HomeMy WebLinkAboutDYIMS PE Site report 20220414 Architect: Perkins Eastman DPC Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File ARCHITECT’S SITE OBSERVATION REPORT DATE OF VISIT: 04/14/2022 PROJECT: Dennis Yarmouth Intermediate Middle School 286 Station Avenue South Yarmouth, MA 02664 DATE OF ISSUE: 04/26/2022 PROJECT NO: 71011 WEATHER CONDITIONS: overcast, 40s ARCHITECT: Perkins Eastman, DPC 20 Ashburton Street 8th floor Boston, MA The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit. WORK IN PROGRESS: 1) Interior partition framing, drywall 2) Painting 3) MEP rough-in 4) Fire protection 5) Elevator installation 6) K 13 installation at open ceiling areas 7) Concrete installation at auditorium and loading dock 8) Main stair plinth installation 9) AVB installation and prep for window installation; stripping in of windows and Curtain wall 10) Curtain wall installation 11) GFRC panel girt installation and insulation 12) Brick masonry and CMU 13) Prep for gym AVB installation at GYM 14) Exterior sheathing at A 15) Site work at the upper sports field FIELD OBSERVATIONS: PE visited the site on Thursday 04-14, to review ongoing progress. 1. Sheetrock installation is ongoing at area B and C, and Prime painting is ongoing for walls in Area D 2. At the time of observation Colony’s Interior framing crew was focusing on the music wing in Area A (see photo on page 4); framing at 2nd floor of B is substantially complete. 3. Colony is installing the wood blocking at the inside face of classroom light shelves 4. Arden has installed the radiant panels in the upper soffits in Area D classrooms. 5. MEP installation at Area D is focused on preparing ceiling plenum areas for ceiling work to begin during the week of 4-24. 6. Harold Bros. is installing the leader lines for the roof drains at the gymnasium. 7. At the time of observation Silverback recently poured the composite deck for the auditorium stage and the auditorium upper tiers, and the stair concrete team was setting forms on the lower steps for the main stair plinth (see photo - page 4). 8. At the time of observation K-13 was being sprayed at the cafetorium in Area A (see photo - page 2) 9. Elevator installation is ongoing (both elevators) 10. United Steel has completed the seismic clips for the gymnasium CMU walls (see photo – page 3). . 11. Moving to exterior items, Colony is in the process of sheathing at the music room wing, as well as framing the curtain wall opening at the auditorium main lobby/corridor. 12. Lighthouse has completed the exterior CMU back up wall at the locker room; brick masonry work is ongoing at the south side of Area D (see photo on page 2). REPORT BY: ABH Page 2 of 4 13. Preparation for the application of spray applied AVB at the gymnasium is substantially complete. 14. Lambrian is in the process of detailing the curtain wall at the links (Area B-C). 15. The Lymo crew is installing clips and mineral wool for the GFRC panels at the south side of Area C, at the B-C courtyard. GFRC panels are expected to start going up the week of 4-25. 16. At the time of observation Silverback was installing concrete for the loading dock Area A) (see photo on page 4). 17. Site progress: RBO is excavating drainage trenches for the athletic fields and installing drain pipe. DISCREPANCIES, SPECIAL INSTRUCTIONS 4141. Poorly plumbed column at A.17/V. CB pointed out that the upper part of the HSS column at A.17/V (auditorium lobby) impinges on the interior space by more than an inch. PE and the Colony foreman discussed a solution that would involve furring out with 7/8” furring channels (see photo below). 4142. Accent paint at classroom walls. The O’Bryne foreman approached PE about RFI #343 (re accent color locations). At O’Byrne’s suggestion, PE directed that the main wall color should carry across the accent wall above the horizontal reveal. The day after the meeting in the field, PE asked CB to use accent colors corresponding to the krion around the doorway on the classroom side. Prior Items 3311. (from 03 31 site report) Missing expansion joint. Update: Colony has addressed the missing expansion joint as requested on 3-31 (see 4-07 report), but PE additionally requested that Colony tweak the location of the jog in the wall finish at the gym corner so that it coincides with the south edge of the interior EJ, and to coordinate radiant panel size with Arden—still open. 3173. (from 03 17 site report) Curtain wall at gym corner. Still open. 31002. (from 03 10 site report) Exposed HSS support brackets in gym.. still open 22402. (from 03 03 site report) Caulk color Update: still waiting for new mock-up color (beige). 11301. (From 01-13 site report): Guard rail welds at D & C stairs - United still needs to grind welds for guards at academic stairs (see photo). still open SITE PHOTOS TILTING LOBBY COLUMN – A.17/V MASONRY PROGRESS - AREA D SE K-13 APPLICATION – AREA A REPORT BY: ABH Page 3 of 4 SHEETROCK PROGRESS – AREA D 2ND FLOOR EXTERIOR CLADDING PROGRESS (AREA D WEST) COMPLETED WEST WALL OF GYM AWAITING CMU CLEANING (AREA B) REPORT BY: ABH Page 4 of 4 PREPARING FOR FINAL CONCRETE POUR AT ATRIUM MAIN STAIR (AREA B) CONCRETE POUR IN PROGRESS AT LOADING DOCK (AREA B) INTERIOR FRAMING PROGRESS AT MUSIC WING (AREA A)