Architect: Perkins Eastman DPC
Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File
ARCHITECT’S SITE OBSERVATION REPORT
DATE OF VISIT: 09/01/2022 PROJECT: Dennis Yarmouth Intermediate
Middle School
286 Station Avenue
South Yarmouth, MA 02664
DATE OF ISSUE: 09/13/2022 PROJECT NO: 71011
WEATHER
CONDITIONS:
Sunny and clear, 80s ARCHITECT: Perkins Eastman, DPC
20 Ashburton Street
8th floor
Boston, MA
The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit.
WORK IN PROGRESS:
1) Drywall installation
2) Drywall taping and painting
3) Tack board and marker board installation
4) Classroom casework installation
5) Classroom Linoleum flooring installation
6) Millwork installation
7) Ceiling framing; ceiling installation
8) MEP/FP finish work—light fixtures etc.
9) Interior painting
10) Curtain wall silicone sealing
11) GFRC panel installation
12) ACM panel installation and prep
13) Site work
FIELD OBSERVATIONS:
PE visited the site on Thursday 09-01, to review ongoing progress.
Interior Items
1. The installation of finishes at Area D is still ongoing, including linoleum flooring installation and marker board
installation (see photo on page 5). Ceiling installation is almost complete in the classrooms and is at 90% in the
corridors.
2. O’Byrne has started the yellow paint on the steel stair stringers and guards at Area D (see photo on page 3).
3. At the time of observation, Wright was in the process of installing the bench under the west stairs at Area D (see
photo on page 3); the radiused millwork portals at the link ‘connectors’ are scheduled to be installed next week
according to CB.
4. Earlier in the week Harold Brothers installed the bottle filling stations at Area D.
5. At Area C, Millwork and casework installation are both still ongoing; “krion” classroom portals at levels 1 and 2 are
completed.
6. At Area C, above-ceiling MEP is almost complete on level 2; will be ready for inspection on 09-06 per CB.
7. At Area C, the installation of ceiling grids, finished ceilings and MEP fixtures are all ongoing.
8. At Area B, H. Carr was in the process of installing the wood “coffers” at the media center in the circulation area at
the time of observation (see photo on page 5).
9. O’Byrne is in the process of painting the ceilings at the Area B central commons area, with locker room areas to
get painted next (according to Commodore).
10. According to CB O’Byrne is due to finish painting the gymnasium steel / MEP on 09-02 (Friday), and all of the wall
painting in Area B is scheduled to be complete next week.
11. The installation of gymnasium accessories (e.g. curtains, hoops etc.) is due to begin next week.
12. At Area A, the staging for the work platform in the auditorium has been removed (see photo on page 4).
REPORT BY: ABH Page 2 of 5
13. At area A, Above-ceiling MEP work is complete at the cafeteria and kitchen—ready for ceiling installation.
Exterior items:
1. Lymo is in the process of installing the Oko skin “formpart” outside corners, beginning at C wing and D wing (see
photo in attached RJK field report FR-19).
2. Lymo has now completed the angled ACM coping at the south low wing of the gymnasium.
3. Lymo has replaced the damaged panels at the parapet of the SW link structure (see “prior item” for action #8112).
4. At the time of observation Lymo had replaced (or re-installed) the GFRC panels around the cafeteria CW
openings where the punctured ETA had to be repaired by Beacon (see relevant section of 8-25 site observation
report).
5. According to the attached RJK FR-19, Lymo installed the factory corner ACM panels at the NW corner of the
auditorium on 8-31 (see photo in FR-19).
6. Lymo has installed the ACM at auditorium entry vestibule on 8-31 (see photo on page 4).
7. At the time of observation, Lymo was installing the angled ACM panels at the east façade of Area A, at the
parapet; angled stud framing is being installed by Lymo ahead of the angled ACM panels (see photo on page 4);
see also photo on page 7 of 12 of attached RJK FR-19).
Site work:
1. RBO has spread loam and prepped for the concrete walkways immediately west of Area D; at the time of
observation RBO’s subcontractor was in the process of pouring those walkways. See photos on 3 and 5.
2. According to CB, irrigation is complete minus the heads at field C.
3. RBO is about to commence installation of the safety netting and footings for playground equipment.
DISCREPANCIES, SPECIAL INSTRUCTIONS
New items
9011. Millwork installation under stairs. For millwork under the stairs, the radiant panel had been set too far out
from the wall to accommodate millwork per shop drawings; Arden to adjust radiant panel and Wright to
make struts for the millwork bench slightly thinner (see photo on page 3.
