3000DNA : Slump 5-9 air 0-3 Design Strength (psi): 3,000 @28 days : Lab Log No.: 17226 (3735)N PMA
EOR to Advise
7 day break 12/09/2021
Set 1 = 1,290 psi
28 day break 12/30/2021
Set 1 = 1,720 psi
56 day break 01/27/2022
Set 1 = 1,780 psi
90 day break 03/2/2022
Set 1 = 1,780 psi
25 1/19/2022
1-P/A.10 Low roof media
center
2-P/A.12 Lowroof media
center
3-A5/W Foundation plan
A
Roney Nakhoul Cohesion/Adhesion of SFRM Applied to Structural Members failure: Fireproofing material is not adhering to the
glue. Noted that material was wet to touch and 2 samples taken Y PMA 2/21/2022
Fireproofing material was given more
time to dry, plus warmer weather during
this dates testing resulted with
the above tests. Cohesion adhesion
values exceed requirements by project
specs .
26 11/16/2021 Building A : N/b20, A5/S Arsene Ntwali Grout, low break: Design Strength (psi): 3,000 @28 days, Lab Log No.: 17087 (3651)Y PMA
1/19/2021
Page 13 of UNIT
MASONRY 04 2000-
13 Notes: 28-day
compressive
strength indicated,
but not less than
2000 psi
EOR to Advise
7 day break 11/23/2021
Set 1 = 2,300 psi
28 day break 12/14/2021
Set 1 = 2,660 psi
56 day break 01/11/2022
Set 1 = 3,300 psi
Set 1 = 3,330 psi
27 11/18/2021 Building A :T.1/A7 Arsene Ntwali Grout, low break: Design Strength (psi): 3,000 @28 days, Lab Log No.: 17119 (3678)Y PMA
1/19/2021
Page 13 of UNIT
MASONRY 04 2000-
13 Notes: 28-day
compressive
strength indicated,
but not less than
2000 psi
EOR to Advise
7 day break 11/25/2021
Set 1 = 1,830 psi
28 day break 12/16/2021
Set 1 = 2,290 psi
56 day break 01/13/2022
Set 1 = 2,450 psi
90 day break 02/16/2022
Set 1 = 2,660 psi
28 11/18/2021 Building D: T.1/A7 Arsene Ntwali Concrete, low break: Design Strength (psi): 4,000 @28 days, Lab Log No.: 17282 (3681)N PMA
EOR to Advise
7 day break 11/25/2021
Set 1 = 2,060 psi
28 day break 12/16/2021
Set 1 = 2,580 psi
56 day break 01/13/2022
Set 1 = 3,220 psi
90 day break 02/16/2022
Set 1 = 3,350 psi
118 day break 03/16/2022
Set 1 = 3,580 psi
29 11/22/2021 Building A : T.1/A6 Arsene Ntwali Concrete, low break: Design Strength (psi): 3,000 @28 days, Lab Log No.: 17197 (3728)N PMA
EOR to Advise
7 day break 11/29/2021
Set 1 = 1,720 psi
28 day break 12/20/2021
Set 1 = 2,310 psi
56 day break 01/17/2022
Set 1 = 2,370 psi
90 day break 02/20/2022
Set 1 = 2,390 psi
30 12/27/2021 Level 2, L-K.8/b21-b22 Eric Pitman Grout, low break: Design Strength (psi): 2,500 @28 days: Lab Log No.: 17890 (4010)N PMA
EOR to Advise
32 day break 01/28/2022
Set 1 = 1,190 psi
56 day break 02/27/2022
Set 1 = 1,270 psi
90 day break 03/27/2022
Set 1 = 1,840 psi
118 day break 04/24/2022
Set 1 = psi
31 2/9/2022 Grade on Level 1 at Line M.5-
Q, Row a18-Pass a30 Enea Mushi
Floor Levelness measurement did not meet project spec requirements.
