HomeMy WebLinkAboutDYIMS PE Site report 20220714
Architect: Perkins Eastman DPC
Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File
ARCHITECT’S SITE OBSERVATION REPORT
DATE OF VISIT: 07/14/2022 PROJECT: Dennis Yarmouth Intermediate
Middle School
286 Station Avenue
South Yarmouth, MA 02664
DATE OF ISSUE: 08/24/2022 PROJECT NO: 71011
WEATHER
CONDITIONS:
Sunny, clear, 80s ARCHITECT: Perkins Eastman, DPC
20 Ashburton Street
8th floor
Boston, MA
The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit.
WORK IN PROGRESS:
1) Interior partition framing, drywall
2) Classroom casework installation
3) Painting and tile
4) Ceiling framing; ceiling installation
5) MEP/FP rough-in and finish work
6) Millwork installation
7) Interior CMU partitions
8) Curtain wall installation
9) Misc. Metals installation
10) GFRC panel and prep (girt/ insulation installation)
11) ACM panel as well as girt/insulation installation
12) Sun shade installation
13) Brick masonry
14) Site work
FIELD OBSERVATIONS:
PE visited the site on Thursday 07-14, to review ongoing progress.
Interior Items
1. At the time of observation Cohn (tile subcontractor) was installing tile in the Area D stairwells (see photo p. 4), as
well as wainscots in the corridors of Area C.
2. Bathroom tile installation and epoxy floor finish installation is complete at Area D; still in progress at Area C;
3. Interior millwork and casework installation is ongoing at Area D; Wright has just installed the chair rail at the Area
D wainscot.
4. At Area D, Colony is substantially complete with drywall taping in the classroom corridors.
5. At the time of observation, the millwork installer was working on the Krion “portals” at D level 1 (see photo p. 4).
6. Ceiling installation by H. Carr is ongoing at Areas D and C.
7. Finish electrical work is ongoing at Areas D and C.
8. At Area C, Arden is in the process of installing the D-1 diffusers and radiant panels in the classrooms.
9. At Area C, Painting is ongoing, including at the science classrooms in the links; Colony is taping drywall on level
1; millwork and painting are ongoing;.
10. Colony has finished taping the GWB ceiling at the Area B “central commons.”
11. Lighthouse masonry is still installing the CMU for the MEP enclosures in the gymnasium, now about 60-70%; the
CMU at the area A kitchen is complete, and United is currently in the process of installing the seismic clips.
12. For Area A, Overhead mechanical and sprinkler work are both ongoing at the auditorium, and MEP rough-in is
ongoing at the music rooms.
13. O’Byrne is currently painting the above ceiling areas at the auditorium (Area A).
REPORT BY: ABH Page 2 of 4
Exterior items:
1. Arden is installing the condenser units on the roof for the kitchen equipment.
2. PE reviewed and approved the CW back pan installation at the Area A curtain wall (curtain wall type C-1).
3. On 7-14 in the AM Marguerite poured about half the exterior door aprons, including those at the east sides of
Areas B-C-D wings and at the NE of Area B.
4. Installation of window sun shades at area C is substantially complete.
5. Lymo (panel contractor) has installed blocking for the building signage on the south side of the gymnasium.
6. Lymo has commenced installing the ACM on the upper curving wall of the auditorium (Area A—see photo below).
7. At the time of observation, Lymo was also in the process of installing GFRC panels at the north side of the
gymnasium and ACM at the NE corner, while prepping for GFRC at the East and south sides.
8. At the time of observation Lighthouse was at about 40% with the brick installation at the East and South-east
façade of Area A (auditorium lobby area).
Site work:
1. RBO has installed the Curbs and the binder course of pavement at the ring road around the building.
2. RBO is in the process of placing concrete at the C-D courtyard (see photo on page 3.)
3. Marguerite is setting the forms for drainage structures at the B-C courtyard.
DISCREPANCIES, SPECIAL INSTRUCTIONS
New items
7141. Edge detail at C-D stairs. In some cases there is an excessive gap between the stair stringer and the wall;
PE asked CB to have United close with a thin 12 gauge plate welded to top of stringer (see photo p. 3).
