HomeMy WebLinkAboutDYIMS PE Site report 20220901 Architect: Perkins Eastman DPC Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File ARCHITECT’S SITE OBSERVATION REPORT DATE OF VISIT: 09/01/2022 PROJECT: Dennis Yarmouth Intermediate Middle School 286 Station Avenue South Yarmouth, MA 02664 DATE OF ISSUE: 09/13/2022 PROJECT NO: 71011 WEATHER CONDITIONS: Sunny and clear, 80s ARCHITECT: Perkins Eastman, DPC 20 Ashburton Street 8th floor Boston, MA The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit. WORK IN PROGRESS: 1) Drywall installation 2) Drywall taping and painting 3) Tack board and marker board installation 4) Classroom casework installation 5) Classroom Linoleum flooring installation 6) Millwork installation 7) Ceiling framing; ceiling installation 8) MEP/FP finish work—light fixtures etc. 9) Interior painting 10) Curtain wall silicone sealing 11) GFRC panel installation 12) ACM panel installation and prep 13) Site work FIELD OBSERVATIONS: PE visited the site on Thursday 09-01, to review ongoing progress. Interior Items 1. The installation of finishes at Area D is still ongoing, including linoleum flooring installation and marker board installation (see photo on page 5). Ceiling installation is almost complete in the classrooms and is at 90% in the corridors. 2. O’Byrne has started the yellow paint on the steel stair stringers and guards at Area D (see photo on page 3). 3. At the time of observation, Wright was in the process of installing the bench under the west stairs at Area D (see photo on page 3); the radiused millwork portals at the link ‘connectors’ are scheduled to be installed next week according to CB. 4. Earlier in the week Harold Brothers installed the bottle filling stations at Area D. 5. At Area C, Millwork and casework installation are both still ongoing; “krion” classroom portals at levels 1 and 2 are completed. 6. At Area C, above-ceiling MEP is almost complete on level 2; will be ready for inspection on 09-06 per CB. 7. At Area C, the installation of ceiling grids, finished ceilings and MEP fixtures are all ongoing. 8. At Area B, H. Carr was in the process of installing the wood “coffers” at the media center in the circulation area at the time of observation (see photo on page 5). 9. O’Byrne is in the process of painting the ceilings at the Area B central commons area, with locker room areas to get painted next (according to Commodore). 10. According to CB O’Byrne is due to finish painting the gymnasium steel / MEP on 09-02 (Friday), and all of the wall painting in Area B is scheduled to be complete next week. 11. The installation of gymnasium accessories (e.g. curtains, hoops etc.) is due to begin next week. 12. At Area A, the staging for the work platform in the auditorium has been removed (see photo on page 4). REPORT BY: ABH Page 2 of 5 13. At area A, Above-ceiling MEP work is complete at the cafeteria and kitchen—ready for ceiling installation. Exterior items: 1. Lymo is in the process of installing the Oko skin “formpart” outside corners, beginning at C wing and D wing (see photo in attached RJK field report FR-19). 2. Lymo has now completed the angled ACM coping at the south low wing of the gymnasium. 3. Lymo has replaced the damaged panels at the parapet of the SW link structure (see “prior item” for action #8112). 4. At the time of observation Lymo had replaced (or re-installed) the GFRC panels around the cafeteria CW openings where the punctured ETA had to be repaired by Beacon (see relevant section of 8-25 site observation report). 5. According to the attached RJK FR-19, Lymo installed the factory corner ACM panels at the NW corner of the auditorium on 8-31 (see photo in FR-19). 6. Lymo has installed the ACM at auditorium entry vestibule on 8-31 (see photo on page 4). 