Architect: Perkins Eastman DPC
Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File
ARCHITECT’S SITE OBSERVATION REPORT
DATE OF VISIT: 03/31/2022 PROJECT: Dennis Yarmouth Intermediate
Middle School
286 Station Avenue
South Yarmouth, MA 02664
DATE OF ISSUE: 04/19/2022 PROJECT NO: 71011
WEATHER
CONDITIONS:
overcast, low 50s ARCHITECT: Perkins Eastman, DPC
20 Ashburton Street
8th floor
Boston, MA
The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit.
WORK IN PROGRESS:
1) Interior partition framing, drywall
2) Painting
3) MEP rough-in
4) Fire protection
5) Misc. metals work (seismic clips)
6) Elevator installation
7) K 13 installation at open ceiling areas
8) Concrete SOG installation
9) Exterior framing and sheathing at A
10) AVB installation and prep for window installation; stripping-in of windows and Curtain wall
11) Curtain wall installation
12) GFRC panel girt/mineral wool installation.
13) Brick masonry and CMU
14) roofing
15) Site work at the upper sports fields
FIELD OBSERVATIONS:
PE visited the site on Thursday 03-31, to review ongoing progress.
1. Prime painting is just commencing at Area D
2. The Colony crew is continuing with detailing work at Area C (soffits and portals etc.). Interior partition framing is
ongoing at Areas A and B; At the time of observation Colony was framing the tiers for the upper auditorium in
area A and installing sheetrock in area B (see photo on page 3).
3. MEP rough-in is ongoing at Area B; Arden started hanging ductwork at Area B; above-ground rough in is just
commencing in Area A.
4. SFRM is ongoing in Area B; K-13 installation is ongoing in Area B.
5. Elevator installation is commencing (Area B).
6. Exterior CFMF framing: At the time of observation, Colony was in the process of framing at exterior walls Area A.
7. Brick masonry work is ongoing at Area D, working its way around the north face of the building.
8. CMU work at the gym is ongoing at the lower north gym area; Beacon has commenced prepping the CMU
envelope for application of spray applied AVB.
9. Lambrian (CW and window) is installing curtain wall at the Area C-D “link.” (see photo on page 3).
10. United Steel is beginning to install the seismic clips for the gym CMU walls.
11. The Lymo crew is installing clips and mineral wool for the GFRC panels at the south side and east side of Area D,
at the C-D courtyard (see photo on page 3).
12. Stanley is in the process of installing the high roof at the gymnasium (see photo on page 2).
REPORT BY: ABH Page 2 of 3
13. the concrete for the lower tier of the stair plinth was poured on 3-31 in the AM, and at the time of observation the
Silverback crew was installing the SOG at the lower bowl of the auditorium and at the cafetorium stage (see
photo on page 3), and preparing to install the depressed slab at the kitchen walk-in coolers.
14. Site progress: RBO is mobilized again and is prepping subgrade for the athletic fields.
DISCREPANCIES, SPECIAL INSTRUCTIONS
3311. Missing expansion joint. PE expressed concern to CB about a missing vertical expansion joint at J.7/B24
(2nd floor joint between gym and the rest of area B); and also noted that the first floor joint at the same
location needs to be moved so that it is per Bulletin 29 – Colony to address (see photo below).
3312. Painting questions the O’Byrne painting foreman made some suggestions about painting details, which PE
accepted. This item will be closed
Prior Items
31702. (from 03 17 site report) Gym truss misalignment: Due to an apparent installation error, there is a
slight misalignment in one of the bottom chords in the N-S direction (at col line K.8). This problem was
submitted as RFI 325, and Girard responded on 3-14. Norgate or United to address the prescribed
repair to straighten the bottom chord. Update: This fix is complete and item will be closed
31703. (from 03 17 site report) Curtain wall corner at gym. The CW at the two east corners is slightly too small in
plan for the masonry opening. CB verified that the opening was built correctly. The CW will need to be
altered in order to fit properly.—Update: PE directed CB/ Lambrian to fix this by holding the the jamb joints
to ¾”, englarging the corner box slightly, and pushing the CW in about an inch (in order to minimize the
change at the corner).
31002. (from 03 10 site report) ‘As-builts’ for outrigger position – Area A. Update: CB verified the location of the
outriggers in Area A and advised that they have been installed accurately. This item is being closed.
31003. (from 03 10 site report) Exposed HSS support brackets in gym (see photo on page 3). CB asked about
masking this condition; PE proposed grinding the steel down as much as possible and infilling voids with
pieces of GFCMU. still open
22402. (from 03 03 site report) Caulk color Update: still open
11301. (From 01-13 site report): Guard rail welds at D & C stairs - United still needs to grind welds for guards at
academic stairs (see photo). still open
21603. (From the 12-16 site report) OF scuppers. Harold bros has installed the originally-specified ‘lamb’s tounge’
scuppers at the overflow outlets high on the building, in spite of revised (B14) detail, which called for
changing to a square one. Update:. Harold bros submitted a modest COR to switch these out; this item is
being closed.
SITE PHOTOS
ROOFING WORK – GYM/AREA B NEEDED EXP. JOINT @ J.7/B.24 ATRIUM PROGRESS – AREA B
REPORT BY: ABH Page 3 of 3
PROGRESS AT MEDIA CENTER – WEST (AREA B)
SOG POUR AT LOWER AUDITORIUM FLOOR (AREA A)
BRICK MASONRY PROGRESS BY LIGHTHOUSE (AREA D)