7142. MAAB issue with Interior door frames. PE inventoried 13 instances of 3’ wide interior doors that conflict with
MAAB 26.6.2 because the face of the door will be recessed 8” from the face of the frame (so that the MAAB
clearance rectangle shown in 26.6.4 is not within 6” of the door, strictly speaking. Bulletin to follow.
Prior items
7072. (from 07 07 site report) DD-1 diffusers. In some cases the DD-1 diffusers need to be plumbed so that they
are orthogonal with the millwork at the window seats. still open
6301. (from 06 30 site report) Distortion in some panels of CW IGUs. CB, PE, and PMA are in discussion
regarding the acceptability of this distortion. still open
6162. (from 06 16 site report) Detail at DD-1 diffusers. Update: this is being addressed--to be closed.
6163. (from 06 16 site report) Parapet ends at links. Still open
6091. (from 06 09 site report) mortar ‘spalling’ at locker room entrance door head. Update: this has been
addressed--to be closed.
6305. (from 04 21 site report) Steel protrusion at auditorium. Still open.
1131. (From 01-13 site report): Guard rail welds at D & C stairs - United still needs to grind welds for the guards
at academic stairs. Still open.
Attachments
· RJK Field Report 13 from 7-01
· RJK Field Report 14 from 7-08
· RJK Tracking Log from 7-08
SITE PHOTOS
VIEW FROM SOUTH - WEST (AREA A)
REPORT BY: ABH Page 3 of 4
COURYARD CONCRETE (AREA C-D) ACM PANEL INSTALLATION (GYM) COMPLETED SUN SHADES (AREA C)
MAIN CENTRAL COMMONS (AREA B) CHAIR RAIL INSTALLATION (AREA D) GAP AT STAIR STRINGERS (AREA D)
REPORT BY: ABH Page 4 of 4
STAIR TILE INSTALLATION (AREA D LEVEL 2)
COMPLETED EPOXY FLOOR IN BATHROOM (AREA D LEVEL 1)
KRION PORTAL INSTALLATION (AREA D LEVEL 1)
FIELD REPORT
RJK discussed the issues with CB and Beacon before leaving the site.
Work Observed
• Air and Vapor Barrier (AVB) Installation
• Various Cladding Installation
• Window Installation
Observations
• Part B, north and east elevations top of wall transition, second floor line, Grid Lines J.7 and B33 - GCP
Perm-A-Barrier Aluminum AVB was installed by Beacon. The membrane was installed in a water
shedding fashion lapping onto the through wall flashing. (Figure 1 and Figure 2)
• Part A, south and east elevation rising walls, Grid Lines A15 and V - Exterior wall penetrations are
detailed utilizing DOWSIL 795 Silicone Building Sealant. (Figure 3)
• Part A, south and east elevations base detail, Grid Lines A15 and V -Hohmann & Bernard Thermal 2-
Seal Wing Nut Anchors are installed through 2 inch extruded polystyrene insulation. Precast concrete
bases were installed onto the foundation, supported by the masonry anchors. (Figure 4)
• Part A, east and south elevations base detail, Grid Lines A15 - B11 - Solid grout fill was installed
between precast concrete bases and extruded polystyrene insulation. (Figure 5)
• Part A, west and east elevations base detail, Grid Lines A15 and A2 - Metal through-wall flashing was
installed over the precast concrete base, set in Sika Sarnafil Sikaflex-1A polyurethane joint sealant prior
to RJK’s arrival on site. The metal was fastened utilizing a termination bar and screws spaced at 16
inches on-center. The through-wall flashing was stripped in at the rising wall and at metal joints
utilizing GCP Perm-A-Barrier Aluminum AVB and the edges are detailed with DOWSIL 795 Silicone
Building Sealant. (Figure 6)
• Part A, east elevation rising walls, Grid Line A15 - Hohmann & Bernard Thermal 2-Seal Wing Nut
Anchors are installed through 6 inch ROCKWOOL insulation. (Figure 7)
• Part A, east elevation rising walls, Grid Line A15 - Window flanges are stripped in utilizing self-
adhered aluminum flashing in a water shedding fashion. Dow Sil 795 Sealant was applied to the
membrane edges. (Figure 8)
Project: Q504 - Mattacheese, Dennis-Yarmouth Intermediate
Middle School Report Number: FR-13
