Architect: Perkins Eastman DPC
Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File
ARCHITECT’S SITE OBSERVATION REPORT
DATE OF VISIT: 05/17/2022 PROJECT: Dennis Yarmouth Intermediate Middle School
286 Station Avenue
South Yarmouth, MA 02664
DATE OF ISSUE: 06/09/2022 PROJECT NO: 71011
WEATHER CONDITIONS: Sunny, clear, high 70s ARCHITECT: Perkins Eastman, DPC
20 Ashburton Street
8th floor
Boston, MA
The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit.
WORK IN PROGRESS:
1) Interior partition framing, drywall, painting 2) MEP/FP rough-in 3) Elevator installation 4) Door frame installation
5) Misc metals work 6) Curtain wall installation
7) GFRC panel installation and prep 8) ACM installation 9) RTU installation 10) Brick masonry and CMU
11) Exterior AVB membrane at A and B 12) Site work at the upper sports field FIELD OBSERVATIONS:
PE visited the site on Tuesday 05-17, to review ongoing progress.
Interior Items: 1. Tile contractor is in the process of getting started In Area D (on level 2 in corridor and small toilet rooms) and
mock up was reviewed in the field. (see photos on page 4) 2. In Area D Ceiling installation and painting are ongoing and in various stages of progress.
3. Colony is still taping in Area C; drywall installation is well underway in the central area of B (level 2) 4. Lighthouse has started building the masonry walls at the gym locker room area (Area B).
5. Interior LGMF appears substantially complete at the cafetorium area (area A) 6. MEP rough at Areas A and B is ongoing—most intensively at the 2nd floor of Area B. (see photo on page 3)
7. Soffit framing is getting started in area A. 8. HM Door frames installation is getting started in Area A
9. Staging for MEP rough-in is being set up at the Area A auditorium (to provide a work platform due to sloping slab) 10. United has installed the framing for the light shelves at the music wing.
Exterior items:
11. At the time of observation, PMA’s testing agency (Fenagh) was on site performing air and water tests for selected windows in Area D. (for more information on testing see attached RJK field report). See photos on page 4
12. AVB membrane installation by Beacon is almost complete at Area B and is just getting started in Area A (at south façade of music wing).
13. At the time of observation, the panel cladding contractor (Lymo) was installing ACM at the north façade of Area D as well as GFRC panels at the central courtyard between D and C; ACM panel installation is in progress at the D wing stairs; GFRC is partially complete at the North façade of D ( NW section). (see photos on pages 3 and 4)
REPORT BY: ABH Page 2 of 4
14. Lymo has placed wall ties for girts at the south upper façade of the gym, with wet set screws; at the time of observation they were in the process of installing mineral wool between the girts (see photo in RJK report). 15. Lambrian is installing curtain wall IGUs at the south and east elevations of Area B (see photo on page 4); they are also preparing to install the CW for the main entrances (Area B). 16. Brick progress: two Lighthouse crews are installing brick at the north facade of Area B and another crew is installing the PCC base and the grout fill on the south side of the gym, preparing for the brick masons to move
there next week (see photo in RJK report). 17. Site work: Marguerite is forming up the curb for the concrete tension ring at the upper synthetic turf athletic field. DISCREPANCIES, SPECIAL INSTRUCTIONS New items 5171. PCC base alignment with window jamb. Taller PCC base at gym NE corner (to left of sill) is slightly too wide;
PE discussed with CB/Lighthouse. Lighthouse to address. (see photo on page 3). Prior items 5122. Furring in corridor on west side of CMU fire wall. (from 05 12 site report). PE discussed with CB/Colony, and called attention to the details in Bulletin 35 (issued on 5-10), i.e. 5/A517 and 10/A515. The issue is to allow movement at seismic joint. Still open
5051. (from 05 05 site report) Roof drains over unconditioned space. Two of the roof drains for the main canopy are above unconditioned space (i.e. south of the perimeter wall at level 1). PE and CB discussed how to address this. If possible PE would like to avoid putting an access panel in the exterior soffit in front of the main entrance. Still open. 4281. (from 04 28 site report) Guards at east stairs level 2. In two cases the guards on level 2 are going to be in conflict with the tile; PE + CB to have it addressed by cleanly torching off the last module of the guard (will be
< 4” from finished wall return) Update: United has addressed this at C east level 2; will be kept open 4282. (from 04 28 site report) CMU wall Seismic clips at Custodial Work Area. CB questioned the size of the steel lintel supporting the block above the “EXT 12” overhead door; GAC directed CB to have United install structural seismic clips all along CMU walls at perimeter-- per the standard detail on S-7.00. (this issue is also addressed in RFI #357). As indicated in photo in 5-12 site report, the seismic clips have been installed at this time: ITEM TO BE CLOSED.