3.9 FINISHING FLOORS AND SLABS
Specified overall values of flatness, F(F) 35; and of levelness, F(L) 25; with minimum local values of flatness, F(F)
24; and of levelness, F(L) 17; for slabs-on grade
N PMA EOR to Advise
32 1/12/2022 P.2-B.30 -B-32 Bernard
Connaughton Mortar low break: Design Strength (psi): 1,800 psi @ 28 days: Lab Log No.: 17776 N PMA
EOR to Advise
7 day break 01/19/2022
Set 1 = 1,060 psi
Set 1 = 1,190 psi
Set 1 = 1,250 psi
28 day break 02/09/2021
Set 1 =1,400 psi
56 day break 03/09/2022
Set 1 = 1,580 psi
33 1/11/2022 Gymnasium - East Elevation
at Line P.2-M.3-b33
Bernard
Connaughton Mortar low break: Design Strength (psi): 1,800 psi @ 28 days: Lab Log No.: 17775 N PMA
EOR to Advise
7 day break 01/18/2022
Set 1 = 630 psi
Set 1 = 740 psi
Set 1 = 770 psi
28 day break 02/08/2021
Set 1 = 840 psi
56 day break 03/08/2022
Set 1 = 890 psi
90 day break 04/11/2022
Set 1 = psi
34 1/24/2022 Gymnasium - at Line K/B33 Arsene Ntwali Mortar low break: Design Strength (psi): 1,800 psi @ 28 days: Lab Log No.: 17921 N PMA
EOR to Advise
7 day break 01/31/2022
Set 1 = 1,390 psi
Set 1 = 1,490 psi
Set 1 = 1,610 psi
28 day break 02/21/2021
Set 1 = 1,630 psi
56 day break 03/21/2022
Set 1 = 1,960 psi
Set 1 = 2,100 psi
35 1/21/2022 Gymnasium, Line J.7-b30-
b31, J.7-b25-b29 Arsene Ntwali Mortar low break: Design Strength (psi): 1,800 psi @ 28 days: Lab Log No.: 17913 N PMA
EOR to Advise
7 day break 01/28/2022
Set 1 = 1,270 psi
Set 1 = 1,300 psi
Set 1 = 1,400 psi
28 day break 02/18/2021
Set 1 = 1,630 psi
56 day break 03/18/2022
Set 1 = 2,050 psi
36 3/1/2022 Bldg B section 5 and section
11 Roney Nakhoul
Missing Bands:
Banding missing in several locations at the exterior face; sheathing needs to be removed to fix in the 11
section. Some of the inside bands also missing. This inspector observed that some studs were screwed into the
top track which they should not, as this is a deflection track. Studs at some of the curved walls need securing at
the bottom on both sides; these areas appear in progress
Y PMA 3/9/2022 Observed hex screws being installed for
the bracing in bldg B
37 2/24/2022 P.1/b26-30 Arsene Ntwali Mortar low break: Design Strength (psi): 1,800 psi @ 28 days: Lab Log No.: 18046 (4052)N PMA
EOR to Advise
7 day break 02/11/2022
Set 1 = 1,050 psi
Set 1 = 1,120 psi
Set 1 = 1,220 psi
28 day break 02/18/2021
Set 1 = 1,450 psi
Set 1 = 1,660 psi
Set 1 = 1,810 psi
38 3/30/2022 Building B Roney Nakhoul Work in Progress - Building B cold form metal framing N PMA Reinspection is required
Status: Work-in-Progress
Legend:
Status: Closed
Status: Open
TESTING
INSPECTION
ENGINEERINGNatick Lab: 12 Tech Circle, Natick, MA 01760
Field Number: 4 Masonry Grout Compression Test
Project Name: Dennis Yarmouth Middle School Permit # : BLD-21-006153
Project No.:5951 Sampled by: Roney Nakhoul Report Date: 03/29/2022
Client: PMA Consultants, LLC
Date of Sampling: 03/01/2022 Lab Log No.: 18445 (4186)
Reviewed by: Edmychael Colon, Lab
Manager
03/29/2022
Date
ASTM Standards Used: Unless noted, material was sampled and tested in accordance with ASTM C172, C1019, C31, C143, C231, C470, C511, C1077,
C1231,C1064, C138 and E4. Compressive strength tests per ASTM C39.