7. At the time of observation, Lymo was installing the angled ACM panels at the east façade of Area A, at the parapet; angled stud framing is being installed by Lymo ahead of the angled ACM panels (see photo on page 4); see also photo on page 7 of 12 of attached RJK FR-19). Site work: 1. RBO has spread loam and prepped for the concrete walkways immediately west of Area D; at the time of observation RBO’s subcontractor was in the process of pouring those walkways. See photos on 3 and 5. 2. According to CB, irrigation is complete minus the heads at field C. 3. RBO is about to commence installation of the safety netting and footings for playground equipment. DISCREPANCIES, SPECIAL INSTRUCTIONS New items 9011. Millwork installation under stairs. For millwork under the stairs, the radiant panel had been set too far out from the wall to accommodate millwork per shop drawings; Arden to adjust radiant panel and Wright to make struts for the millwork bench slightly thinner (see photo on page 3. Prior items 8183. (from 8-18 site report) Shot put concrete curb in wrong location: Still open 8184. (from 8-18 site report) Disconnect between PVC roof membrane and AVB: Still open 8185. (from 8-18 site report) Unsealed prefab pipe flashing. Still open 8111. (from 8-11 site report) Water filling station at Level 2. Still open 8112. (from 8-11 site report) Metal in contact with roof membrane. This has been addressed according to CB 7191. (from 07 19 site report) Exterior Sealant at brick pattern at inside link corner. still open 7192. (from 07 19 site report) Gap at PCC base and CW at Area D stair entries. still open 6305. (from 04 21 site report) Steel protrusion at auditorium. still open. Attachments · RJK site report FR 19 (from 08-30-2022) SITE PHOTOS LEVEL 1 MATTACHEESE LOBBY LOOKING SOUTH (AREA B) REPORT BY: ABH Page 3 of 5 BENCH INSTALLATION (AREA D) DISPLAY CASE INSTALLATION (AREA C) CORRIDOR AT AUDITORIUM LOBBY (A) LOAM INSTALLATION (NORTH COURT) PROTECTED CW ENTRANCE (AREA B) FRESH SIDEWALK POUR AT C-D WEST REPORT BY: ABH Page 4 of 5 ACM PAREAPET INSTALLATION (AREA A) AUDITORIUM PROGRESS (AREA A) MARKER BOARD INSTALLATION PROGRESS (AREA D LEVEL 1) REPORT BY: ABH Page 5 of 5 UNDER-STAIR BENCH MILLWORK READY FOR INSTALLATION (AREA C) SITE WORK PROGRESS AT WEST OF ACADEMIC WINGS INSTALLATION OF WOOD ‘COFFERED’ CEILING AT MEDIA CENTER (AREA B) FIELD REPORT RJK discussed the issues with CB prior to leaving the site. Work Observed • Various Cladding Installation • Sealant Joint Installation • Roofing Installation Observations • Part C, East Elevation Rising Walls, Grid Lines C11 - C12, and Part D, West and East Elevations Rising Walls, Grid Lines D24 - D25 - Reider formparts.fab outside corners were installed fastened to the horizontal galvanized hat channel with color matched screws. (Figure 1, Figure 2) • Part A, North Elevation, Grid Lines B4 - B14, K - Jamb and head flashings were installed at curtain walls where Rieder Öko Skin is installed. The metal laps over the end dams of the through-wall flashing at the top of the brick cladding. (Figures 3, 4) • Part B, South Elevation Curtain Walls, Grid Lines A17 - B21, and Part A, East Elevation Curtain Walls, Grid Lines V - S.1 - At the sealant joints between flashing and curtain wall, backer rod and sealant were installed. The backer rod is set half the width of the joint into the cavity, to a maximum of ½-inch recessed. Sealant was applied and tooled in by sealant knife to create a concave shape to the sealant. (Figures 5, 6) • Part A, East Elevation, Grid Lines V - T.2 - GreenGirt is installed wet set in sealant and fastened utilizing screws. Six (6) inch mineral wool insulation is set between the GreenGirt. (Figure 7) • Part A, North, East and West Elevation Rising Walls, Grid Lines A1 - B13 - LYMO 2000 ACM Panels were installed fastened utilizing panel clips to the horizontal GreenGirt. Factory outside corner panels were installed fastened utilizing clips to the horizontal GreenGirt. (Figures 8, 9) • Part A, East Elevation, Grid Lines V - S.1 and Part B, South Elevation, Grid Lines A17 - B21 - Stud framing was installed prior to installation to the angled ACM