4211. (from 04 21 site report) Facia plate at auditorium. Steel fascia at the balcony was installed ½” too low. Still open: team to look at Schluter strip options. 4212. (from 04 21 site report) Steel protrusion at auditorium. Still open. 4141. (from 04 14 site report) Poorly plumbed column at A.17/V. to be furred out with 7/8” furring channels. Still open. 4142. (from 04 14 site report) Accent paint at classroom walls. (soffit issue still open)
31002. (from 03 10 site report) Exposed HSS support brackets in gym. still open. 11301. (From 01-13 site report): Guard rail welds at D & C stairs - United still needs to grind welds for the guards at academic stairs (see photo). Update: PE reviewed this item with United and CB emphasized schedule issue-still open. Attachments:
• RJK site report dated 5-17-2022
• GGD site report dated 5-19-2022
SITE PHOTOS
OVERALL VIEW FROM EAST
REPORT BY: ABH Page 3 of 4
GFRC PANEL INSTALLATION (AREA D) ACM PARAPET INSTALLATION (AREA D) PCC BASE AT GYM CW NE (AREA B)
MASONRY PROGRESS AT AREA B NORTH FAÇADE (C-B COURTYARD)
REPORT BY: ABH Page 4 of 4
WINDOW AIR TEST PREP WINDOW AIR TEST IGU INSTALLATION AT AREA B
FIELD REPORT
RJK discussed the issues with PE, CB, and Beacon on site.
Work Observed
• Air and Vapor Barrier (AVB) Installation
• Window Installation
• Roofing Installation
• Window Testing as Performed by Fenagh Engineering & Testing LLC.
Observations
• On Part A, west, south and east elevations rising walls, Grid Lines A1 - B13, K-W, GCP Perm-A-
Barrier Aluminum AVB was installed by Beacon prior to RJK observations. Primer/adhesive was
applied to the DensGlass Sheathing. The membrane was installed in a water shedding fashion, with a
minimum 2 inch side lap and 10 inch lap around outside corners, as required. (Figure 1)
• On Part A, west and south elevations, Grid Lines V-W, window rough openings were detailed into the
AVB prior to RJK observations. A strip of AVB was installed extending past the jamb and onto the
exterior sheathing. The horizontal field sheets were run into the jambs in water shedding fashion. The
head strip had not yet been installed. (Figure 2)
• On Part B, south and east elevations, Grid Lines A17 - B33, insulated glazing units (IGU) were installed
in the Kawneer 1600IR curtain wall systems, utilizing temporary pressure bars. (Figure 3)
• On Part B, south elevation, Grid Lines A17 - B21, ELBEX HS-222 Silicone Transition Sheet was
installed at curtain wall frames, lapping into the glazing pocket and onto the vertical AVB membrane, in
Project: Q504 - Mattacheese, Dennis-Yarmouth Intermediate
Middle School Report Number: FR-9
Property Address: 276 Station Avenue, South Yarmouth, MA 02664
Client: Perkins Eastman
Date of Site Visit: Tuesday, May 17, 2022
Report Date: Thursday, May 19, 2022
Weather: Sunny 70 °F
Purpose of Visit: Observe Building Enclosure Construction & Window Testing by Fenagh
On-Site During Visit:
Michael Groome - R. J. Kenney Associates, Inc. (RJK)
Andrew Hazelton - Perkins Eastman (PE)
Paul Genereux - Commodore Builders (CB)
Ryan DeRico - CB
John Pope - PMA Consultants (PMA)
Nick Hull - PMA
Ken - Beacon Waterproofing and Restoration Inc (Beacon)
Joe - Peerless Products Inc (PPI)
