ARCHITECT’S SITE OBSERVATION REPORT
DATE OF VISIT: 08/25/2022 PROJECT: Dennis Yarmouth Intermediate
Middle School
286 Station Avenue
South Yarmouth, MA 02664
DATE OF ISSUE: 09/07/2022 PROJECT NO: 71011
WEATHER
CONDITIONS:
Sunny and clear, 90s ARCHITECT: Perkins Eastman, DPC
20 Ashburton Street
8th floor
Boston, MA
The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit.
WORK IN PROGRESS:
1) Drywall taping and painting
2) Classroom casework installation
3) Classroom Linoleum flooring installation
4) Millwork installation
5) Tile installation
6) Ceiling framing; ceiling installation
7) Completion of MEP/FP rough-in
8) MEP/FP finish work
9) Interior painting
10) Air barrier installation
11) Curtain wall silicone sealing
12) GFRC panel installation and prep (girt/ insulation installation)
13) ACM panel installation and prep (girt/insulation installation)
14) Site work
15) Irrigation installation
FIELD OBSERVATIONS:
PE visited the site on Thursday 08-25, to review ongoing progress.
Interior Items
1. RTUs for Area D were started up earlier this week.
2. Linoleum flooring installation At Area D is ongoing
3. H. Carr will be installing marker boards starting tomorrow, beginning with Area D.
4. At Area D, epoxy and SSM casework counter tops have been installed; ceiling installation is almost complete in
the classrooms and 80% in the corridors.
5. Millwork installation at Area C is ongoing.
6. At Area C, finished ceiling installation is underway, installation of portals at levels 1 and 2 is complete.
7. At Area C, Casework installation is ongoing; corridor tile at Area C is complete.
8. At Area B central commons area, the walls are finished and primed and ready for finishes; at the time of
observation Colony was taping the locker room ceilings.
9. O’Byrne is in the process of painting the stair metal in the academic wings.
10. O’Byrne is painting the south side gymnasium steel / MEP (See photo on page 3), as well as the overhead
mechanicals etc. in adaptive PE; the HM doors for the gym area have been painted.
11. At Area A the auditorium ceiling is mostly complete and the staging for the work platform is being dismantled. See
photo on page 3.
12. At area A, Above-ceiling MEP work is ongoing at the cafeteria and kitchen— at the kitchen it is almost complete
and ready for ceiling installation.
REPORT BY: ABH Page 2 of 4
Exterior items:
1. Curtain wall water penetration resistance testing and air leakage testing was conducted on 8-22-22 (see attached
RJK field report FR-18).
2. At the time of observation, Lymo had removed the damaged panels at the parapet of the SW link structure (see
“prior item” 8112 below).
3. At the time of observation, Lymo had finished prepping the east façade of Area A and was installing the ACM at
the SE corner of the auditorium (Area A). See photo below.
4. At the time of observation, Beacon was installing the silicone tape to seal the CW at the curtain wall at the media
center (south side of Area B).
5. Per RJK, on 8-22 Beacon installed patches for the holes in the silicone transition sheets at cafeteria CW openings
where damaged by Stanley (see attached RJK field report FR-18).
6. At the time of observation, Stanley was in the process of replacing the sheet metal window surrounds for the large
curtain wall openings at the cafetorium. See photo on page 4.
Site work:
1. RBO’s subcontractor partially installed the concrete walkways east of D earlier in the week. See photo page 4.
2. RBO installed the scoreboard for field B yesterday.
3. RBO is working on the west side of D wing spreading loam and prepping subgrade and forms for the sidewalks.
4. At the time of observation RBO’s subcontractor was cutting relief joints in the concrete sidewalks on the north and
east of field C; the Station Avenue sidewalk has been paved. See photo page 4.
5. At the time of observation, RBO working on the fine grade for Field A (lower turf field) See photo page 4.
DISCREPANCIES, SPECIAL INSTRUCTIONS
New items-no new items
Prior items
8182. (from 8-18 site report) Grading issue at basketball court: Update: On 8-31 TLA issued direction in response
to RFI #425 – item to be closed.