Prior items
8183. (from 8-18 site report) Shot put concrete curb in wrong location: Still open
8184. (from 8-18 site report) Disconnect between PVC roof membrane and AVB: Still open
8185. (from 8-18 site report) Unsealed prefab pipe flashing. Still open
8111. (from 8-11 site report) Water filling station at Level 2. Still open
8112. (from 8-11 site report) Metal in contact with roof membrane. This has been addressed according to CB
7191. (from 07 19 site report) Exterior Sealant at brick pattern at inside link corner. still open
7192. (from 07 19 site report) Gap at PCC base and CW at Area D stair entries. still open
6305. (from 04 21 site report) Steel protrusion at auditorium. still open.
Attachments
· RJK site report FR 19 (from 08-30-2022)
SITE PHOTOS
LEVEL 1 MATTACHEESE LOBBY LOOKING SOUTH (AREA B)
REPORT BY: ABH Page 3 of 5
BENCH INSTALLATION (AREA D) DISPLAY CASE INSTALLATION (AREA C) CORRIDOR AT AUDITORIUM LOBBY (A)
LOAM INSTALLATION (NORTH COURT) PROTECTED CW ENTRANCE (AREA B) FRESH SIDEWALK POUR AT C-D WEST
REPORT BY: ABH Page 4 of 5
ACM PAREAPET INSTALLATION (AREA A)
AUDITORIUM PROGRESS (AREA A)
MARKER BOARD INSTALLATION PROGRESS (AREA D LEVEL 1)
REPORT BY: ABH Page 5 of 5
UNDER-STAIR BENCH MILLWORK READY FOR INSTALLATION (AREA C)
SITE WORK PROGRESS AT WEST OF ACADEMIC WINGS
INSTALLATION OF WOOD ‘COFFERED’ CEILING AT MEDIA CENTER (AREA B)
FIELD REPORT
RJK discussed the issues with CB prior to leaving the site.
Work Observed
• Various Cladding Installation
• Sealant Joint Installation
• Roofing Installation
Observations
• Part C, East Elevation Rising Walls, Grid Lines C11 - C12, and Part D, West and East Elevations Rising
Walls, Grid Lines D24 - D25 - Reider formparts.fab outside corners were installed fastened to the
horizontal galvanized hat channel with color matched screws. (Figure 1, Figure 2)
• Part A, North Elevation, Grid Lines B4 - B14, K - Jamb and head flashings were installed at curtain
walls where Rieder Öko Skin is installed. The metal laps over the end dams of the through-wall flashing
at the top of the brick cladding. (Figures 3, 4)
• Part B, South Elevation Curtain Walls, Grid Lines A17 - B21, and Part A, East Elevation Curtain Walls,
Grid Lines V - S.1 - At the sealant joints between flashing and curtain wall, backer rod and sealant were
installed. The backer rod is set half the width of the joint into the cavity, to a maximum of ½-inch
recessed. Sealant was applied and tooled in by sealant knife to create a concave shape to the sealant.
(Figures 5, 6)
• Part A, East Elevation, Grid Lines V - T.2 - GreenGirt is installed wet set in sealant and fastened
utilizing screws. Six (6) inch mineral wool insulation is set between the GreenGirt. (Figure 7)
• Part A, North, East and West Elevation Rising Walls, Grid Lines A1 - B13 - LYMO 2000 ACM Panels
were installed fastened utilizing panel clips to the horizontal GreenGirt. Factory outside corner panels
were installed fastened utilizing clips to the horizontal GreenGirt. (Figures 8, 9)
• Part A, East Elevation, Grid Lines V - S.1 and Part B, South Elevation, Grid Lines A17 - B21 - Stud
framing was installed prior to installation to the angled ACM panels. (Figure 10)
• Part B, South Low Roof Parapets, Grid Lines B21 - B33, and Part C West and East Elevations, Grid
Lines E-H, and Part D, West and East Elevations Grid Lines A - D - Sheet metal coping was installed at
Project: Q504 - Mattacheese, Dennis-Yarmouth Intermediate
Middle School Report Number: FR-19
Property Address: 276 Station Avenue, South Yarmouth, MA 02664
Client: Perkins Eastman
Date of Site Visit: Tuesday, August 30, 2022
Report Date: Wednesday, August 31, 2022
Weather: Cloudy 79°F
Purpose of Visit: Observe Building Enclosure Construction
On-Site During Visit:
Michael Groome - R. J. Kenney Associates, Inc. (RJK)
Paul Genereux - Commodore Builders (CB)
Ken - Beacon Waterproofing and Restoration Inc (Beacon)
Report By: Michael Groome
Report Attachments: Detailed Photographs
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number: FR-19
8/31/2022
Report
G:\RJK\WORD\32202 Q504 Mattacheese DYIMS Yarmouth FR19 Report 8-30-22.docx Page 2 of 12
parapet walls in various locations. Angle metal was installed wet set in sealant and fastened utilizing
screws. The panels were then installed fastened to the angles utilizing screws. A concealed plate is
installed at seams with each panel set in sealant at the plate. (Figures 11 - 13)
Discussion Items
• Damaged and Unsealed Prefabricated Pipe Flashing - South B, Low Roof, Grid Lines B26.5, N.6 - A
prefabricated pipe flashing is compressed, and the sealant applied around the top is unadhered. It
appears the flashing was not set in sealant and there was no clamping ring installed. Clean the areas, fix
the flashing, apply sealant under the top flange and install a clamping ring. (Figures 14, 15)
• Roof Membrane Damage - Part C, East, Grid Lines C19, G - Two areas of damage are marked in black
lumber crayon. Repair per the manufacturer’s requirements. (Figures 16 - 18)
• Open Pipe Penetrations - Part C, East, Grid Lines C20, F.5 - A pipe penetration is not sealed, leaving an
entrance for moisture to infiltrate into the roof assembly and the building. Detail the pipe per the
manufacturer’s requirements. (Figures 16, 19, 20)
END OF REPORT
RJK has no contractual responsibility in the design or actual construction of the project and is acting solely in a consultant and/or in an
advisory capacity to the Client. Any and all modifications, changes, recommendations, suggestions, etc., relating to the design and/or
construction, should be forwarded, reviewed, and approved by the designer of record prior to implementation. RJK reserves the right
to change or amend this report as new information becomes available.