Eric - Fenagh Engineering & Testing LLC (FET)
James - FET
Report By: Michael Groome
Report Attachments: Detailed Photographs
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number: FR-9
5/19/2022
Report Narrative
G:\RJK\WORD\31811 Q504 Mattacheese DYIMS Yarmouth FR9 Report 5-17-22.docx Page 2 of 9
water shedding fashion between strips at the head, jambs, and sill. Dow Sil 795 Sealant was applied to
the edges of the membrane at the wall and glazing pocket. (Figure 4)
• On Part B, east elevation rising walls, Grid Lines B25 - B33, Hohmann & Bernard Thermal 2-Seal Wing
Nut Anchors are installed through 6-inch John Mansville MinWool-1200. (Figure 5)
• On Part B, south elevation base detail, Grid Lines A17-A30, solid grout fill was installed between
precast concrete bases and extruded polystyrene insulation. (Figure 6)
• On Part B, south elevation base detail, Grid Lines A17 - B33, metal through-wall flashing is installed
over the precast concrete base, fastened utilizing termination bar and screws at 16 inches on-center.
(Figure 7)
• On Part B, south elevation rising walls, Grid Lines B25 - B33, Knight MFI ThermaBracket S-Series
wall ties were installed, fastened utilizing screws, and wet set in GCP Perm-A-Barrier S100 Sealant.
(Figure 8)
• On Part D, north elevation rising wall, Grid Lines D6 - D21, LYMO 2000 ACM panels were installed,
fastened utilizing panel clips to horizontal GreenGirt. (Figure 9)
Window Testing
• On the Part D, north elevation, Grid Lines D3, G1A and G2A windows, testing was conducted by FET
to check for air and water leakage. The water penetration resistance testing was performed in
accordance with ASTM E 1105: “Test Method for Field Determination of Water Penetrations of
Installed Exterior Windows, Skylights, Doors, and Curtain Walls, By Uniform or Cyclical Static Air
Pressure Difference”. Each window was first tested for air leakage and then water leakage. A total of
four tests were conducted on two window units. Air testing was conducted at 3 psf and water testing
was conducted at 6 psf. Both window units pass air and water testing. (Figures 10 - 14)
END OF REPORT
RJK has no contractual responsibility in the design or actual construction of the project and is acting solely in a consultant and/or in an
advisory capacity to the Client. Any and all modifications, changes, recommendations, suggestions, etc., relating to the design and/or
construction, should be forwarded, reviewed, and approved by the designer of record prior to implementation. RJK reserves the right
to change or amend this report as new information becomes available.
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-9
5/19/2022
Appendix A
G:\RJK\WORD\31811 Q504 Mattacheese DYIMS Yarmouth FR9 Report 5-17-22.docx Page 3 of 9
Callouts:
Comments:
0517 026 R. J. Kenney Associates, Inc.
Figure 1 ‐ Sheet-Applied AVB
Callouts:
Comments:
0512 020 R. J. Kenney Associates, Inc.
Figure 2 ‐ AVB Rough Opening Detailing
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-9
5/19/2022
Appendix A
G:\RJK\WORD\31811 Q504 Mattacheese DYIMS Yarmouth FR9 Report 5-17-22.docx Page 4 of 9
Callouts:
Comments:
0517 073 R. J. Kenney Associates, Inc.