Testing was performed by qualifed personnel in accordance with generally accepted industry practice, material testing consultants procedures and the above reference standards. This report is
applicable only to the items listed herein. The test performed and in this report are not intended to be considered as any guarantee or warranty of suitability for service or fitness of use of itemstested and it should not be relied on as such. The report has been prepared for the exclusive use of the client and any partial or whole reproduction without the consent of the client is prohibited.Pg. 1 of 1
Information provided by Field Technician
Mix #: Spec mix Supplier: CCRM Contractor: Lighthouse
Set: 1 of 1 Truck #: N/A Design Strength (psi): 3,000 @28
days Ticket#: N/A
Sample Material/Shape: ASTM C1019 Compressive Testing of Masonry Grout
(Grout Box)Type of Structure: wall
Location: Onsite
Location for overall pour:
Location when sampled: S/E corner of gymnasium
Concrete Quality Actual Req'ment Actual Req'ment Actual Req'ment
Mix Temperature (ºF):49 50-90 Slump (in.):N/A N/A Unit Wt (#cu ft):N/A
Air Temperature (ºF):35 >40 Air Content (%):N/A N/A Time Sampled:
Aggregate Size (in):N/A N/A Batch Time: Time in Truck:<90 Mins <90 Mins
Information supplied by Laboratory Technician
Date Received: 03/07/2022 Technician that received: MN
Test #Age of
Test (Days)Date Technician Dimensions (inch)X-section Total Load
(lbs)Strength (psi)Width Width Height Area (in²)
A 7 03/08/2022 Max Nabulsi 3.44 3.43 6.15 11.80 43,093 3,650 psi
B 28 03/29/2022 Luis Soto Soldevilla 3.34 3.43 6.08 11.46 63,765 5,570 psi
C 28 03/29/2022 Luis Soto Soldevilla 3.32 3.43 6.14 11.39 64,686 5,680 psi
D 28 03/29/2022 Luis Soto Soldevilla 3.34 3.44 6.06 11.49 59,752 5,200 psi
MEETS DESIGN STRENGTH
28 Day Avg.:5480
Remarks: Temp Air & Temp Mix, was below specified requirement.
TESTING
INSPECTION
ENGINEERINGNatick Lab: 12 Tech Circle, Natick, MA 01760
Field Number: 6 Masonry Mortar Compression Test
Project Name: Dennis Yarmouth Middle School Permit # : BLD-21-006153
Project No.:5951 Sampled by: Roney Nakhoul Report Date: 03/30/2022
Client: PMA Consultants, LLC
Date of Sampling: 03/02/2022 Lab Log No.: 18437 (4187)
Reviewed by: Edmychael Colon, Lab
Manager
03/30/2022
Date
ASTM Standards Used: Unless noted, material was sampled and tested in accordance with ASTM C172, C1019, C31, C143, C231, C470, C511, C1077,
C1231,C1064, C138 and E4. Compressive strength tests per ASTM C39.
