ARCHITECT’S SITE OBSERVATION REPORT
DATE OF VISIT: 03/17/2022 PROJECT: Dennis Yarmouth Intermediate
Middle School
286 Station Avenue
South Yarmouth, MA 02664
DATE OF ISSUE: 04/20/2022 PROJECT NO: 71011
WEATHER
CONDITIONS:
overcast, high 40s ARCHITECT: Perkins Eastman, DPC
20 Ashburton Street
8th floor
Boston, MA
The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit.
WORK IN PROGRESS:
1) Exterior panel girts and thermafiber at 2nd floor (D and C)
2) AVB installation and prep for window installation; stripping in of windows and Curtain wall
3) Curtain wall installation
4) Brick masonry at Area D
5) CMU at gymnasium
6) Parapet framing and exterior sheathing (area B)
7) Interior partition framing
8) Interior drywall
9) Main stair plinth construction
10) MEP rough-in
11) Fire protection
12) SFRM installation
FIELD OBSERVATIONS:
PE visited the site on Thursday 03-17, to review ongoing progress.
1. Colony is continuing with Interior partition detailing (soffits and portals etc) in Area C, and has started installing
Sheetrock at area D on level 2 (see photo). Layout and basic wall framing is progressing on both floors of Area
B “central commons” / admin area (see photos on pages 2 and 3).
2. HVAC and electrical rough-in is ongoing in Areas A and B. Gas piping installation is ongoing.
3. Plumbing work is ongoing at the core bathrooms in C.
4. At the time of observation, Silverback was prepping for upcoming slab pours in Area A (i.e. the
cafetorium/cafetorium stage, auditorium/auditorium stage, and auditorium lobby). CB says that the next SOG
pour is scheduled for Tuesday 3-22 (see photo on page 3).
5. Sprinkler piping installation by Rustic is ongoing.
6. SFRM installation is now in process at Area A.
7. Moving to exterior envelope, Colony recently framed the main canopy “prow” at Area B and was in the process of
sheathing area B (see photo on page 3).
8. Lymo is continuing to install clips and mineral wool for the GFRC panels at the academic wings; they have started
on Area C and are almost finished with Area D (see photo on page 2).
9. Curtain Wall is going in at links between Area C and Area D.
10. At the time of observation, United had commenced geofoam installation for the stair landing plinth at the Area B
atrium (see photo).
11. Brick masonry work is ongoing at Area D, working its way around the north face of the building.
12. Lighthouse is in the process of removing the tenting at the gym, and ground-faced CMU installation at the gym
west wall is about 65% complete (about 14 courses above level 2). (see photo on page 2).
REPORT BY: ABH Page 2 of 3
DISCREPANCIES, SPECIAL INSTRUCTIONS
31701. Masonry detail questions: CB raised a question about how the brick and the ACM panels resolve at the
inside corners (such as bump-outs at D north), and the question was resolved. (this is being closed).
31702. Gym truss misalignment: Due to an apparent installation error, there is a slight misalignment in one of the
bottom chords in the N-S direction (at col line K.8). This problem was submitted as RFI 325, and Girard
responded on 3-14. Norgate or United to address the prescribed repair to straighten the bottom chord.
31703. CW corner at gym: The CW at the two east corners is slightly too small in plan for the masonry opening.
CB verified that the opening was built correctly. The CW will need to be altered in order to fit properly.
Prior Items
31001. Prep for AVB at gym. There were a number of discussions about voids in the outside-side of the east wall
(see photo below). PE and CB agreed that large voids in the masonry will be filled with CMU, and minor
voids at the columns will be bridged with sheathing prior to the application of the fluid applied membrane.
Update: This question was submitted as RFI no. 326 on 3-14 and answered. This item is being closed,
31003. (from 03 10 site report) ‘As-builts’ for outrigger position – Area A. PE asked CB to check the stud
locations for the sunshade outriggers at Area A south wall so that if there is a systematic “offset” in the as
built outrigger placement (as there was in some other areas) the window R O locations can be adjusted
accordingly. Still open
31004. (from 03 10 site report) Exposed HSS support brackets in gym (see photo on page 3). CB asked about
masking this condition; PE proposed grinding the steel down as much as possible and infilling voids with
pieces of GFCMU. Still open
22402. (from 03 03 site report) Caulk color PE reviewed caulk color options at mockup and gave direction
Update:. Still open
11301. (From 01-13 site report): Guard rail welds at D & C stairs - United still needs to grind welds for guards at
academic stairs (see photo). still open
21603. (From the 12-16 site report) OF scuppers. Harold bros has installed the originally-specified ‘lamb’s tounge’
scuppers at the overflow outlets high on the building, in spite of revised (B14) detail, which called for
changing to a square one. Update:. Still open.
SITE PHOTOS
GIRT INSTALLATION – AREA C CLASSROOM SHEETROCK -AREA D GYM WEST WALL FROM ATRIUM
REPORT BY: ABH Page 2 of 3
ATRIUM PROGRESS INCLUDING STAIR PLINTH GEOFOAM – AREA B
ATRIUM PROGRESS INCLUDING STAIR PLINTH GEOFOAM – AREA B
PREP FOR SOG POUR – AREA