Figure 3 ‐ Insulated Glazing Units in Curtain Wall
Callouts:
Comments:
0517 062 R. J. Kenney Associates, Inc.
Figure 4 ‐ Silicone Transition Sheet
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-9
5/19/2022
Appendix A
G:\RJK\WORD\31811 Q504 Mattacheese DYIMS Yarmouth FR9 Report 5-17-22.docx Page 5 of 9
Callouts:
1. Hohmann & Bernard
Thermal 2-Seal Wing Nut
Anchors
Comments:
0517 072 R. J. Kenney Associates, Inc.
Figure 5 ‐ Brick Ties and Wall Insulation
Callouts:
Comments:
0517 047 R. J. Kenney Associates, Inc.
Figure 6 ‐ Solid Grout Fill
1
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-9
5/19/2022
Appendix A
G:\RJK\WORD\31811 Q504 Mattacheese DYIMS Yarmouth FR9 Report 5-17-22.docx Page 6 of 9
Callouts:
Comments:
0517 051 R. J. Kenney Associates, Inc.
Figure 7 ‐ Through-Wall Flashing
Callouts:
1. GCP Perm-A-Barrier
S100 Sealant
Comments:
0517 156 R. J. Kenney Associates, Inc.
Figure 8 ‐ Knight MFI ThermaBracket S-Series
1
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-9
5/19/2022
Appendix A
G:\RJK\WORD\31811 Q504 Mattacheese DYIMS Yarmouth FR9 Report 5-17-22.docx Page 7 of 9
Callouts:
Comments:
0517 016 R. J. Kenney Associates, Inc.
Figure 9 ‐ LYMO 2000 ACM panels
Callouts:
Comments:
0517 145 R. J. Kenney Associates, Inc.
Figure 10 ‐ Exterior Seal for Window Air Test
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-9
5/19/2022
Appendix A
G:\RJK\WORD\31811 Q504 Mattacheese DYIMS Yarmouth FR9 Report 5-17-22.docx Page 8 of 9
Callouts:
Comments:
0517 147 R. J. Kenney Associates, Inc.
Figure 11 ‐ Air Test in Progress
Callouts:
Comments:
0517 160 R. J. Kenney Associates, Inc.
Figure 12 ‐ Spray Rack for Water Testing
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-9
5/19/2022
Appendix A
G:\RJK\WORD\31811 Q504 Mattacheese DYIMS Yarmouth FR9 Report 5-17-22.docx Page 9 of 9
Callouts:
Comments:
0517 177 R. J. Kenney Associates, Inc.
Figure 13 ‐ Testing Set Up
Callouts:
1. Water Column Meter
Comments:
0517 178 R. J. Kenney Associates, Inc.
Figure 14 ‐ Water Testing Inches of Water
1
1
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
5/17/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
1.1
Open Seam Part D Roof
Concrete Slab
that Intesects
Grid Lines D21,
and B.5
04/28/22: Repairs have been
made.
Closed
1.2 Uncovered Polyisocyanurate
Insulation
Part C and Part
D Roofs
04/28/22: Insulation is no
longer stored on site. Closed
1.3
Open Membrane at Penetration Part D Roof,
East Connection
to Part C, Grid
Lines C115 and
D.1
12/15/21: Commodore sent
photos depicting sealing of
membrane at penetration. Closed
2.1
Rough Opening Detailing Part D North and
South Elevations
12/23/21: Per email from GCP
rep Mark Kennedy the on-site
condition will be sealed and
acceptable for the
manufacturer.
Closed
2.2 Insulation Offset Part D Roof 05/17/22: Photos of the
correction will close the item. Open
2.3 Wetted Polyisocyanurate
Insulation
Part D Roof Open
2.4
Upside Down Insulation Part D Roof 05/17/22: Written approval
from the manufacturer that the
orientation is acceptable for the
assembly will close the item,
otherwise correction of
installation methods.