Testing was performed by qualifed personnel in accordance with generally accepted industry practice, material testing consultants procedures and the above reference standards. This report is
applicable only to the items listed herein. The test performed and in this report are not intended to be considered as any guarantee or warranty of suitability for service or fitness of use of itemstested and it should not be relied on as such. The report has been prepared for the exclusive use of the client and any partial or whole reproduction without the consent of the client is prohibited.Pg. 1 of 1
Information provided by Field Technician
Mix #: Type S Supplier: Spec Mix Contractor: Lighthouse
Set: 1 of 1 Truck #: N/A Design Strength (psi): 1,800 @28
days Ticket#: N/A
Sample Material/Shape: ASTM C780 A7.6 Compressive Testing of Masonry
Mortar (2x2)Type of Structure: wall
Location: Onsite
Location for overall pour:
Location when sampled: West wall of the gymnasium B24/P.1-K
Concrete Quality Actual Req'ment Actual Req'ment Actual Req'ment
Mix Temperature (ºF):47 50-90 Slump (in.):N/A N/A Unit Wt (#cu ft):N/A
Air Temperature (ºF):45 >40 Air Content (%):N/A N/A Time Sampled:11:15 AM
Aggregate Size (in):N/A N/A Batch Time:11:00 AM Time in Truck:15
minutes <90 Mins
Information supplied by Laboratory Technician
Date Received: 03/07/2022 Technician that received: MN
Test #Age of
Test (Days)Date Technician Dimensions (inch)X-section Total Load
(lbs)Strength (psi)Width Width Height Area (in²)
A 7 03/09/2022 Luis Soto Soldevilla 2.00 2.00 2.01 4.00 6,977 1,740 psi
B 7 03/09/2022 Luis Soto Soldevilla 1.99 2.00 2.03 3.98 6,948 1,750 psi
C 7 03/09/2022 Luis Soto Soldevilla 1.99 2.00 2.04 3.98 6,977 1,750 psi
D 28 03/30/2022 Luis Soto Soldevilla 1.99 2.01 2.04 4.00 11,203 2,800 psi
E 28 03/30/2022 Luis Soto Soldevilla 2.00 2.00 2.06 4.00 9,434 2,360 psi
F 28 03/30/2022 Luis Soto Soldevilla 1.99 2.00 2.03 3.98 10,585 2,660 psi
MEETS DESIGN STRENGTH
28 Day Avg.:2610
Remarks: Temp Mix was below specified requirement.
TESTING
INSPECTION
ENGINEERINGNatick Lab: 12 Tech Circle, Natick, MA 01760
Field Number: 6 Masonry Mortar Compression Test
Project Name: Dennis Yarmouth Middle School Permit # : BLD-21-006153
Project No.:5951 Sampled by: Roney Nakhoul Report Date: 03/29/2022
Client: PMA Consultants, LLC
Date of Sampling: 03/22/2022 Lab Log No.: 18722 (4282)
Reviewed by: Edmychael Colon, Lab
Manager
03/29/2022
Date
ASTM Standards Used: Unless noted, material was sampled and tested in accordance with ASTM C172, C1019, C31, C143, C231, C470, C511, C1077,
C1231,C1064, C138 and E4. Compressive strength tests per ASTM C39.
Testing was performed by qualifed personnel in accordance with generally accepted industry practice, material testing consultants procedures and the above reference standards. This report is
applicable only to the items listed herein. The test performed and in this report are not intended to be considered as any guarantee or warranty of suitability for service or fitness of use of itemstested and it should not be relied on as such. The report has been prepared for the exclusive use of the client and any partial or whole reproduction without the consent of the client is prohibited.Pg. 1 of 1
Information provided by Field Technician
Mix #: Type N Supplier: Spec Mix Contractor: Lighthouse
Set: 1 of 1 Truck #: N/A Design Strength (psi): 750 @28
days Ticket#: N/A
Sample Material/Shape: ASTM C780 A7.6 Compressive Testing of Masonry
Mortar (2x2)Type of Structure: wall
Location: Onsite
Location for overall pour:
Location when sampled: Blg D. North Elevation
Concrete Quality Actual Req'ment Actual Req'ment Actual Req'ment
Mix Temperature (ºF):62 50-90 Slump (in.):N/A N/A Unit Wt (#cu ft):N/A