panels. (Figure 10) • Part B, South Low Roof Parapets, Grid Lines B21 - B33, and Part C West and East Elevations, Grid Lines E-H, and Part D, West and East Elevations Grid Lines A - D - Sheet metal coping was installed at Project: Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School Report Number: FR-19 Property Address: 276 Station Avenue, South Yarmouth, MA 02664 Client: Perkins Eastman Date of Site Visit: Tuesday, August 30, 2022 Report Date: Wednesday, August 31, 2022 Weather: Cloudy 79°F Purpose of Visit: Observe Building Enclosure Construction On-Site During Visit: Michael Groome - R. J. Kenney Associates, Inc. (RJK) Paul Genereux - Commodore Builders (CB) Ken - Beacon Waterproofing and Restoration Inc (Beacon) Report By: Michael Groome Report Attachments: Detailed Photographs Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School Report Number: FR-19 8/31/2022 Report G:\RJK\WORD\32202 Q504 Mattacheese DYIMS Yarmouth FR19 Report 8-30-22.docx Page 2 of 12 parapet walls in various locations. Angle metal was installed wet set in sealant and fastened utilizing screws. The panels were then installed fastened to the angles utilizing screws. A concealed plate is installed at seams with each panel set in sealant at the plate. (Figures 11 - 13) Discussion Items • Damaged and Unsealed Prefabricated Pipe Flashing - South B, Low Roof, Grid Lines B26.5, N.6 - A prefabricated pipe flashing is compressed, and the sealant applied around the top is unadhered. It appears the flashing was not set in sealant and there was no clamping ring installed. Clean the areas, fix the flashing, apply sealant under the top flange and install a clamping ring. (Figures 14, 15) • Roof Membrane Damage - Part C, East, Grid Lines C19, G - Two areas of damage are marked in black lumber crayon. Repair per the manufacturer’s requirements. (Figures 16 - 18) • Open Pipe Penetrations - Part C, East, Grid Lines C20, F.5 - A pipe penetration is not sealed, leaving an entrance for moisture to infiltrate into the roof assembly and the building. Detail the pipe per the manufacturer’s requirements. (Figures 16, 19, 20) END OF REPORT RJK has no contractual responsibility in the design or actual construction of the project and is acting solely in a consultant and/or in an advisory capacity to the Client. Any and all modifications, changes, recommendations, suggestions, etc., relating to the design and/or construction, should be forwarded, reviewed, and approved by the designer of record prior to implementation. RJK reserves the right to change or amend this report as new information becomes available. Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School Report Number FR-19 8/31/2022 Appendix A G:\RJK\WORD\32202 Q504 Mattacheese DYIMS Yarmouth FR19 Report 8-30-22.docx Page 3 of 12 Callouts: 1. Outside corner detailing Comments: 0830 010 R. J. Kenney Associates, Inc. Figure 1 ‐ Reider formpart.fab outside corners Callouts: 1. Horizontal hat channel 2. Reider formpart.fab outside corners Comments: 0830 011 R. J. Kenney Associates, Inc. Figure 2 ‐ Outside Corner Installation 1 1 2 Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School Report Number FR-19 8/31/2022 Appendix A G:\RJK\WORD\32202 Q504 Mattacheese DYIMS Yarmouth FR19 Report 8-30-22.docx Page 4 of 12 Callouts: 1. Flashing at jambs and heads Comments: 0830 015 R. J. Kenney Associates, Inc. Figure 3 ‐ Jamb and Head Flashing at Rieder Öko Skin Callouts: 1. Sheet metal jamb flashing 2. Through-wall flashing Comments: 0830 017 R. J. Kenney Associates, Inc. Figure 4 ‐ Jamb Flashing Laps Though-Wall Flashing End Dam 1 1 1 1 2 Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School Report Number FR-19 8/31/2022 Appendix A G:\RJK\WORD\32202 Q504 Mattacheese DYIMS Yarmouth FR19 Report 8-30-22.docx Page 5 of 12 Callouts: 1. Sealant joint Comments: 0830 048 R. J. Kenney Associates, Inc. Figure 5 ‐ Sealant at Curtain Wall Callouts: 1. Pressure bar 2. Sealant joint Comments: 0830 049 