Open
FR-1, 12/15/2021
FR-2, 12/22/2021
G:\RJK\WORD\31812 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 5-17-22 1 of 5
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
5/17/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
3.1 Voids/Fish Mouth in Laps Part B 01/06/22: Repairs observed
during site visit Closed
3.2 Voids in Penetration Detailing Part B 01/06/22: Repairs observed
during site visit Closed
3.3 Tape Unadhered to Column
Footing
Part B 01/06/22: Repairs observed
during site visit.Closed
3.4
Wet Polyisocyanurate
Insulation and Cover Board Is
Installed
Part C 05/12/22: Testing will be
necessary to confirm materials
are dry and without organic
growth.
Open
3.5
Incomplete Night Tie-In Part C 05/17/22: Testing should be
conducted at the location to
ensure no moisture intrusion
occurred at the incomplete tie
in.
Open
4.1 Unadhered/Missing Stego Tape Part B 04/28/22: Per Ryan DeRico
(CB) repairs were made. Closed
4.2 Knife Plates in Rough Opening Part D and Part
C
04/28/22: Knife plates were
relocated.Closed
4.3
Interior Air Barrier Seal at
Windows
Part D 04/28/22: Please provide
approved direction for the issue. Open
4.4
Window Fastening Part D 04/28/22: Please provide
photos of sealant at fasteners. Open
FR-3, 12/28/2021
FR-4, 1/6/2022
G:\RJK\WORD\31812 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 5-17-22 2 of 5
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
5/17/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
4.5
Wet Polyisocyanurate
Insulation and Cover Board Is
Installed
Part C and Part
D Roofs
05/12/22: Testing will be
necessary to confirm materials
are dry and without organic
growth.
Open
4.6 Pitch Pocket Detail Part C 04/28/22: No change.Open
4.7
Uncut Clamping Rings Part C 04/07/22: Multiple clamping
rings still left uncut at Part C.
04/28/22: No change.
Open
4.8
No Clamping Ring Part C 04/07/22: A clamping ring was
installed at the corner
penetration, but two
penetrations were observed
between Part C and Part B
without clamipng rings.
04/28/22: No change.
05/17/22: Clamping rings have
been installed.
Closed
5.1
Equipment and Debris on Roof
Membrane
Part A 04/28/22: Ongoing. 05/12/22"
Item condensed to ITEM 6.3 Closed
5.2
Damage to Below Slab Vapor
Barrier
Part A On Tuesday, March 22, 2022,
photographs of the repairs were
sent by Ryan DiRico (CB)Closed
5.3
Undetailed Penetration in
Below Slab Vapor Barrier
Part A On Tuesday, March 22, 2022,
photographs of the repairs were
sent by Ryan DiRico (CB)Closed
FR-5, 3/21/2022
G:\RJK\WORD\31812 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 5-17-22 3 of 5
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
5/17/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
5.4
Voids in Below Slab Vapor
Barrier Details
Part A On Tuesday, March 22, 2022,
photographs of the repairs were
sent by Ryan DiRico (CB)Closed
5.5
Air Barrier Holes Part D North
Elevation
On Tuesday, March 22, 2022,
photographs of the repairs were
sent by Ryan DiRico (CB)Closed
6.1 Voids in Damproofing From
Damage
Part D and Part
C Open
6.2 AVB Damage Part D and Part
C
04/28/22: Repairs are ongoing. Closed
6.3
Roof Debris Typical 04/28/22: Some large
equipment is on plywood,
although screws, pipes and
other debris are still observed
on the membrane.
Open
6.4
Roof Ponding Part C to Part B 04/28/22: Additional ponding
is observed at the west
breezeway. 05/12/22:
Ponding is continuously
observed at both locations.
Open
6.5
PVC In Contact with Asphalt Part B Penthouse 04/28/22: Membrane is still in
contact, and through wall
flashing is installed.
05/12/22: No change observed.