Air Temperature (ºF):47 >40 Air Content (%):N/A N/A Time Sampled:9:45 AM
Aggregate Size (in):N/A N/A Batch Time:9:30 AM Time in Truck:15
minutes <90 Mins
Information supplied by Laboratory Technician
Date Received: 03/28/2022 Technician that received: MN
Test #Age of
Test (Days)Date Technician Dimensions (inch)X-section Total Load
(lbs)Strength (psi)Width Width Height Area (in²)
A 7 03/29/2022 Luis Soto Soldevilla 1.99 1.99 2.03 3.96 4,215 1,060 psi
B 7 03/29/2022 Luis Soto Soldevilla 1.99 1.99 2.05 3.96 4,304 1,090 psi
C 7 03/29/2022 Luis Soto Soldevilla 1.99 1.99 2.02 3.96 4,227 1,070 psi
D 28 04/19/2022
E 28 04/19/2022
F 28 04/19/2022
7 Day Avg.:1070
Remarks: Received Sample Condition: Acceptable and/or Satisfactory
TESTING
INSPECTION
ENGINEERINGNatick Lab: 12 Tech Circle, Natick, MA 01760
Field Number: 25 Laboratory Compression Test (4x8)
Project Name: Dennis Yarmouth Middle School Permit # : BLD-21-006153
Project No.:5951 Sampled by: Roney Nakhoul Report Date: 03/29/2022
Client: PMA Consultants, LLC
Date of Sampling: 03/22/2022 Lab Log No.: 18725
Reviewed by: Edmychael Colon, Lab
Manager
03/29/2022
Date
ASTM Standards Used: Unless noted, material was sampled and tested in accordance with ASTM C172, C31, C143, C231, C470, C511, C1077,
C1231,C1064, C138 and E4. Compressive strength tests per ASTM C39.
Testing was performed by qualifed personnel in accordance with generally accepted industry practice, material testing consultants procedures and the above reference standards. This report is
applicable only to the items listed herein. The test performed and in this report are not intended to be considered as any guarantee or warranty of suitability for service or fitness of use of itemstested and it should not be relied on as such. The report has been prepared for the exclusive use of the client and any partial or whole reproduction without the consent of the client is prohibited.Pg. 1 of 5
Information provided by Field Technician
Mix #: 3000DNA Supplier: Cape Cod Ready Mix Inc.Contractor: Silverback
Set: 1 of 5 Truck #: 55 Design Strength (psi): 3,000
@28 days Ticket#: 23650
Sample Material/Shape: ASTM C39 Compressive Strength of Cylindrical
Concrete Specimens (4x8)Type of Structure: Slab on Grade
Location: Onsite
Location for overall pour: Level 1 Slab on Grade at M.6-K/b1-b12
Location when sampled: b12.3/P
Concrete Quality Actual Req'ment Actual Req'ment Actual Req'ment
Mix Temperature (ºF):76 50-90 Slump or Spread (in.):7.5 5-9 Unit Wt (#cu ft):147.6 145
Air Temperature (ºF):47 >40 Air Content (%):1.8 0-3 Time Sampled:7:15 AM
Aggregate Size (in):3/4 N/A Batch Time:6:14 AM Time in Truck:61 minutes <90 Mins
Information supplied by Laboratory Technician
Date Received: 03/28/2022 Technician that received: MN
Test #
Age of
Test
(Days)
Date Technician Diameter Length Area (in²)Cure Loc Ultimate Load
(lbs)
Compressive
Strength (psi)
Type of
Fracture
A 7 03/29/2022 Luis Soto Soldevilla 4.00 8.00 12.57 Lab 37,206 2,960 psi Type 2
B 28 04/19/2022 4.00 8.00 12.57 Lab
C 28 04/19/2022 4.00 8.00 12.57 Lab
D 28 04/19/2022 4.00 8.00 12.57 Lab
E H H 4.00 8.00 12.57 Lab
7 Day Avg.:2,960 psi
Remarks: Received Sample Condition: Acceptable and/or Satisfactory
TESTING
INSPECTION
ENGINEERINGNatick Lab: 12 Tech Circle, Natick, MA 01760
Field Number: 25 Laboratory Compression Test (4x8)
Project Name: Dennis Yarmouth Middle School Permit # : BLD-21-006153
Project No.:5951 Sampled by: Roney Nakhoul Report Date: 03/29/2022
Client: PMA Consultants, LLC
Date of Sampling: 03/22/2022 Lab Log No.: 18725
Reviewed by: Edmychael Colon, Lab
Manager
03/29/2022
Date
ASTM Standards Used: Unless noted, material was sampled and tested in accordance with ASTM C172, C31, C143, C231, C470, C511, C1077,
C1231,C1064, C138 and E4. Compressive strength tests per ASTM C39.