Property Address: 276 Station Avenue, South Yarmouth, MA 02664
Client: Perkins Eastman
Date of Site Visit: Friday, July 1, 2022
Report Date: Thursday, July 7, 2022
Weather: Sunny 80 °F, 4 mph winds
Purpose of Visit: Observe Building Enclosure Construction
On-Site During Visit: Michael Groome - R. J. Kenney Associates, Inc. (RJK)
Ken - Beacon Waterproofing and Restoration, Inc. (Beacon)
Report By: Michael Groome
Report Attachments: Detailed Photographs
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number: FR-13
7/7/2022
Report Narrative
G:\RJK\WORD\32042 Q504 Mattacheese DYIMS Yarmouth FR13 Report 7-01-22.docx Page 2 of 11
• Part A, south elevation rising wall exterior window sealant joints, Grid Line W - Backer rod was
installed without twist or dent and DOWSIL 795 Silicone Building Sealant was gun applied onto the
backer rod. The sealant was then tooled in to complete the concave shape and promote adhesion to the
frame and metal. (Figure 9)
• Part B, west elevation courtyard rising wall, Grid Line B15 and east elevation rising wall, Grid Line B24
- Insulation was set between horizontal GreenGirt. (Figure 10)
• Part B, west elevation courtyard rising wall, Grid Line B1 - LYMO 2000 ACM panels were installed,
fastened utilizing panel clips to the horizontal GreenGirt. (Figure 11)
• Part B, north, south, east and west elevation rising walls, Grid Lines B21, B24, B33, P.1 and J.7 -
Knight MFI ThermaBracket S-Series wall ties were installed, wet set in GCP Perm-A-Barrier S100
Sealant, and fastened utilizing screws wet set in the sealant. (Figure 12)
• Part B, north and east elevation rising walls, Grid Lines B21 and J.7 - S-rails were fastened vertically
between the Knight MFI ThermaBracket S-Series wall ties. Insulation is set between the ties and held in
place by friction and the rails. Horizontal galvanized hat channel is installed, fastened to vertical Knight
S-Rails. (Figures 13 and 14)
• Part B, east elevation rising wall, Grid Line B21 - Rieder Öko Skin high performance cementitious wall
panels were installed and are fastened to the horizontal galvanized hat channel with screws. (Figure 15)
• Part A, east elevation curtain wall systems, Grid Line B13 - Individual insulated glazing units are
installed, temporarily fastened utilizing intermittent pressure plate sections. (Figures 16 and 17)
Discussions
13.1 End Dams at Through Wall - Part B, East Elevation, Grid Line B33 - Top of brick through-wall flashing
does not have end dams extending 2 inches high, per Specification 076200, 2.8, A. End dams to be
added unless condition has been approved by the design team. (Figures 1 and 2)
END OF REPORT
RJK has no contractual responsibility in the design or actual construction of the project and is acting solely in a consultant and/or in an
advisory capacity to the Client. Any and all modifications, changes, recommendations, suggestions, etc., relating to the design and/or
construction, should be forwarded, reviewed, and approved by the designer of record prior to implementation. RJK reserves the right
to change or amend this report as new information becomes available.
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-13
7/7/2022
Appendix A
G:\RJK\WORD\32042 Q504 Mattacheese DYIMS Yarmouth FR13 Report 7-01-22.docx Page 3 of 11
Callouts:
1. GCP Perm-A-Barrier
Aluminum AVB
2. No End Dam
Comments:
0701 109 R. J. Kenney Associates, Inc.
Figure 1 ‐ Sheet-Applied AVB Over Through-Wall at Top of Brick
Callouts:
1. No End Dam
Comments:
0701 106 R. J. Kenney Associates, Inc.
Figure 2 ‐ AVB Over Through-Wall at Top of Brick
1 2
1
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-13
7/7/2022
Appendix A
G:\RJK\WORD\32042 Q504 Mattacheese DYIMS Yarmouth FR13 Report 7-01-22.docx Page 4 of 11
Callouts:
1. DOWSIL 795 Silicone
Building Sealant
Comments:
0701 040 R. J. Kenney Associates, Inc.
