HomeMy WebLinkAboutDYIMS PE Site report 20220908 Architect: Perkins Eastman DPC Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File ARCHITECT’S SITE OBSERVATION REPORT DATE OF VISIT: 09/08/2022 PROJECT: Dennis Yarmouth Intermediate Middle School 286 Station Avenue South Yarmouth, MA 02664 DATE OF ISSUE: 09/13/2022 PROJECT NO: 71011 WEATHER CONDITIONS: Ovecast to partly cloudy, 70s ARCHITECT: Perkins Eastman, DPC 20 Ashburton Street 8th floor Boston, MA The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit. WORK IN PROGRESS: 1) Drywall taping and painting 2) Classroom casework installation 3) Classroom Linoleum flooring installation 4) Tack board and marker board installation 5) Smart screen bracket installation 6) Millwork installation 7) Ceiling framing; ceiling installation 8) MEP/FP finish work—light fixtures etc. 9) Interior painting 10) Curtain wall silicone sealing 11) GFRC panel installation 12) ACM panel installation and prep 13) Site work FIELD OBSERVATIONS: PE visited the site on Thursday 09-08, to review ongoing progress. Interior Items 1. The installation of finishes at Area D is ongoing, including linoleum flooring installation and marker board installation (see photo on page 4). 2. At the time of observation, H. Carr was installing the finished wood slat ceilings at the Area D collaboration spaces on level 2 (see photo on page 3). 3. On the same floor Wright was installing the radiused wood portals at the cross-corridor terminations (see photo on page 5). 4. At the time of observation, wood doors were being delivered to the 2nd floor of Area D. 5. At Area C, Millwork and casework installation are both ongoing; Casework for level C1 will be here next week according to Commodore. 6. At Area C, above-ceiling MEP is substantially complete. 7. At Area C, the installation of ceiling grids, finished ceilings and MEP fixtures are all still ongoing. 8. At Area B, O’Byrne is finishing up painting the locker room area ceilings. 9. H. Carr is finishing the ceiling grid installation in the admin area, as well as at the two art rooms. 10. O’Byrne has finished painting the gymnasium steel / MEP and at the time of observation the gymnasium accessories (e.g. basketball hoops etc.) were going in (see photo on page 5). 11. At Area A, The epoxy flooring in the kitchen area has commenced, and at the time of observation the main floor was prepped and most of the cove base had been installed. 12. At area A, Above-ceiling MEP work is complete at the music wing; drywall for the main auditorium walls is still being installed. REPORT BY: ABH Page 2 of 5 Exterior items: 1. Envelope cladding is nearing completion. The metal panel installation is substantially complete at Area A. 2. At the time of observation Lymo was installing the angled ACM panels at the south façade of Area B (media center); the angled stud framing is in place (see photo on page 4); 3. Oko skin “formpart” outside corner are mostly installed; at the time of observation Lymo was installing the panels at the NW corner of Area D (see photo on page 3). 4. Beacon is continuing to seal the penetrations etc. 5. Commodore is preparing to install the window and close off the opening that has been used for loading materials into D level 2. Site work: 1. The grading at Fields A and B appears substantially complete. 2. RBO is continuing to spread loam and prepare for walkway pours in the areas immediately adjacent to the academic wings. 3. At the time of observation RBO’s subcontractor was putting in the footings for the playground equipment (see photo on page 4.) DISCREPANCIES, SPECIAL INSTRUCTIONS New items 9081. Ceiling-height conflict at D135. At corridor D135 (west cross-corridor at level 1) H. Carr identified a conflict between the design ceiling height and a drain pipe that protrudes from the soffit above the hold-open door. PE asked Carr’s foreman to lower the ceiling by six inches. 9082. Gap at the west elevation. The ACM-to-brick transition at the west elevation has some excessive gaps that need to be addressed. CB said that Lymo is re-making ACM so that it is not as far recessed as it is now. (see photo on page 3). 9083. Grading at PCC base. In certain places, for instance at the very NW corner of D, the top of the loam as currently installed is too close to the bottom of the base (see photo on page 5). It should be min 2-3 inches up on the PCC base so that it does not wash out exposing the bottom of the PCC. Prior items 8183. (from 8-18 site report) Shot put concrete curb in wrong location: Still open 8184. (from 8-18 site report) Disconnect between PVC roof membrane and AVB: Still open 8185. (from 8-18 site report) Unsealed prefab pipe flashing. Still open 8111. (from 8-11 site report) Water filling station at Level 2. Still open 8112. (from 8-11 site report) Metal in contact with roof membrane. Closed per CB—to be verified. 7191. (from 07 19 site report) Exterior Sealant at brick pattern at inside link corner. still open 7192. (from 07 19 site report) Gap at PCC base and CW at Area D stair entries. still open 6305. (from 04 21 site report) Steel protrusion at auditorium. still open. SITE PHOTOS NE CORNER OF C WING AND EAST FAÇADE OF C-D LINK REPORT BY: ABH Page 3 of 5 CORNER PANEL INSTALLATION GAP AT MATERIALS CHANGE (AREA A) ACM END CAP AT LINK (AREA C) WOOD SLAT CEILING INSTALLATION AT PROJECT AREAS (AREA D) REPORT BY: ABH Page 4 of 5 ACM CLADDING PROGRESS (AREA B) MARKER BOARD INSTALLATION PROGRESS (AREA D LEVEL 1) SITE WORK AT FUTURE PLAYGROUND (FOOTINGS FOR PLAYGROUND EQUIPMENT) REPORT BY: ABH Page 5 of 5 GYMNASIUM ACCESSORIES INSTALLATION INSTALLATION OF WOOD PORTAL AT CROSS CORRIDOR (AREA D) LOAM INSTALLATION AT NORTH WEST CORNER (AREA D