HomeMy WebLinkAboutCOC request
August 18, 2022 C18543.00
Yarmouth Conservation Commission By Hand Delivery
Attn: Brittany DiRienzo
1146 Route 28
South Yarmouth, MA 02664
Re: Certificate of Compliance Filing Package
Proposed Site Development
Mill Cove Associates
183 Route 28
West Yarmouth, MA
Map 37, Parcel 72.1
DEP File NO: SE 83-487
OOC Book 4151, Book 79
Dear Ms. DiRienzo and Commission Members:
On behalf of our client The Cove at Yarmouth Associates, we are submitting a Certificate of Compliance
Filing Package. The following items are enclosed:
• Yarmouth Conservation COC Administrative Checklist
• WPA Form 8A – Request for a Certificate of Compliance
• Engineer’s Statement of Compliance
• Copy of $75.00 check made payable to Town of Yarmouth for filing fee
Please schedule this for the September 1, 2022 public hearing. If you have any questions or require
additional information, please give our office a call. Thank you.
Sincerely,
COASTAL ENGINEERING CO., INC.
Carla A. Davis
Enclosures: as stated
cc: The Cove at Yarmouth Associates Limited Partnership
Sean M. Riley, Project Manager
Yarmouth Conservation Commission • 1146 Route 28 • South Yarmouth, MA 02664-4492
Tel. (508)-398-2231 Ext. 1288 • Fax (508)-398-0836 • TTD# (508) 398-2231 • kgrant@yarmouth.ma.us
Rev 8/2021
Administrative Checklist
Certificate of Compliance
General Information:
All filings must be made on Town of Yarmouth forms.
All applications must be submitted two weeks prior to the next scheduled Conservation
Commission meeting. Refer to Meeting Schedule.
Failure to follow the Administrative Checklist shall result in an Administrative Incomplete
Application and will not be scheduled for a Public Hearing.
Contact the Conservation Office if you need assistance.
Submitting an Application:
1 complete original application, plan/sketch, and other supporting information
to the Conservation Division - mailed to/dropped off at Town Hall.
1 complete pdf of application, plan/sketch, and other supporting information
emailed to kgrant@yarmouth.ma.us.
Statement from Engineer and/or stamped As-Built plan if required under the
Order of Conditions to be included with both original and pdf application.
Refer to 310 CMR 10.05(9)(d).
Local filing fee. Refer to Fee Schedule. Make check payable to “Town of Yarmouth”
and include property address in memo.
All forms, Fee Schedule and Meeting schedule can be found at
https://www.yarmouth.ma.us/696/Filing-Forms.
CONSERVATION
DIVISION
X
X
X
X
wpaform8a.doc •• rev. 5/29/14 Page 1 of 2
Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands
WPA Form 8A – Request for Certificate of Compliance
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
Town of Yarmouth Wetland By-law, Chapter 143
DEP File Number:
SE 83-487
Provided by DEP
A. Project Information
Important:
When filling out
forms on the
computer, use
only the tab
key to move
your cursor -
do not use the
return key.
1. This request is being made by:
The Cove at Yarmouth Associates Limited Partnership
Name
183 Route 28
Mailing Address
West Yarmouth
City/Town
MA
State
02673
Zip Code
Phone Number
2. This request is in reference to work regulated by a final Order of Conditions issued to:
Mill Cove Assosciates
Applicant
June 8, 1984
Dated
SE 83-487
DEP File Number
Upon completion
of the work
authorized in
an Order of
Conditions, the
property owner
must request a
Certificate of
Compliance
from the issuing
authority stating
that the work or
portion of the
work has been
satisfactorily
completed.
3. The project site is located at:
183 Route 28
Street Address
West Yarmouth
City/Town
37
Assessors Map/Plat Number
72.1
Parcel/Lot Number
4. The final Order of Conditions was recorded at the Registry of Deeds for:
Mill Cove Assosciates
Property Owner (if different)
Barnstable
County
4151
Book
79
Page
Certificate (if registered land)
5. This request is for certification that (check one):
the work regulated by the above-referenced Order of Conditions has been satisfactorily completed.
the following portions of the work regulated by the above-referenced Order of Conditions have
been satisfactorily completed (use additional paper if necessary).
the above-referenced Order of Conditions has lapsed and is therefore no longer valid, and the
work regulated by it was never started.
wpaform8a.doc •• rev. 5/29/14 Page 2 of 2
Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands
WPA Form 8A – Request for Certificate of Compliance
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
Town of Yarmouth Wetland By-law, Chapter 143
DEP File Number:
SE 83-487
Provided by DEP
A. Project Information (cont.)
6. Did the Order of Conditions for this project, or the portion of the project subject to this request, contain
an approval of any plans stamped by a registered professional engineer, architect, landscape
architect, or land surveyor?
Yes If yes, attach a written statement by such a professional certifying substantial
compliance with the plans and describing what deviation, if any, exists from the plans
approved in the Order.
No
B. Submittal Requirements
Requests for Certificates of Compliance should be directed to the issuing authority that issued the final
Order of Conditions (OOC). If the project received an OOC from the Conservation Commission, submit
this request to that Commission. If the project was issued a Superseding Order of Conditions or was the
subject of an Adjudicatory Hearing Final Decision, submit this request to the appropriate DEP Regional
Office (see http://www.mass.gov/eea/agencies/massdep/about/contacts/find-the-massdep-regional-office-
for-your-city-or-town.html).
August 18, 2022 C18543.00
Yarmouth Conservation Commission By Hand Delivery
Attn: Brittany DiRienzo
1146 Route 28
South Yarmouth, MA 02664
Re: Statement of Compliance
Proposed Site Development
Mill Cove Associates
183 Route 28
West Yarmouth, MA
Map 37, Parcel 72.1
DEP File NO: SE 83-487
OOC Book 4151, Book 79
Dear Ms. DiRienzo and Commission Members,
We have reviewed the original plan submitted under the above referenced DEP File No. from May 18,
1984. Coastal Engineering Company (CEC) has conducted a site inspection of the referenced property
and find the work to be in relatively substantial conformance with the plan, “Mill Creek Cove Site Plan”,
Revised 5/18/1984 and Order of Conditions issued on June 8, 1984.
An as-built plan showing current conditions as well as proposed restoration improvements (which are
to be filed under a separate after-the-fact NOI application) has been provided.
Therefore, on behalf of The Cove at Yarmouth Associates Limited Partnership, we respectfully request
a Certificate of Compliance be issued for this project.
Please contact me if you have any questions or require additional information.
Sincerely,
COASTAL ENGINEERING CO., INC.
Sean M. Riley, P.E.
cc: The Cove at Yarmouth Associates Limited Partnership