Figure 3 ‐ AVB Penetration Detailing
Callouts:
Comments:
0701 039 R. J. Kenney Associates, Inc.
Figure 4 ‐ Precast Concrete Bases
1
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-13
7/7/2022
Appendix A
G:\RJK\WORD\32042 Q504 Mattacheese DYIMS Yarmouth FR13 Report 7-01-22.docx Page 5 of 11
Callouts:
1. Solid Fill Grout
Comments:
0701 038 R. J. Kenney Associates, Inc.
Figure 5 ‐ Solid Grout Fill at Precast Concrete Bases
Callouts:
1. AVB Lapping Through-
Wall Flashing
2. Flashing
3. Sika Sarnafil Sikaflex-1A
Polyurethane Joint
Sealant
Comments:
0701 058 R. J. Kenney Associates, Inc.
Figure 6 ‐ Stripped in Through-Wall Flashing
1
1
2 3
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-13
7/7/2022
Appendix A
G:\RJK\WORD\32042 Q504 Mattacheese DYIMS Yarmouth FR13 Report 7-01-22.docx Page 6 of 11
Callouts:
1. Hohmann & Bernard
Thermal 2-Seal Wing Nut
Anchor
2. 6 Inch ROCKWOOL
Insulation
Comments:
0701 025 R. J. Kenney Associates, Inc.
Figure 7 ‐ Wall Insulation
Callouts:
Comments:
0701 046 R. J. Kenney Associates, Inc.
Figure 8 ‐ Lentil Strip In
1
2
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-13
7/7/2022
Appendix A
G:\RJK\WORD\32042 Q504 Mattacheese DYIMS Yarmouth FR13 Report 7-01-22.docx Page 7 of 11
Callouts:
1. Sealant Knife
Comments:
0701 050 R. J. Kenney Associates, Inc.
Figure 9 ‐ Tooled in Sealant
Callouts:
Comments:
0701 021 R. J. Kenney Associates, Inc.
Figure 10 ‐ Green Girt and Insulation
1
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-13
7/7/2022
Appendix A
G:\RJK\WORD\32042 Q504 Mattacheese DYIMS Yarmouth FR13 Report 7-01-22.docx Page 8 of 11
Callouts:
Comments:
0701 073 R. J. Kenney Associates, Inc.
Figure 11 ‐ LYMO 2000 ACM panels
Callouts:
Comments:
0701 121 R. J. Kenney Associates, Inc.
Figure 12 ‐ Knight MFI ThermaBracket S-Series Wall Ties
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-13
7/7/2022
Appendix A
G:\RJK\WORD\32042 Q504 Mattacheese DYIMS Yarmouth FR13 Report 7-01-22.docx Page 9 of 11
Callouts:
Comments:
0701 093 R. J. Kenney Associates, Inc.
Figure 13 ‐ Wall Insulation at ThermaBracket Ties
Callouts:
Comments:
0701 123 R. J. Kenney Associates, Inc.
Figure 14 ‐ Horizontal Hat Channel
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-13
7/7/2022
Appendix A
G:\RJK\WORD\32042 Q504 Mattacheese DYIMS Yarmouth FR13 Report 7-01-22.docx Page 10 of 11
Callouts:
Comments:
0701 124 R. J. Kenney Associates, Inc.
Figure 15 ‐ Rieder Öko Skin High Performance Cementitious Wall Panels
Callouts:
Comments:
0701 129 R. J. Kenney Associates, Inc.
Figure 16 ‐ Curtain Wall IGU Installation
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-13
7/7/2022
Appendix A
G:\RJK\WORD\32042 Q504 Mattacheese DYIMS Yarmouth FR13 Report 7-01-22.docx Page 11 of 11
Callouts:
Comments:
0701 130 R. J. Kenney Associates, Inc.
Figure 17 ‐ Temporary Clip Fastening
FIELD REPORT
RJK discussed the issues with CB and Beacon before leaving the site.