Testing was performed by qualifed personnel in accordance with generally accepted industry practice, material testing consultants procedures and the above reference standards. This report is
applicable only to the items listed herein. The test performed and in this report are not intended to be considered as any guarantee or warranty of suitability for service or fitness of use of itemstested and it should not be relied on as such. The report has been prepared for the exclusive use of the client and any partial or whole reproduction without the consent of the client is prohibited.Pg. 2 of 5
Information provided by Field Technician
Mix #: 3000DNA Supplier: Cape Cod Ready Mix Inc.Contractor: Silverback
Set: 2 of 5 Truck #: 51 Design Strength (psi): 3,000
@28 days Ticket#: 23654
Sample Material/Shape: ASTM C39 Compressive Strength of Cylindrical
Concrete Specimens (4x8)Type of Structure: Slab on Grade
Location: Onsite
Location for overall pour: Level 1 Slab on Grade at M.6-K/b1-b12
Location when sampled: b12.3/T
Concrete Quality Actual Req'ment Actual Req'ment Actual Req'ment
Mix Temperature (ºF):74 50-90 Slump or Spread (in.):7.5 5-9 Unit Wt (#cu ft):148.0 145
Air Temperature (ºF):47 >40 Air Content (%):1.9 0-3 Time Sampled:7:50 AM
Aggregate Size (in):3/4 N/A Batch Time:6:59 AM Time in Truck:51 minutes <90 Mins
Information supplied by Laboratory Technician
Date Received: 03/28/2022 Technician that received: MN
Test #
Age of
Test
(Days)
Date Technician Diameter Length Area (in²)Cure Loc Ultimate Load
(lbs)
Compressive
Strength (psi)
Type of
Fracture
A 7 03/29/2022 Luis Soto Soldevilla 4.00 8.00 12.57 Lab 51,124 4,070 psi Type 3
B 28 04/19/2022 4.00 8.00 12.57 Lab
C 28 04/19/2022 4.00 8.00 12.57 Lab
D 28 04/19/2022 4.00 8.00 12.57 Lab
E H H 4.00 8.00 12.57 Lab
7 Day Avg.:4,070 psi
Remarks:
TESTING
INSPECTION
ENGINEERINGNatick Lab: 12 Tech Circle, Natick, MA 01760
Field Number: 25 Laboratory Compression Test (4x8)
Project Name: Dennis Yarmouth Middle School Permit # : BLD-21-006153
Project No.:5951 Sampled by: Roney Nakhoul Report Date: 03/29/2022
Client: PMA Consultants, LLC
Date of Sampling: 03/22/2022 Lab Log No.: 18725
Reviewed by: Edmychael Colon, Lab
Manager
03/29/2022
Date
ASTM Standards Used: Unless noted, material was sampled and tested in accordance with ASTM C172, C31, C143, C231, C470, C511, C1077,
C1231,C1064, C138 and E4. Compressive strength tests per ASTM C39.
