PROJECT
Tom Lampron Cape Cod Inflatable Park
Project Manager 518 Main Street Route 28
Aquatic Development Group West Yarmouth, MA 02673
13 Green Mountain Drive
Cohoes, NY 12047
C: (518) 257-2067 Prepared By: Matt Ryan
Visit Date: June 27, 2022
Contractor: Robert B. Our Co., Inc.
Time: 9:45am
Weather: Sunny, 74˚F
Attendees: Matt Ryan, Dembling + Dembling Architects, P.C.
Field notes and general observations:
1. Pump House:
a. General building construction approximately 95% complete.
b. Asphalt roof shingle installation is complete.
c. Exterior siding and trim is complete except at entry door and wall louver perimeter.
d. Wall finish and door at Control Room 102, guardrail, and access ladder not completed while
interior electrical and piping work is underway.
e. Interior electrical and plumbing work ongoing.
2. Restroom Building:
a. General building construction approximately 95% complete.
b. Exterior siding, trim, roofing and vinyl privacy screening is complete.
c. Interior tile wall finish and resinous flooring is complete.
d. Toilet partitions are complete.
ARCHITECTS FIELD OBSERVATION REPORT 02
Report Date: June 27, 2022
Page 2 of 3
A R C H I T E C T U R E I N T E R I O R S P L A N N I N G
307 Washington Avenue Albany, New York 12206 USA T: 518•463•8066 F: 518•463•8610 Internet http://www.DDArch.com/
DEMBLING + DEMBLING
A R C H I T E C T S , P.C.
e. Handicap accessibility grab bars are installed.
f. Toilet accessories installed except for mirrors, soap dispensers, and toilet paper dispensers.
g. Lavatory counters are being installed and plumbing connection made.
h. Continuation of toilet room chase wall to underside of roof deck has been started. There
appears to be several small openings between adjacent spaces that need to be sealed.
3. Wave Building:
a. General building construction approximately 95% complete.
b. Asphalt roof shingle installation is complete.
c. Exterior siding and trim is complete except at exterior door, wall louver perimeter, and
structural beam adjacent to pump pit.
d. Exterior doors not installed.
e. Interior electrical and plumbing work ongoing.
ARCHITECTS FIELD OBSERVATION REPORT 02
Report Date: June 27, 2022
Page 3 of 3
A R C H I T E C T U R E I N T E R I O R S P L A N N I N G
307 Washington Avenue Albany, New York 12206 USA T: 518•463•8066 F: 518•463•8610 Internet http://www.DDArch.com/
DEMBLING + DEMBLING
A R C H I T E C T S , P.C.
4. Pool Bar:
a. Foundation formwork and rebar installation underway.
This Field Observation Report represents a summary of the conditions noted at the project site by
Dembling + Dembling Architects, P.C. on the date of the site visit. The site visit was performed to
review general conformance of construction with the design concept of the project and general
compliance with the information provided in the contract documents.
END OF ARCHITECTS FIELD OBSERVATION REPORT 02