Work Observed
• Air and Vapor Barrier (AVB) Installation
• Various Cladding Installation
• Window Installation
Observations
• Part B, south elevation, second floor line, entrance canopy, Grid Lines A17 and B29 - GCP Perm-A-
Barrier Aluminum AVB was installed by Beacon prior to RJK’s arrival on site. The membrane was
installed in a water shedding fashion with sealant at the angle change. (Figure 1)
• Part B, courtyard east elevation base detail, Grid Line B22 - Hohmann & Bernard Thermal 2-Seal Wing
Nut Anchors are installed through 2 inch extruded polystyrene insulation. Precast concrete bases were
installed onto the foundation, supported by the masonry anchors. Solid grout fill was installed between
precast concrete bases and extruded polystyrene insulation. (Figure 2)
• Part A, south elevations base detail, Grid Lines A18 and A19 - Metal drip flashing was installed over the
precast concrete base at the radial wall, set in Sika Sarnafil Sikaflex-1A polyurethane joint sealant. The
metal was fastened utilizing concrete anchors hammered into pre-drilled holes. (Figures 3 - 5)
• Part A, south elevations base detail, Grid Lines A17 and A18 - Through-wall flashing was installed
lapping onto the exterior wall and onto the drip flashing set in sealant. (Figure 6)
• Part A, west elevation base detail, Grid Lines R - U - Through-wall flashing was stripped in at the rising
wall and at metal joints utilizing GCP Perm-A-Barrier Aluminum AVB and the edges are detailed with
DOWSIL 795 Silicone Building Sealant. (Figure 7)
• Part A, north elevation rising walls, Grid Lines B4-B13 - Hohmann & Bernard Thermal 2-Seal Wing
Nut Anchors are installed through 6 inch ROCKWOOL insulation. (Figure 8)
• Part B, south elevation rising wall, Grid lines B10-B13, and Part A, south elevation rising wall, Grid
Lines A1-A6 - GreenGirt was installed set in GCP Perm-A-Barrier S100 Sealant. (Figure 9)
Project: Q504 - Mattacheese, Dennis-Yarmouth Intermediate
Middle School Report Number: FR-14
Property Address: 276 Station Avenue, South Yarmouth, MA 02664
Client: Perkins Eastman
Date of Site Visit: Friday, July 8, 2022
Report Date: Monday, July 18, 2022
Weather: Sunny 74 °F
Purpose of Visit: Observe Building Enclosure Construction
On-Site During Visit:
Michael Groome - R. J. Kenney Associates, Inc. (RJK)
Ryan DiRico - Commodore Builders (CB)
Ken - Beacon Waterproofing and Restoration, Inc. (Beacon)
Report By: Michael Groome
Report Attachments: Detailed Photographs
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number: FR-14
7/18/2022
Report Narrative
G:\RJK\WORD\32043 Q504 Mattacheese DYIMS Yarmouth FR14 Report 7-08-22.docx Page 2 of 10
• Part A, south elevation rising wall, Grid Lines A1 - A6 - Insulation was set between horizontal
GreenGirt. (Figure 10)
• Part A, south elevation rising wall, Grid Lines A6-A12 - LYMO 2000 ACM panels were installed,
fastened utilizing panel clips to the horizontal GreenGirt. (Figure 11)
• Part B, east elevation and Part C, south elevation rising walls, Grid Lines B24, H - Backer rod and
sealant were installed between the brick cladding and LYMO 2000 ACM panels prior to RJK’s arrival
on site. (Figure 12)
• Part B, east and north elevation rising walls, Grid Lines B33 and J.7 - Knight MFI ThermaBracket S-
Series wall ties were installed, wet set in GCP Perm-A-Barrier S100 Sealant and fastened utilizing
screws. (Figure 13)
• Part B, east elevation rising wall, Grid Lines B33 - Z-metal is installed directly on the AVB membrane
at the parapet due to the change in plane between block and gypsum per Ryan DiRico (CB). (Figure
14)
• Part B, north and east elevation rising walls, Grid Lines B33 and J.7 - S-rails were fastened vertically
between the Knight MFI ThermaBracket S-Series wall ties. Insulation is set between the ties and held in
place by friction and the rails. Horizontal galvanized hat channel is installed, fastened to vertical Knight
S-Rails. (Figure 15)
• Part B, north elevation rising wall, Grid Line J.7 - Rieder Öko Skin high performance cementitious wall
panels were installed and are fastened to the horizontal galvanized hat channel with color matched
screws. (Figure 16)
END OF REPORT
RJK has no contractual responsibility in the design or actual construction of the project and is acting solely in a consultant and/or in an
advisory capacity to the Client. Any and all modifications, changes, recommendations, suggestions, etc., relating to the design and/or
construction, should be forwarded, reviewed, and approved by the designer of record prior to implementation. RJK reserves the right
to change or amend this report as new information becomes available.