8183. (from 8-18 site report) Shot put concrete curb in wrong location: Still open
8184. (from 8-18 site report) Disconnect between PVC roof membrane and AVB: Still open
8185. (from 8-18 site report) Unsealed prefab pipe flashing. Still open
8111. (from 8-11 site report) Water filling station at Level 2. Still open
8112. (from 8-11 site report) Damaged ACM parapet panels: Update: Per observation above, Lymo is in the
process of replacing the two damaged parapet panels; item to be closed.
8113. (from 8-11 site report) Metal in contact with roof membrane. still open
7191. (from 07 19 site report) Brick pattern at inside corner. still open
7192. (from 07 19 site report) Gap at PCC base and CW at Area D stair entries. still open
6301. (from 06 30 site report) Distortion in some panels of CW IGUs. Update: PE issued a “notice of non-
conformance” on 8-26, requesting that Lambrian replace specified IGU panels. This item to be closed.
6305. (from 04 21 site report) Steel protrusion at auditorium. still open.
Attachments
· RJK site report FR 18 (from 08-22-2022)
SITE PHOTOS
ACM INSTALLATION AT SE CORNER OF AUDITORIUM (AREA A)
REPORT BY: ABH Page 3 of 4
GYMNASIUM PROGRESS (AREA B)
KITCHEN AND CAFETORIUM PROGRESS (AREA B)
AUDITORIUM PROGRESS (AREA A)
REPORT BY: ABH Page 4 of 4
RE-INSTALLATION OF WINDOW SURROUNDS AT CAFETORIUM (AREA A)
SITE WORK PROGRESS AT FUTURE PLAYGROUND AREA (EAST OF ACADEMIC WINGS)
SITE WORK PROGRESS AT STATION AVENUE
FIELD REPORT
RJK discussed the issues with CB prior to leaving the site.
Work Observed
• Air Barrier Installation
• Curtain Wall Testing
Observations
• Part A, North Elevation, Grid Line K - Elbex HS-222 silicone transition sheet was damaged during
installation of metal at the edge of the Rieder Öko Skin high performance cementitious wall panels.
Patches set in sealant were being installed to create a continuous barrier around the curtain walls.
(Figures 1, 2)
Curtain Wall Testing
• Part D, West Elevation, Grid Lines D2, C-B.4, C29 Curtain Wall at Exit 39 - Testing was conducted by
UTS to check for air and water leakage. The water penetration resistance testing was performed in
accordance with ASTM E 1105: “Test Method for Field Determination of Water Penetrations of
Installed Exterior Windows, Skylights, Doors, and Curtain Walls, By Uniform or Cyclical Static Air
Pressure Difference”. The curtain wall was first tested for air leakage and then water leakage. A total of
two tests were conducted on the curtain wall unit. Air testing was conducted at 6.24 psf and water
testing was conducted at 6.24 psf. The unit passed air and water testing. (Figures 4 - 6)
• Part C, West Elevation, Grid Lines ii, E, C28 Curtain Wall - Testing was conducted by UTS to check for
air and water leakage. The water penetration resistance testing was performed in accordance with
ASTM E 1105: “Test Method for Field Determination of Water Penetrations of Installed Exterior
Windows, Skylights, Doors, and Curtain Walls, By Uniform or Cyclical Static Air Pressure Difference”.