Open
FR-8, 5/12/2022
FR-7, 4/28/2022
No New Issues
FR-6, 4/7/2022
G:\RJK\WORD\31812 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 5-17-22 4 of 5
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
5/17/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
8.1
Missing AVB Part B, Level 1
Rising Wall to
Parapet
Transition
Open
8.2
Discontinued AVB at Curtain
Wall Column
Part B, East
Elevation Rising
Wall, Grid Lines
M.9-L
Open
8.3
Missing Insulation Behind
Brick
Part B, North
Elevation Rising
Wall, Grid Lines
B32
Open
8.4
Roof Discontinuation Between
Vapor Barrier and PVC
Membrane
Part B,
Gymnasium
Roof, Grid Lines
B24 - B25
Open
No New Issues
FR-9, 5/17/2022
G:\RJK\WORD\31812 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 5-17-22 5 of 5
TEL 508-998-5700 FAX 508-998-0883 email: info@g-g-d.com
MECHANICAL & ELECTRICAL
FIELD OBSERVATION REPORT
FI#80617
J# 685 005 00.00
DATE: May 26, 2022
PROJECT: Dennis Yarmouth Intermediate / Middle School
296 Station Ave
South Yarmouth, MA 02664
CLIENT: Perkins Eastman
DATE OF
OBSERVATION: May 19, 2022
OBSERVED BY: Frank J. Mortell
_______________________
CONTACT: Andrew Hazelton, Senior Associate, Perkins Eastman
DISTRIBUTION: Andrew Hazelton, Senior Associate, Perkins Eastman
Jennifer Gill, Perkins Eastman
John Lam, Perkins Eastman
Matthew S. Woodward, EIT., GGD Engineers, Inc.
Jorge Rosa, EIT, GGD Engineers, Inc.
Cheryl Cieplik, GGD Engineers, Inc.
The following comments are observations noted by our field personnel and may include items of work which
were noted as not meeting the intent of the documents. There may be additional items which also do not
meet the intent of the documents and their lack of notation should not be construed as acceptance of non-
compliant elements of the work. Contractor is to review all documents and comply with all requirements,
whether or not listed below.
Area B Second Floor:
1. CHWS/R and HHWS/R main piping rough installation appears to be complete, branch circuit and
dual temperature piping rough installation is in progress.
2. Boilers B-1 through B-3 are installed on their respective housekeeping pads rough piping
connections are complete. Boilers are presently protected with sheet poly.
3. Pumps P-1 through P-4 are installed on their respective isolation bases. Pump header piping rough
installation is complete.
4. HVAC main trunk and branch duct rough installation in in progress, variable volume terminal unit
installation is in progress. Open ended ducts are sealed with poly.
5. HVAC stored materials are sealed with sheet poly.
6. Electrical power and lighting branch circuit rough installation is in progress.
FI#80617
J# 685 005 00.00
Page 2
7. Electrical raceway rough installation is in progress.
8. Fire alarm rough wiring is in progress.
FI#80617
J# 685 005 00.00
Page 3
Area A First Floor:
9. Main and branch duct rough installation is in progress. Open ended ducts are sealed with sheet
poly.
10. Welded black iron kitchen exhaust duct rough installation appears to be nearly complete, clean out
access doors are not cut in at this time.
11. HVAC stored materials are sealed with sheet poly.
12. HVAC stored variable volume terminal units are palletized and protected with sheet poly.
13. Generator duct bank rough installation appears to be complete.
FI#80617
J# 685 005 00.00
Page 4
Area B First Floor:
14. Main and branch duct rough installation is in progress. Open ended ducts are sealed with sheet
poly.
15. HVAC stored materials are sealed with sheet poly.
16. Stored variable volume terminal units are sealed with sheet poly.
17. CHWS/R and HHWS/R main piping rough installation is in progress and appears to be nearing
completion. Branch circuit piping hangers are installed at this time.
18. Electrical overhead raceway rough installation appears to be complete in gymnasium.
FI#80617
J# 685 005 00.00
Page 5