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-14
7/18/2022
Appendix A
G:\RJK\WORD\32043 Q504 Mattacheese DYIMS Yarmouth FR14 Report 7-08-22.docx Page 3 of 10
Callouts:
1. GCP Perm-A-Barrier
Aluminum AVB
Comments:
0708 033 R. J. Kenney Associates, Inc.
Figure 1 ‐ Sheet-Applied AVB Over Parapet Wall
Callouts:
Comments:
0708 100 R. J. Kenney Associates, Inc.
Figure 2 ‐ Precast Concrete Bases
1
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-14
7/18/2022
Appendix A
G:\RJK\WORD\32043 Q504 Mattacheese DYIMS Yarmouth FR14 Report 7-08-22.docx Page 4 of 10
Callouts:
1. AVB Lapping Through-
Wall Flashing
2. Flashing
3. Sika Sarnafil Sikaflex-1A
Polyurethane Joint
Sealant
Comments:
0708 022 R. J. Kenney Associates, Inc.
Figure 3 ‐ Stripped in Through-Wall Flashing
Callouts:
Comments:
0708 027 R. J. Kenney Associates, Inc.
Figure 4 ‐ Drip Flashing at Precast Concrete Bases
1
2 3
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-14
7/18/2022
Appendix A
G:\RJK\WORD\32043 Q504 Mattacheese DYIMS Yarmouth FR14 Report 7-08-22.docx Page 5 of 10
Callouts:
Comments:
0708 045 R. J. Kenney Associates, Inc.
Figure 5 ‐ Drip Metal Fastened
Callouts:
Comments:
0708 057 R. J. Kenney Associates, Inc.
Figure 6 ‐ Through-Wall Flashing Over Drip Metal
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-14
7/18/2022
Appendix A
G:\RJK\WORD\32043 Q504 Mattacheese DYIMS Yarmouth FR14 Report 7-08-22.docx Page 6 of 10
Callouts:
Comments:
0708 126 R. J. Kenney Associates, Inc.
Figure 7 ‐ Through-Wall Flashing Stripped In
Callouts:
1. Hohmann & Bernard
Thermal 2-Seal Wing Nut
Anchor
2. 6 Inch ROCKWOOL
Insulation
Comments:
0708 115 R. J. Kenney Associates, Inc.
Figure 8 ‐ Wall Insulation
1
2
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-14
7/18/2022
Appendix A
G:\RJK\WORD\32043 Q504 Mattacheese DYIMS Yarmouth FR14 Report 7-08-22.docx Page 7 of 10
Callouts:
Comments:
0708 070 R. J. Kenney Associates, Inc.
Figure 9 ‐ GreenGirt Installation
Callouts:
Comments:
0708 006 R. J. Kenney Associates, Inc.
Figure 10 ‐ Insulation at GreenGirt
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-14
7/18/2022
Appendix A
G:\RJK\WORD\32043 Q504 Mattacheese DYIMS Yarmouth FR14 Report 7-08-22.docx Page 8 of 10
Callouts:
Comments:
0708 004 R. J. Kenney Associates, Inc.
Figure 11 ‐ LYMO 2000 ACM panels
Callouts:
Comments:
0708 090 R. J. Kenney Associates, Inc.
Figure 12 ‐ Sealant Between Brick and Metal
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-14
7/18/2022
Appendix A
G:\RJK\WORD\32043 Q504 Mattacheese DYIMS Yarmouth FR14 Report 7-08-22.docx Page 9 of 10
Callouts:
Comments:
0708 075 R. J. Kenney Associates, Inc.
Figure 13 ‐ Knight MFI ThermaBracket S-Series Wall Ties
Callouts:
Comments:
0708 078 R. J. Kenney Associates, Inc.