The curtain wall was first tested for air leakage and then water leakage. A total of two tests were
Project: Q504 - Mattacheese, Dennis-Yarmouth Intermediate
Middle School Report Number: FR-18
Property Address: 276 Station Avenue, South Yarmouth, MA 02664
Client: Perkins Eastman
Date of Site Visit: Monday, August 22, 2022
Report Date: Friday, August 26, 2022
Weather: Overcast to Rain 74°F
Purpose of Visit: Observe Building Enclosure Construction
On-Site During Visit:
Michael Groome - R. J. Kenney Associates, Inc. (RJK)
Paul Genereux - Commodore Builders (CB)
Jon Pope - PMA Consultants (PMA)
Ken - Beacon Waterproofing and Restoration Inc (Beacon)
Bob - Universal Testing Services of Massachusetts (UTS)
Mario - UTS
Report By: Michael Groome
Report Attachments: Detailed Photographs
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number: FR-18
8/26/2022
Report
G:\RJK\WORD\32179 Q504 Mattacheese DYIMS Yarmouth FR18 Report 8-22-22.docx Page 2 of 7
conducted on the curtain wall unit. Air testing was conducted at 6.24 psf and water testing was
conducted at 6.24 psf. The unit passed air and water testing. (Figures 7 - 9)
END OF REPORT
RJK has no contractual responsibility in the design or actual construction of the project and is acting solely in a consultant and/or in an
advisory capacity to the Client. Any and all modifications, changes, recommendations, suggestions, etc., relating to the design and/or
construction, should be forwarded, reviewed, and approved by the designer of record prior to implementation. RJK reserves the right
to change or amend this report as new information becomes available.
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-18
8/26/2022
Appendix A
G:\RJK\WORD\32179 Q504 Mattacheese DYIMS Yarmouth FR18 Report 8-22-22.docx Page 3 of 7
Callouts:
Comments:
0822 024 R. J. Kenney Associates, Inc.
Figure 1 ‐ Silicone Transition Sheet Damage Areas
Callouts:
Comments:
0822 042 R. J. Kenney Associates, Inc.
Figure 2 ‐ Damage to Silicone Sheet
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-18
8/26/2022
Appendix A
G:\RJK\WORD\32179 Q504 Mattacheese DYIMS Yarmouth FR18 Report 8-22-22.docx Page 4 of 7
Callouts:
Comments:
0822 040 R. J. Kenney Associates, Inc.
Figure 3 ‐ Elbex Repairs
Callouts:
Comments:
0822 003 R. J. Kenney Associates, Inc.
Figure 4 ‐ Curtain Wall Air Test #1
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-18
8/26/2022
Appendix A
G:\RJK\WORD\32179 Q504 Mattacheese DYIMS Yarmouth FR18 Report 8-22-22.docx Page 5 of 7
Callouts:
Comments:
0822 012 R. J. Kenney Associates, Inc.
Figure 5 ‐ Curtain Wall Water Test #1
Callouts:
Comments:
0822 013 R. J. Kenney Associates, Inc.
Figure 6 ‐ Curtain Wall Water Test #1 Pressure
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-18
8/26/2022
Appendix A
G:\RJK\WORD\32179 Q504 Mattacheese DYIMS Yarmouth FR18 Report 8-22-22.docx Page 6 of 7
Callouts:
Comments:
0822 016 R. J. Kenney Associates, Inc.
Figure 7 ‐ Curtain Wall Air Test #2
Callouts:
Comments:
0822 019 R. J. Kenney Associates, Inc.
Figure 8 ‐ Curtain Wall Water Test #2
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-18
8/26/2022
Appendix A
G:\RJK\WORD\32179 Q504 Mattacheese DYIMS Yarmouth FR18 Report 8-22-22.docx Page 7 of 7
Callouts:
Comments:
0822 020 R. J. Kenney Associates, Inc.
Figure 9 ‐ Curtain Wall Water Test #2 Pressure
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
8/22/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
2.3 Wetted Polyisocyanurate
Insulation
Part D Roof Open
2.4
Upside Down Insulation Part D Roof 05/17/22: Written approval
from the manufacturer that the
orientation is acceptable for the
assembly will close the item,
otherwise correction of
installation methods.
Open
3.4
Wet Polyisocyanurate
Insulation and Cover Board Is
Installed
Part C 05/12/22: Testing will be
necessary to confirm materials
are dry and without organic
growth.