Testing was performed by qualifed personnel in accordance with generally accepted industry practice, material testing consultants procedures and the above reference standards. This report is
applicable only to the items listed herein. The test performed and in this report are not intended to be considered as any guarantee or warranty of suitability for service or fitness of use of itemstested and it should not be relied on as such. The report has been prepared for the exclusive use of the client and any partial or whole reproduction without the consent of the client is prohibited.Pg. 3 of 5
Information provided by Field Technician
Mix #: 3000DNA Supplier: Cape Cod Ready Mix Inc.Contractor: Silverback
Set: 3 of 5 Truck #: 55 Design Strength (psi): 3,000
@28 days Ticket#: 34055
Sample Material/Shape: ASTM C39 Compressive Strength of Cylindrical
Concrete Specimens (4x8)Type of Structure: Slab on Grade
Location: Onsite
Location for overall pour: Level 1 Slab on Grade at M.6-K/b1-b12
Location when sampled: b6/K.5
Concrete Quality Actual Req'ment Actual Req'ment Actual Req'ment
Mix Temperature (ºF):74 50-90 Slump or Spread (in.):7.0 5-9 Unit Wt (#cu ft):147.8 145
Air Temperature (ºF):47 >40 Air Content (%):2.1 0-3 Time Sampled:8:50 AM
Aggregate Size (in):3/4 N/A Batch Time:8:21 AM Time in Truck:29 minutes <90 Mins
Information supplied by Laboratory Technician
Date Received: 03/28/2022 Technician that received: MN
Test #
Age of
Test
(Days)
Date Technician Diameter Length Area (in²)Cure Loc Ultimate Load
(lbs)
Compressive
Strength (psi)
Type of
Fracture
A 7 03/29/2022 Luis Soto Soldevilla 4.00 8.00 12.57 Lab 47,974 3,820 psi Type 2
B 28 04/19/2022 4.00 8.00 12.57 Lab
C 28 04/19/2022 4.00 8.00 12.57 Lab
D 28 04/19/2022 4.00 8.00 12.57 Lab
E H H 4.00 8.00 12.57 Lab
7 Day Avg.:3,820 psi
Remarks:
TESTING
INSPECTION
ENGINEERINGNatick Lab: 12 Tech Circle, Natick, MA 01760
Field Number: 25 Laboratory Compression Test (4x8)
Project Name: Dennis Yarmouth Middle School Permit # : BLD-21-006153
Project No.:5951 Sampled by: Roney Nakhoul Report Date: 03/29/2022
Client: PMA Consultants, LLC
Date of Sampling: 03/22/2022 Lab Log No.: 18725
Reviewed by: Edmychael Colon, Lab
Manager
03/29/2022
Date
ASTM Standards Used: Unless noted, material was sampled and tested in accordance with ASTM C172, C31, C143, C231, C470, C511, C1077,
C1231,C1064, C138 and E4. Compressive strength tests per ASTM C39.
Testing was performed by qualifed personnel in accordance with generally accepted industry practice, material testing consultants procedures and the above reference standards. This report is
applicable only to the items listed herein. The test performed and in this report are not intended to be considered as any guarantee or warranty of suitability for service or fitness of use of itemstested and it should not be relied on as such. The report has been prepared for the exclusive use of the client and any partial or whole reproduction without the consent of the client is prohibited.Pg. 4 of 5
Information provided by Field Technician
Mix #: 3000DNA Supplier: Cape Cod Ready Mix Inc.Contractor: Silverback
Set: 4 of 5 Truck #: 62 Design Strength (psi): 3,000
@28 days Ticket#: 34058
Sample Material/Shape: ASTM C39 Compressive Strength of Cylindrical
Concrete Specimens (4x8)Type of Structure: Slab on Grade