Figure 14 ‐ Variant Z-Metal at Substrate Transition
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-14
7/18/2022
Appendix A
G:\RJK\WORD\32043 Q504 Mattacheese DYIMS Yarmouth FR14 Report 7-08-22.docx Page 10 of 10
Callouts:
Comments:
0708 135 R. J. Kenney Associates, Inc.
Figure 15 ‐ Wall Insulation at ThermaBracket Ties
Callouts:
Comments:
0708 134 R. J. Kenney Associates, Inc.
Figure 16 ‐ Rieder Öko Skin High Performance Cementitious Wall Panels
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
7/08/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
2.2 Insulation Offset Part D Roof 05/17/22: Photos of the
correction will close the item. Open
2.3 Wetted Polyisocyanurate
Insulation
Part D Roof Open
2.4
Upside Down Insulation Part D Roof 05/17/22: Written approval
from the manufacturer that the
orientation is acceptable for the
assembly will close the item,
otherwise correction of
installation methods.
Open
3.4
Wet Polyisocyanurate
Insulation and Cover Board Is
Installed
Part C 05/12/22: Testing will be
necessary to confirm materials
are dry and without organic
growth.
Open
3.5
Incomplete Night Tie-In Part C 05/17/22: Testing should be
conducted at the location to
ensure no moisture intrusion
occurred at the incomplete tie
in.
Open
4.3
Interior Air Barrier Seal at
Windows
Part D 04/28/22: Please provide
approved direction for the issue. Open
4.4
Window Fastening Part D 04/28/22: Please provide
photos of sealant at fasteners. Open
FR-1, 12/15/2021
FR-3, 12/28/2021
FR-2, 12/22/2021
FR-4, 1/6/2022
G:\RJK\WORD\32044 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 7-08-22 1 of 4
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
7/08/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
4.5
Wet Polyisocyanurate
Insulation and Cover Board Is
Installed
Part C and Part
D Roofs
05/12/22: Testing will be
necessary to confirm materials
are dry and without organic
growth.
Open
4.6 Pitch Pocket Detail Part C 04/28/22: No change.Open
4.7
Uncut Clamping Rings Part C 04/07/22: Multiple clamping
rings still left uncut at Part C.
04/28/22: No change.
Open
6.1 Voids in Damproofing From
Damage
Part D and Part
C Open
6.3
Roof Debris Typical 04/28/22: Some large
equipment is on plywood,
although screws, pipes and
other debris are still observed
on the membrane.
Open
6.4
Roof Ponding Part C to Part B 04/28/22: Additional ponding
is observed at the west
breezeway.
05/12/22: Ponding is
continuously observed at both
locations.
Open
6.5
PVC In Contact with Asphalt Part B Penthouse 04/28/22: Membrane is still in
contact, and through wall
flashing is installed.
05/12/22: No change observed.
Open
FR-6, 4/7/2022
FR-5, 3/21/2022
FR-8, 5/12/2022
FR-7, 4/28/2022
No New Issues
G:\RJK\WORD\32044 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 7-08-22 2 of 4
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
7/08/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
8.1
Missing AVB Part B, Level 1
Rising Wall to
Parapet
Transition
06/10/22: AVB membrane and
sealant was installed. Closed
8.2
Discontinued AVB at Curtain
Wall Column
Part B, East
Elevation Rising
Wall, Grid Lines
M.9-L
Open
8.3
Missing Insulation Behind
Brick
Part B, North
Elevation Rising
Wall, Grid Lines
B32
06/10/22: Insulation was
observed at the location. Closed
8.4
Roof Discontinuation Between
Vapor Barrier and PVC
Membrane
Part B,
Gymnasium
Roof, Grid Lines
B24 - B25
Open
10.1
AVB Above Brick Cladding Part B, Gridlines
A17-A22, P.7
06/16/22: The steel was
cleaned and air barrier applied. Closed
FR-12, 6/21/2022
No New Issues
FR-11, 6/16/2022
FR-13, 7/1/2022
FR-9, 5/17/2022
No New Issues
FR-10, 6/10/2022
No New Issues
G:\RJK\WORD\32044 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 7-08-22 3 of 4
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
7/08/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
13.1
End Dams at Through-Wall Part B, East
Elevation, Grid
Line B33
Open
No New Issues
FR-14, 7/8/2022
G:\RJK\WORD\32044 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 7-08-22 4 of 4