Re: Septic installation @ 2 Virginia Street,W. Yarmouth, MA
Dear Mr. Murphy,
On September 12, 2005 I was contacted by PKM Contractors to conduct an inspection of the
septic system installation at 2 Virginia Street,West Yarmouth, MA.
The Water District,per the request of the Asst. Health Director,had located the water main and
the concern was that the SAS was installed in a different location than the proposed plan by
TADCO Consultants on 9/21/04.
A thorough inspection of the system confirmed the Agents apprehension and a meeting with you
that afternoon resulted in providing the Health Department with a Certified As-Built. The SAS,
as presently installed, requires a 5.5' lot line variance from the eastern property line abutting
Cleveland Way. The SAS is exactly 10' from the water main. The installer, PKM,was
instructed to alter the grading over the SAS as the original plan proposed and as a result of>3' of
cover over approximately ''A of the SAS.
Other than the above changes during installation,the system was installed in substantial
compliance with acceptable tolerances to the Massachusetts Sanitary Code,Title 5, and the plan
by TADCO Consultants dated 9/21/04. The"as-built"card was to be supplied by the installer.
If there are any further questions or concerns, please don't hesitate to call.
Very Truly Xexirs,
��J
Tanya Johansen .
Enclosed revised blueprint
File
G. Sherman
PKM Contractors