Architect: Perkins Eastman DPC
Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File
ARCHITECT’S SITE OBSERVATION REPORT
DATE OF VISIT: 04/14/2022 PROJECT: Dennis Yarmouth Intermediate
Middle School
286 Station Avenue
South Yarmouth, MA 02664
DATE OF ISSUE: 04/26/2022 PROJECT NO: 71011
WEATHER
CONDITIONS:
overcast, 40s ARCHITECT: Perkins Eastman, DPC
20 Ashburton Street
8th floor
Boston, MA
The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit.
WORK IN PROGRESS:
1) Interior partition framing, drywall
2) Painting
3) MEP rough-in
4) Fire protection
5) Elevator installation
6) K 13 installation at open ceiling areas
7) Concrete installation at auditorium and loading dock
8) Main stair plinth installation
9) AVB installation and prep for window installation; stripping in of windows and Curtain wall
10) Curtain wall installation
11) GFRC panel girt installation and insulation
12) Brick masonry and CMU
13) Prep for gym AVB installation at GYM
14) Exterior sheathing at A
15) Site work at the upper sports field
FIELD OBSERVATIONS:
PE visited the site on Thursday 04-14, to review ongoing progress.
1. Sheetrock installation is ongoing at area B and C, and Prime painting is ongoing for walls in Area D
2. At the time of observation Colony’s Interior framing crew was focusing on the music wing in Area A (see photo on
page 4); framing at 2nd floor of B is substantially complete.
3. Colony is installing the wood blocking at the inside face of classroom light shelves
4. Arden has installed the radiant panels in the upper soffits in Area D classrooms.
5. MEP installation at Area D is focused on preparing ceiling plenum areas for ceiling work to begin during the week
of 4-24.
6. Harold Bros. is installing the leader lines for the roof drains at the gymnasium.
7. At the time of observation Silverback recently poured the composite deck for the auditorium stage and the
auditorium upper tiers, and the stair concrete team was setting forms on the lower steps for the main stair plinth
(see photo - page 4).
8. At the time of observation K-13 was being sprayed at the cafetorium in Area A (see photo - page 2)
9. Elevator installation is ongoing (both elevators)
10. United Steel has completed the seismic clips for the gymnasium CMU walls (see photo – page 3).
.
11. Moving to exterior items, Colony is in the process of sheathing at the music room wing, as well as framing the
curtain wall opening at the auditorium main lobby/corridor.
12. Lighthouse has completed the exterior CMU back up wall at the locker room; brick masonry work is ongoing at the
south side of Area D (see photo on page 2).
REPORT BY: ABH Page 2 of 4
13. Preparation for the application of spray applied AVB at the gymnasium is substantially complete.
14. Lambrian is in the process of detailing the curtain wall at the links (Area B-C).
15. The Lymo crew is installing clips and mineral wool for the GFRC panels at the south side of Area C, at the B-C
courtyard. GFRC panels are expected to start going up the week of 4-25.
16. At the time of observation Silverback was installing concrete for the loading dock Area A) (see photo on page 4).
17. Site progress: RBO is excavating drainage trenches for the athletic fields and installing drain pipe.
DISCREPANCIES, SPECIAL INSTRUCTIONS
4141. Poorly plumbed column at A.17/V. CB pointed out that the upper part of the HSS column at A.17/V
(auditorium lobby) impinges on the interior space by more than an inch. PE and the Colony foreman
discussed a solution that would involve furring out with 7/8” furring channels (see photo below).
4142. Accent paint at classroom walls. The O’Bryne foreman approached PE about RFI #343 (re accent color
locations). At O’Byrne’s suggestion, PE directed that the main wall color should carry across the accent wall
above the horizontal reveal. The day after the meeting in the field, PE asked CB to use accent colors
corresponding to the krion around the doorway on the classroom side.
Prior Items
3311. (from 03 31 site report) Missing expansion joint. Update: Colony has addressed the missing expansion
joint as requested on 3-31 (see 4-07 report), but PE additionally requested that Colony tweak the location of
the jog in the wall finish at the gym corner so that it coincides with the south edge of the interior EJ, and to
coordinate radiant panel size with Arden—still open.
3173. (from 03 17 site report) Curtain wall at gym corner. Still open.
31002. (from 03 10 site report) Exposed HSS support brackets in gym.. still open
22402. (from 03 03 site report) Caulk color Update: still waiting for new mock-up color (beige).
11301. (From 01-13 site report): Guard rail welds at D & C stairs - United still needs to grind welds for guards at
academic stairs (see photo). still open
SITE PHOTOS
TILTING LOBBY COLUMN – A.17/V MASONRY PROGRESS - AREA D SE K-13 APPLICATION – AREA A
REPORT BY: ABH Page 3 of 4
SHEETROCK PROGRESS – AREA D 2ND FLOOR
EXTERIOR CLADDING PROGRESS (AREA D WEST)
COMPLETED WEST WALL OF GYM AWAITING CMU CLEANING (AREA B)
REPORT BY: ABH Page 4 of 4
PREPARING FOR FINAL CONCRETE POUR AT ATRIUM MAIN STAIR (AREA B)
CONCRETE POUR IN PROGRESS AT LOADING DOCK (AREA B)
INTERIOR FRAMING PROGRESS AT MUSIC WING (AREA A)