R. J. Kenney Associates, Inc. Figure 6 ‐ Backer Rod and Sealant Joint 1 1 2 Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School Report Number FR-19 8/31/2022 Appendix A G:\RJK\WORD\32202 Q504 Mattacheese DYIMS Yarmouth FR19 Report 8-30-22.docx Page 6 of 12 Callouts: 1. GreenGirt 2. Mineral wool insulation Comments: 0830 034 R. J. Kenney Associates, Inc. Figure 7 ‐ Green Girt and Insulation Callouts: 1. Factory corner panel 2. Clips Comments: 0830 024 R. J. Kenney Associates, Inc. Figure 8 ‐ Factory Corner Panel 1 2 1 2 Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School Report Number FR-19 8/31/2022 Appendix A G:\RJK\WORD\32202 Q504 Mattacheese DYIMS Yarmouth FR19 Report 8-30-22.docx Page 7 of 12 Callouts: 1. Clips Comments: 0830 033 R. J. Kenney Associates, Inc. Figure 9 ‐ LYMO 2000 ACM panels Callouts: 1. Stud framing Comments: 0830 037 R. J. Kenney Associates, Inc. Figure 10 ‐ Stud Framing for Angle ACM Panel 1 1 1 1 1 1 Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School Report Number FR-19 8/31/2022 Appendix A G:\RJK\WORD\32202 Q504 Mattacheese DYIMS Yarmouth FR19 Report 8-30-22.docx Page 8 of 12 Callouts: Comments: 0830 088 R. J. Kenney Associates, Inc. Figure 11 ‐ Angle Metal Installation Callouts: 1. Sealant bleed out 2. Angle metal 3. Sheet metal coping Comments: 0830 057 R. J. Kenney Associates, Inc. Figure 12 ‐ Wet Set Angle Metal 1 2 3 Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School Report Number FR-19 8/31/2022 Appendix A G:\RJK\WORD\32202 Q504 Mattacheese DYIMS Yarmouth FR19 Report 8-30-22.docx Page 9 of 12 Callouts: 1. Coping 2. Concealed plate at laps 3. Angle metal Comments: 0830 055 R. J. Kenney Associates, Inc. Figure 13 ‐ Low Roof Coping Callouts: 1. Prefabricated pipe flashing Comments: 0830 058 R. J. Kenney Associates, Inc. Figure 14 ‐ Compressed and Unsealed Pipe Flashing 1 2 3 1 Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School Report Number FR-19 8/31/2022 Appendix A G:\RJK\WORD\32202 Q504 Mattacheese DYIMS Yarmouth FR19 Report 8-30-22.docx Page 10 of 12 Callouts: 1. Pipe penetration 2. Prefabricate pipe flashing 3. Sealant Comments: 0830 060 R. J. Kenney Associates, Inc. Figure 15 ‐ No Sealant at Prefabricated Pipe Flashing Callouts: 1. Damage 2. Unsealed pipe Comments: 0830 073 R. J. Kenney Associates, Inc. Figure 16 ‐ Locations of Roof Damage and Unsealed Pipe 1 1 2 1 2 3 Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School Report Number FR-19 8/31/2022 Appendix A G:\RJK\WORD\32202 Q504 Mattacheese DYIMS Yarmouth FR19 Report 8-30-22.docx Page 11 of 12 Callouts: Comments: 0830 077 R. J. Kenney Associates, Inc. Figure 17 ‐ Roof Damage Callouts: Comments: 0830 078 R. J. Kenney Associates, Inc. Figure 18 ‐ Roof Damage Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School Report Number FR-19 8/31/2022 Appendix A G:\RJK\WORD\32202 Q504 Mattacheese DYIMS Yarmouth FR19 Report 8-30-22.docx Page 12 of 12 Callouts: 1. Open penetration Comments: 0830 079 R. J. Kenney Associates, Inc. Figure 19 ‐ Unsealed Pipe Penetration Callouts: Comments: 0830 080 R. J. Kenney Associates, Inc. Figure 20 ‐ Open Area at Penetration 1 Building Envelope Field Report Tracking Log Q504 - Mattacheese DYMIS Yarmouth Tracking Log 8/30/2022 Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status 2.3 Wetted Polyisocyanurate Insulation Part D Roof Open 2.4 Upside Down Insulation Part D Roof 05/17/22: Written approval from the manufacturer that the orientation is acceptable for the assembly will close the item, otherwise correction of installation methods. Open 3.4 Wet Polyisocyanurate Insulation and Cover Board Is Installed Part C 05/12/22: Testing will be necessary to confirm materials are dry and without organic growth. Open 3.5 Incomplete Night Tie-In Part C 05/17/22: Testing should be conducted at the location to ensure no moisture intrusion occurred at the incomplete tie in. Open 4.3 Interior Air Barrier Seal at Windows Part D 04/28/22: Please provide