Open
3.5
Incomplete Night Tie-In Part C 05/17/22: Testing should be
conducted at the location to
ensure no moisture intrusion
occurred at the incomplete tie
in.
Open
4.3
Interior Air Barrier Seal at
Windows
Part D 04/28/22: Please provide
approved direction for the issue. Open
4.4
Window Fastening Part D 04/28/22: Please provide
photos of sealant at fasteners. Open
FR-1, 12/15/2021
FR-3, 12/28/2021
FR-2, 12/22/2021
FR-4, 1/6/2022
G:\RJK\WORD\32180 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 8-22-22 1 of 5
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
8/22/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
4.5
Wet Polyisocyanurate
Insulation and Cover Board Is
Installed
Part C and Part
D Roofs
05/12/22: Testing will be
necessary to confirm materials
are dry and without organic
growth.
Open
4.6 Pitch Pocket Detail Part C 04/28/22: No change.Open
4.7
Uncut Clamping Rings Part C 04/07/22: Multiple clamping
rings still left uncut at Part C.
04/28/22: No change.
Open
6.1 Voids in Damproofing From
Damage
Part D and Part
C Open
6.3
Roof Debris Typical 04/28/22: Some large
equipment is on plywood,
although screws, pipes and
other debris are still observed
on the membrane.
Open
6.4
Roof Ponding Part C to Part B 04/28/22: Additional ponding
is observed at the west
breezeway.
05/12/22: Ponding is
continuously observed at both
locations.
Open
FR-6, 4/7/2022
FR-5, 3/21/2022
G:\RJK\WORD\32180 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 8-22-22 2 of 5
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
8/22/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
6.5
PVC In Contact with Asphalt Part B Penthouse 04/28/22: Membrane is still in
contact, and through wall
flashing is installed.
05/12/22: No change observed.
08/08/22: Repairs to the roof
membrane in contact with
asphaltic adhesive were
conducted. The affect
membrane was cut back, and a
new strip of polyvinyl chloride
(PVC) membrane heat welded
to the existing base flashing and
then glued to the wall over the
roofing vapor barrier. A bead
of Sika Sarnafil Sika-Flex is
gun applied to the top edge of
the membrane and struck in. It
is our understanding that this
repair method will be
conducted at similar areas on
the stair tower.
Open
8.2
Discontinued AVB at Curtain
Wall Column
Part B, East
Elevation Rising
Wall, Grid Lines
M.9-L
Open
FR-8, 5/12/2022
FR-7, 4/28/2022
No New Issues
G:\RJK\WORD\32180 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 8-22-22 3 of 5
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
8/22/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
8.4
Roof Discontinuation Between
Vapor Barrier and PVC
Membrane
Part B,
Gymnasium
Roof, Grid Lines
B24 - B25
Open
13.1
End Dams at Through-Wall Part B, East
Elevation, Grid
Line B33
Open
15.1
Glazed in ACM Panels Part B, South
Elevation,
Curtain Wall,
Grid Lines A17-
B21
Open
16.1
Metal Panel in Contact with
Roof Membrane
Part C and D,
East and West
Elevations, Stair
Towers
08/18/22: The metal has been
cut back. Closed
No New Issues
FR-16, 8/8/2022
FR-15, 8/1/2022
FR-12, 6/21/2022
No New Issues
FR-11, 6/16/2022
No New Issues
FR-14, 7/8/2022
FR-13, 7/1/2022
FR-17, 8/18/2022
FR-9, 5/17/2022
No New Issues
FR-10, 6/10/2022
G:\RJK\WORD\32180 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 8-22-22 4 of 5
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
8/22/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
17.1
Damaged Metal Panels Part C,
Courtyard East
Elevation,
Parapet Level
Open
17.2
Disconnect Between PVC Roof
Membrane and AVB
Part B, South
Elevation,
Parapet
Open
17.3
Unsealed Prefabricated Pipe
Flashing
Part B Roof,
Grid Lines L,
B16
Open
No New Issues
FR-18, 8/22/2022