Location: Onsite
Location for overall pour: Level 1 Slab on Grade at M.6-K/b1-b12
Location when sampled: b3.5/K.8
Concrete Quality Actual Req'ment Actual Req'ment Actual Req'ment
Mix Temperature (ºF):72 50-90 Slump or Spread (in.):7.25 5-9 Unit Wt (#cu ft):147.4 145
Air Temperature (ºF):47 >40 Air Content (%):2.1 0-3 Time Sampled:9:45 AM
Aggregate Size (in):3/4 N/A Batch Time:8:52 AM Time in Truck:53 minutes <90 Mins
Information supplied by Laboratory Technician
Date Received: 03/28/2022 Technician that received: MN
Test #
Age of
Test
(Days)
Date Technician Diameter Length Area (in²)Cure Loc Ultimate Load
(lbs)
Compressive
Strength (psi)
Type of
Fracture
A 7 03/29/2022 Luis Soto Soldevilla 4.00 8.00 12.57 Lab 48,660 3,870 psi Type 5
B 28 04/19/2022 4.00 8.00 12.57 Lab
C 28 04/19/2022 4.00 8.00 12.57 Lab
D 28 04/19/2022 4.00 8.00 12.57 Lab
E H H 4.00 8.00 12.57 Lab
7 Day Avg.:3,870 psi
Remarks:
TESTING
INSPECTION
ENGINEERINGNatick Lab: 12 Tech Circle, Natick, MA 01760
Field Number: 25 Laboratory Compression Test (4x8)
Project Name: Dennis Yarmouth Middle School Permit # : BLD-21-006153
Project No.:5951 Sampled by: Roney Nakhoul Report Date: 03/29/2022
Client: PMA Consultants, LLC
Date of Sampling: 03/22/2022 Lab Log No.: 18725
Reviewed by: Edmychael Colon, Lab
Manager
03/29/2022
Date
ASTM Standards Used: Unless noted, material was sampled and tested in accordance with ASTM C172, C31, C143, C231, C470, C511, C1077,
C1231,C1064, C138 and E4. Compressive strength tests per ASTM C39.
Testing was performed by qualifed personnel in accordance with generally accepted industry practice, material testing consultants procedures and the above reference standards. This report is
applicable only to the items listed herein. The test performed and in this report are not intended to be considered as any guarantee or warranty of suitability for service or fitness of use of itemstested and it should not be relied on as such. The report has been prepared for the exclusive use of the client and any partial or whole reproduction without the consent of the client is prohibited.Pg. 5 of 5
Information provided by Field Technician
Mix #: 3000DNA Supplier: Cape Cod Ready Mix Inc.Contractor: Silverback
Set: 5 of 5 Truck #: 75 Design Strength (psi): 3,000
@28 days Ticket#: 34064
Sample Material/Shape: ASTM C39 Compressive Strength of Cylindrical
Concrete Specimens (4x8)Type of Structure: Slab on Grade
Location: Onsite
Location for overall pour: Level 1 Slab on Grade at M.6-K/b1-b12
Location when sampled: b2/L.9
Concrete Quality Actual Req'ment Actual Req'ment Actual Req'ment
Mix Temperature (ºF):73 50-90 Slump or Spread (in.):7.50 5-9 Unit Wt (#cu ft):148.1 145
Air Temperature (ºF):47 >40 Air Content (%):2 0-3 Time Sampled:10:45 AM
Aggregate Size (in):3/4 N/A Batch Time:9:57 AM Time in Truck:48 minutes <90 Mins
Information supplied by Laboratory Technician
Date Received: 03/28/2022 Technician that received: MN
Test #
Age of
Test
(Days)
Date Technician Diameter Length Area (in²)Cure Loc Ultimate Load
(lbs)
Compressive
Strength (psi)
Type of
Fracture
A 7 03/29/2022 Luis Soto Soldevilla 4.00 8.00 12.57 Lab 44,906 3,570 psi Type 5
B 28 04/19/2022 4.00 8.00 12.57 Lab
C 28 04/19/2022 4.00 8.00 12.57 Lab
D 28 04/19/2022 4.00 8.00 12.57 Lab
E H H 4.00 8.00 12.57 Lab
7 Day Avg.:3,570 psi
Remarks: