HomeMy WebLinkAboutSW2022-002 Stormwater Management Permit Application 225 Whites Path Stormwater Management Permit Application Warehouse & Distribution Center Alterations 225 White’s Path Yarmouth, Massachusetts CHA Project Number: 072846 Applicant: Two Twenty Five White’s Path Units Two and Three, LLC 231 Willow Street Yarmouthport, MA 02675 Prepared by: 141 Longwater Drive, Suite 104 Norwell, Massachusetts 02061 Phone: (781) 982-5400 Fax: (781) 982-5490 May, 2022 May 5, 2022 Town of Yarmouth Conservation Commission 1146 Route 28 South Yarmouth, MA 02664 RE:Two Twenty Five White’s Path Units Two and Three LLC 225 White’s Path, Yarmouth, MA Stormwater Management Permit Application Dear Commission Members: On behalf of the Applicant, Two Twenty Five White’s Path Units Two and Three LLC CHA Consulting, Inc. is pleased to submit the enclosed Stormwater Management Permit Application and supporting documents associated with the proposed Alteration to Warehouse and Distribution Center project located at 225 White’s Path. The project purpose is to modernize the existing warehouse/distribution center building and site as described in more detail below. The project site consists of a large single parcel of land containing 17.7 acres. The parcel is located within the Business District, B-3 and Watershed Protection Overlay district. No change in use of the property is proposed. No portion of the project occurs within a FEMA 100-year floodplain (Zone X). A review of the Massachusetts Natural Heritage Endangered Species Program (NHESP) GIS data layer indicate that there are no Estimated/Priority habitats or rare-listed wetland, or upland wildlife or vegetation designated within the project vicinity, including vernal pools. There are no onsite wetland resource areas or offsite wetland resource areas within 100’ of the property, nor other special resource areas including Area of Critical Environmental Concern (ACEC) or Outstanding Resource waters (ORW). The site is improved with an existing single-story steel and masonry building approximately 156,000 square feet in size. The building is subdivided into three (3) condominium units. Unit 1 contains approximately 46,000 square feet and comprises the front portion of the building. Unit 2 contains approximately 42,500 square feet and Unit 3 contains approximately 37,500 square feet comprise the remaining portion of the building. Units 2 and Unit 3 together comprise the project premises, Unit 1 is not part of the proposed project. Access to the site is gained from a single driveway entrance from White’s Path, located in the northwest corner of the site. Paved parking and loading areas are in the westerly portion of the site, adjacent to the centrally located building. The remaining portions of the site consist of naturally wooded and landscaped areas. The proposed project will modernize the interiors of Units 2 and 3 to better serve the warehouse/distribution use, including new van loading area, screening area, and staff support and administrative spaces. Two (2) vehicular ramps are proposed to provide access to interior parking and to facilitate sorting and loading of packaging. No changes to the footprint of the building or to the overall area of the building are proposed. Site improvements proposed include new paved parking for vans, paved areas reserved for trailers and automobile parking. The single driveway access from White’s Path will continue to be used without alteration. Moreover, there are no changes proposed to the existing access and parking/loading facilities from White’s Path to a point approximately 450 feet into the site as this area is generally reserved for Unit 1. The proposed improvements have been positioned on the site to provide considerable natural or landscaped buffers to adjacent properties. In lot trees and perimeter trees are proposed to enhance screening. Existing and new paved surfaces will be striped and site lighting will be installed in conformance with the Town’s requirements for mounting height and intensity. Stormwater management improvements are proposed, incorporating deep sump/hooded catch basins, oil/grit separators, water quality units, and a replacement retention/recharge basin. These best management practices will improve water quality and provide treatment, flood control and groundwater recharge. Refer to the attached Stormwater Report and Project Plans for a detailed description of the stormwater management improvements that are proposed as part of this project. In accordance with Section 145 of the Code of the Town of Yarmouth, the proposed project will require a Stormwater Management Permit as the project will disturb land area equal to or greater than one (1) acre. The project has recently been reviewed by the Town of Yarmouth Site Plan Review Team and comments received are included in this Stormwater Management Permit application. Approval has also been received from the Cape Cod Commission for a Minor Modification of their 1992 Development of Regional Impact Decision. The following is hereby submitted in support of this Stormwater Management Permit Application: 1.Stormwater Management Permit Application dated 4/19/22. 2.Administrative Checklist, Stormwater Management Permit Application. 3.Certified List of Abutters, Abutters Notification and Proof of Delivery of Notification. 4.Civil Site Plan Set entitled “Site Development Plans 225 White’s Path, Yarmouth, MA” prepared; by CHA Consulting, Inc. dated 2/18/22 and last revised 4/19/22 (9 sets). 5.Stormwater Report entitled “Stormwater Report, Warehouse & Distribution Center Alterations, 225 White’s Path, Yarmouth, Massachusetts” prepared by CHA Consulting, Inc. dated April, 2022. 6.Draft Stormwater Pollution Prevention Plan (SWPPP) 7.Checks for $200. And $10. for application fee and legal ad fee, respectively. Please note that enclosed Civil Site Plan Set includes an Erosion and Sediment Control Plan, and the enclosed Stormwater Report includes the Project Narrative, Operation and Maintenance Plan, and Checklist for Stormwater Report. We appreciate your consideration of this Alteration to Warehouse and Distribution Center project, and we look forward to presenting to the Commission at a future public hearing. Please do not hesitate to contact us should any additional materials be needed, or questions arise. Sincerely, Scott F. Arnold, P.E. Senior Engineer Section 2 – Application and Administrative Checklist Yarmouth Conservation Commission • 1146 Route 28 • South Yarmouth, MA 02664-4492 Tel. (508)-398-2231 Ext. 1288 • Fax (508)-398-0836 • TTD# (508) 398-2231 Rev 9/2021 Page 1 of 1 Administrative Checklist Stormwater Management Permit Application General Information: All filings must be made on Town of Yarmouth forms found at www.yarmouth.ma.us/325/Conservation. No new information may be accepted into the Commissioners’ packets within the week before a meeting. The Conservation Commission shall issue a written notice of administrative completeness or deficiencies to an applicant for an application within ten (10) business days of receiving the application. Refer to the meeting and fee schedule. Contact the Conservation Office if you need assistance. Submitting an Application: Has the project been reviewed under Site Plan Review? 9 hardcopies of the following: Completed signed original application (double sided) List of abutters from the most recent certified record of the Yarmouth Assessor’s Office Stormwater Management Site Plan* (folded separately, right side out with title visible) Project Narrative including project description and construction sequence per Section 2.04, and how the project meets the performance standards in Section 2.05 Erosion and Sediment Control Plan* Operation and Maintenance Plan* *(see Stormwater Management Regulations found at www.yarmouth.ma.us/325/Conservation for required information) Site Plan Review comments Checklist for Stormwater Report Proof of delivery of notification to abutters at least 10 days prior to Conservation meeting Pdf copy of signed application, supporting information and plan(s) emailed to kgrant@yarmouth.ma.us Please list project property’s street address in the pdf file name. Filing fee: separate check made payable to “Town of Yarmouth” Legal ad fee: separate check made payable to “Town of Yarmouth” Please list project property’s street address on checks. Refer to Fee Schedule at https://www.yarmouth.ma.us/696/Filing-Forms DEPARTMENT OF CONSERVATION Section 3 – Abutter Notification, Certified List of Abutters Page 1 of 2 Town of Yarmouth Stormwater By-Law Ch. 145 Stormwater Management Permit Application Important: When filling out forms on the computer, use only the tab key to move your cursor - do not use the return key. A. General Information 1. Project Location: 225 White’s Path a. Street Address Yarmouth b. City/Town 02664 c. Zip Code Latitude and Longitude:41.69015° d. Latitude -70.19646° e. Longitude 98 & 99 f. Assessors Map/Plat Number 33C g. Parcel /Lot Number 2. Applicant: Greg a. First Name Bilezikian b. Last Name Two Twenty Five White’s Path Units Two and Three, LLC c. Organization 231 Willow Street d. Street Address Yarmouthport e. City/Town MA f. State 02675 g. Zip Code 781-987-3647 h. Phone Number gbilezikian@4-corners.com j. Email Address 3. Property owner (required if different from applicant): Check if more than one owner a. First Name b. Last Name c. Organization d. Street Address e. City/Town f. State g. Zip Code h. Phone Number j. Email address 4. Representative (if any): Kelly a. First Name Killeen b. Last Name CHA Consulting, Inc, c. Company 141 Longwater Drive Suite 104 d. Street Address Norwell e. City/Town MA f. State 02061 g. Zip Code 781-792-2254 h. Phone Number kkilleen@chacompanies.com j. Email address 5. Total Fee Paid: $210.00 a. Total Fee Paid NOTIFICATION TO ABUTTERS UNDER THE TOWN OF YARMOUTH STORMWATER BY-LAW, CHAPTER 145 In accordance with the second paragraph of the Massachusetts General Laws Chapter 131, Section 40, and Yarmouth By-Law Chapter 145,you are hereby notified of the following: A.The name of the applicant is B. The applicant has filed a Stormwater Management Permit Application with the Yarmouth Conservation Commission, seeking permission to undertake a construction activity, including clearing, grading, excavation or redevelopment, in an area subject to Protection under Town of Yarmouth Stormwater By-Law, Chapter 145. C.The address of the lot where the activity is proposed is D.Proposed work is E.Copies of the Stormwater Management Permit Application may be examined at the Yarmouth Town Hall at the Conservation Commission office between the hours of 9:00 a.m. and 4:00 p.m. Monday thru Friday. For more information, call (508) 398-2231 ext.1288. F.Copies of the Stormwater Management Permit Application may be obtained from either the applicant or applicant’s representative. Applicant’s phone number Or Applicant’s representative’s phone number G.Information regarding the date, time and place of the public hearing may be obtained by calling the Yarmouth Conservation Commission office at (508) 398-2231 ext. 1288 H.Person sending this notification (applicant, representative or other): Name Address Town State Zip Telephone NOTES : Notice of the public hearing, including date, time and place will be published at least five (5) days in advance in a newspaper of general circulation. Notice of the public hearing, including date, time and place will be posted in the Town Hall not less than 48 hours in advance and online at yarmouth.ma.us 98/ 77/ / / MAJEWSKI ROBERT E TR 134 BLUE ROCK RD SOUTH YARMOUTH , MA 02664 98/ 81/ / / COLONIAL GAS COMPANY 40 SYLVAN RD WALTHAM , MA 02451 99/ 33/ C1/ / REARDON REALTY MA INC 123 EAST ST ATTLEBORO , MA 02703 99/ 36/ / / COLE LOUISE TREMBLAY 170 BEACON ST SOUTH YARMOUTH , MA 02664 99/ 35/ / / WATTS DANIEL W WATTS SHAWNA M 164 BEACON ST, SOUTH YARMOUTH , MA 02664 99/ 34/ / / WEAVER FREDERICK WEAVER OLIVE 158 BEACON ST SOUTH YARMOUTH , MA 02664-1852 98/ 57/ / / VAUGHN DIANA LEE 152 BEACON ST, SOUTH YARMOUTH , MA 02664 109/ 3/ / / LOCK UP-CAPE COD LMTD PTNRSHP 800 WEST FRONTAGE ROAD NORTHFIELD , IL 60093-1241 99/ 41/ / / MURDOCK ELIZABETH ANNE C/O ELIZABETH SUYDAM & DAVID SUY 202 BEACON ST SOUTH YARMOUTH , MA 02664 99/ 40/ / / MINARDI ROBERT S 196 BEACON ST SOUTH YARMOUTH , MA 02664 99/ 39/ / / JOSEPH ISAAC JOSEPH MARIA 190 BEACON ST SOUTH YARMOUTH , MA 02664-1852 99/ 38/ / / COOLIDGE JACQUELYN A TR JACQUELYN A COOLIDGE REV TRUST 182 BEACON ST SOUTH YARMOUTH , MA 02664 99/ 37/ / / CHAN TAI M CHANG NANCY 176 BEACON ST, SOUTH YARMOUTH , MA 02664 99/ 33/ C2/ / TWO TWENTY FIVE WHITES PATH LLC C/O TURTLE ROCK LLC 231 WILLOW ST YARMOUTH PORT , MA 02675-1744 99/ 33/ C3/ / TWO TWENTY FIVE WHITES PATH LLC C/O TURTLE ROCK LLC 231 WILLOW ST YARMOUTH PORT , MA 02675-1744 , Section 4 – Site Plan Review Comments SITE PLAN REVIEW COMMENT SHEET Date: April 26, 2022 Map: 33C Applicant: 225 White's Path Units Two and Three, LLC Parcel 98 & 99 Location: 225 White's Path Unit Two and Three Zone: B-3/APD Formal Review Lots: 98 & 99 Persons Present: Amanda Lima Liza Cox Laurie Ruszala Kathy Williams Kurt Raber Carl Lawson Rick Fennucio Capt Kevin Huck Kelly Kiilleen Mark Grylls Scott Arnold Project Summary Proposed project includes modernization of the interior space to better serve the warehousing/distribution use, including an interior van loading space, a new screening area, and staff support spaces. On the exterior, 2 new vehicle access ramps are proposed on the west façade of the building. Site improvements to include new paved area for 25 vans and 20 trailers, replacement of the infiltration basin and addition of water quality unit, landscaping and lighting. Comments Building: Project is located in the B-3 / APD overlay district. Applicant seeks to modify the structure to allow interior parking / loading and an increase to the outdoor parking area. The original ZBA decision, #2856 allowed for F3, trucking and warehousing use of the entire property. Interior parking will likely require compliance with 248 CMR MA State Plumbing Gas Code, section 10.09 regarding floor drains. Parking area upgrades appear to meet the standard of section 301 of the zoning bylaw. Stormwater Management Permit through Con Com will be required. All proposed construction to comply with 780 CMR and appendant codes. Community Development and Planning: As some of the project components (parking for vans and tractor trailers) will be occurring closer to the southern property line (Cape Cod Rail Trail and residential properties), applicant should ensure robust screening and adequate noise attenuation from trucks backing up. Depending upon the thickness of the vegetation to remain, supplemental plantings and or fencing may be required. The minor modification to the Development of Regional Impact (DRI) submitted to the Cape Cod Commission (CCC) included a traffic report showing that the project will not exceed the maximum traffic volumes outlined in the 1992 DRI approval. However, the problem with allowing for traffic increases based on a DRI from 1992 is it doesn't take into consideration the background increases that have happened over time. The analysis back in 1992 may have shown one level of impact based on the proposed project traffic increases, but the impacts will be much more exacerbated based on our increased traffic levels over the past 30 years. Applicant should adhere to the amended DRI requirements including implementing the Transportation Demand Management (TDM) program and any ongoing traffic monitoring requirements and provide the information to the Town. Conservation: Not present. A stormwater permit is required from the Conservation Commission. Design Review: Not present. Engineering: • Drainage o Existing catch basins & piping to be retained shall be cleaned, inspected and repaired as needed. o Tight tank location has close proximity to CB with RIM 36.8. Is it possible to relocate to an area that if it overflew, then it wouldn't go into the drainage? o What is the purpose of the drainage to the southern part of the property? DMH Rim 37.2 heading east. o Provide stormwater O&M plan as part of the stormwater submission to Conservation. ire: Evaluation of fire alarm and sprinkler system by design professional. Carbon monoxide monitoring and \ alarm evaluation. Access and signage for FDC. Early detection requirements for sprinkler activation. Acess and training for fire department personnel. Requirement for interior standpipes. Health: c1-Toxic or Hazardous Materials The project must comply with the Town of Yarmouth, Board of Health Regulation: Handling and Storage of Toxic or Hazardous Materials, which includes, but is not limited to 150% volume secondary containment of all toxic and hazardous materials and annual Board of Health licensing. The site plan review application lists "None" beneath the heading "List of all Hazardous Materials and Quantities". However, please consider the following areas and explain each with regard to toxic and hazardous materials: (1) those that will pass through the facility; (2) those that will be used at the facility and (3) those that will be stored at the facility. Some materials will overlap the aforementioned categories. Since this project is a warehouse/distribution center please list what materials are not acceptable for receiving and shipping. Please also provide a list of all toxic or hazardous materials along with the maximum quantities of each that may be present at any time. Furthermore, if any toxic or hazardous materials are to be handled please explain: (1) the damaged goods assessment, containerization and disposal program and (2) the dangerous goods shipping program. Concerning toxic or hazardous materials that pass through the facility please explain how such materials will (1) be provided secondary containment and (2) be physically protected against threats such as vehicle strikes. The engineered plans depict new proposed indoor vehicle parking and expanded outdoor vehicle parking. With this in mind please explain whether or not vehicle fluids such as, but not limited to engine oil and windshield wash will be stored and used onsite in support of the vehicle fleet. Please state whether or not vehicles used only indoor and onsite such as forklifts will be propane powered. Tight Tank Drawing Number C-103, Site Grading and Drainage Plan, depicts a proposed tight beneath the parking lot. Drawing Number C-602, Details-2, illustrates details of the system. Please explain the purpose of this tank and whether or not it receives water from the indoor vehicle parking area. Note 10 references Industrial Waste Water Holding Tank regulations. If this is the purpose of the tank please revise all references to tight tank with holding tank. Please then revise the design to be in compliance with 314 CMR 18, which includes, but is not limited to secondary containment and leak detection. Septic Please elaborate on the use and occupancy number of the building including the expanded office areas so that compliance with Title 5 septic regulations can be evaluated. Solar Array Please explain whether or not: (1) the solar panels contain any toxic or hazardous material within such as, but limited to heat transfer fluid; (2) the electrical inverters contain any toxic or hazardous materials such as but not limited to antifreeze or dielectric fluid and (3) any battery storage is present and list the involved toxic or hazardous materials. Water: 41,, Proposed 8' Landscape Screening on southern property line is located directly on top of water main. Please relocate V screening a minimum of 10 feet from the water line. Please note the hydrant lateral to the hydrant located at the edge of the south parking area is not shown. This lateral should be located and considered when relocating screening. Read & Received by Applicant(s) Section 5 – Filing Fee Checks