approved direction for the issue. Open 4.4 Window Fastening Part D 04/28/22: Please provide photos of sealant at fasteners. Open FR-1, 12/15/2021 FR-3, 12/28/2021 FR-2, 12/22/2021 FR-4, 1/6/2022 G:\RJK\WORD\32203 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 8-30-22 1 of 5 Building Envelope Field Report Tracking Log Q504 - Mattacheese DYMIS Yarmouth Tracking Log 8/30/2022 Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status 4.5 Wet Polyisocyanurate Insulation and Cover Board Is Installed Part C and Part D Roofs 05/12/22: Testing will be necessary to confirm materials are dry and without organic growth. Open 4.6 Pitch Pocket Detail Part C 04/28/22: No change.Open 4.7 Uncut Clamping Rings Part C 04/07/22: Multiple clamping rings still left uncut at Part C. 04/28/22: No change. Open 6.1 Voids in Damproofing From Damage Part D and Part C Open 6.3 Roof Debris Typical 04/28/22: Some large equipment is on plywood, although screws, pipes and other debris are still observed on the membrane. Open 6.4 Roof Ponding Part C to Part B 04/28/22: Additional ponding is observed at the west breezeway. 05/12/22: Ponding is continuously observed at both locations. Open FR-6, 4/7/2022 FR-5, 3/21/2022 G:\RJK\WORD\32203 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 8-30-22 2 of 5 Building Envelope Field Report Tracking Log Q504 - Mattacheese DYMIS Yarmouth Tracking Log 8/30/2022 Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status 6.5 PVC In Contact with Asphalt Part B Penthouse 04/28/22: Membrane is still in contact, and through wall flashing is installed. 05/12/22: No change observed. 08/08/22: Repairs to the roof membrane in contact with asphaltic adhesive were conducted. The affect membrane was cut back, and a new strip of polyvinyl chloride (PVC) membrane heat welded to the existing base flashing and then glued to the wall over the roofing vapor barrier. A bead of Sika Sarnafil Sika-Flex is gun applied to the top edge of the membrane and struck in. It is our understanding that this repair method will be conducted at similar areas on the stair tower. Open FR-8, 5/12/2022 FR-7, 4/28/2022 No New Issues G:\RJK\WORD\32203 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 8-30-22 3 of 5 Building Envelope Field Report Tracking Log Q504 - Mattacheese DYMIS Yarmouth Tracking Log 8/30/2022 Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status 8.2 Discontinued AVB at Curtain Wall Column Part B, East Elevation Rising Wall, Grid Lines M.9-L Open 8.4 Roof Discontinuation Between Vapor Barrier and PVC Membrane Part B, Gymnasium Roof, Grid Lines B24 - B25 Open 13.1 End Dams at Through-Wall Part B, East Elevation, Grid Line B33 Open 15.1 Glazed in ACM Panels Part B, South Elevation, Curtain Wall, Grid Lines A17- B21 Open FR-9, 5/17/2022 No New Issues FR-10, 6/10/2022 No New Issues FR-16, 8/8/2022 FR-15, 8/1/2022 FR-12, 6/21/2022 No New Issues FR-11, 6/16/2022 No New Issues FR-14, 7/8/2022 FR-13, 7/1/2022 G:\RJK\WORD\32203 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 8-30-22 4 of 5 Building Envelope Field Report Tracking Log Q504 - Mattacheese DYMIS Yarmouth Tracking Log 8/30/2022 Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status 16.1 Metal Panel in Contact with Roof Membrane Part C and D, East and West Elevations, Stair Towers 08/18/22: The metal has been cut back. Closed 17.1 Damaged Metal Panels Part C, Courtyard East Elevation, Parapet Level Open 17.2 Disconnect Between PVC Roof Membrane and AVB Part B, South Elevation, Parapet Open 17.3 Unsealed Prefabricated Pipe Flashing Part B Roof, Grid Lines L, B16 Open 19.1 Damaged and Unsealed Prefabricated Pipe Flashing South B, Low Roof, Grid Lines B26.5, N.6 Open 19.2 Roof Membrane Damage Part C, East, Grid Lines C19, G Open 19.3 Open Pipe Penetrations Part C, East, Grid Lines C20, F.5 Open FR-19, 8/30/2022 No New Issues FR-18, 8/22/2022 FR-17, 8/18/2022 G:\RJK\WORD\32203 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 8-30-22 5 of 5