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-19
8/31/2022
Appendix A
G:\RJK\WORD\32202 Q504 Mattacheese DYIMS Yarmouth FR19 Report 8-30-22.docx Page 3 of 12
Callouts:
1. Outside corner detailing
Comments:
0830 010 R. J. Kenney Associates, Inc.
Figure 1 ‐ Reider formpart.fab outside corners
Callouts:
1. Horizontal hat channel
2. Reider formpart.fab
outside corners
Comments:
0830 011 R. J. Kenney Associates, Inc.
Figure 2 ‐ Outside Corner Installation
1
1
2
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-19
8/31/2022
Appendix A
G:\RJK\WORD\32202 Q504 Mattacheese DYIMS Yarmouth FR19 Report 8-30-22.docx Page 4 of 12
Callouts:
1. Flashing at jambs and
heads
Comments:
0830 015 R. J. Kenney Associates, Inc.
Figure 3 ‐ Jamb and Head Flashing at Rieder Öko Skin
Callouts:
1. Sheet metal jamb flashing
2. Through-wall flashing
Comments:
0830 017 R. J. Kenney Associates, Inc.
Figure 4 ‐ Jamb Flashing Laps Though-Wall Flashing End Dam
1
1
1
1
2
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-19
8/31/2022
Appendix A
G:\RJK\WORD\32202 Q504 Mattacheese DYIMS Yarmouth FR19 Report 8-30-22.docx Page 5 of 12
Callouts:
1. Sealant joint
Comments:
0830 048 R. J. Kenney Associates, Inc.
Figure 5 ‐ Sealant at Curtain Wall
Callouts:
1. Pressure bar
2. Sealant joint
Comments:
0830 049 R. J. Kenney Associates, Inc.
Figure 6 ‐ Backer Rod and Sealant Joint
1
1
2
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-19
8/31/2022
Appendix A
G:\RJK\WORD\32202 Q504 Mattacheese DYIMS Yarmouth FR19 Report 8-30-22.docx Page 6 of 12
Callouts:
1. GreenGirt
2. Mineral wool insulation
Comments:
0830 034 R. J. Kenney Associates, Inc.
Figure 7 ‐ Green Girt and Insulation
Callouts:
1. Factory corner panel
2. Clips
Comments:
0830 024 R. J. Kenney Associates, Inc.
Figure 8 ‐ Factory Corner Panel
1
2
1
2
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-19
8/31/2022
Appendix A
G:\RJK\WORD\32202 Q504 Mattacheese DYIMS Yarmouth FR19 Report 8-30-22.docx Page 7 of 12
Callouts:
1. Clips
Comments:
0830 033 R. J. Kenney Associates, Inc.
Figure 9 ‐ LYMO 2000 ACM panels
Callouts:
1. Stud framing
Comments:
0830 037 R. J. Kenney Associates, Inc.
Figure 10 ‐ Stud Framing for Angle ACM Panel
1
1
1
1
1
1
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-19
8/31/2022
Appendix A
G:\RJK\WORD\32202 Q504 Mattacheese DYIMS Yarmouth FR19 Report 8-30-22.docx Page 8 of 12
Callouts:
Comments:
0830 088 R. J. Kenney Associates, Inc.
Figure 11 ‐ Angle Metal Installation
Callouts:
1. Sealant bleed out
2. Angle metal
3. Sheet metal coping
Comments:
0830 057 R. J. Kenney Associates, Inc.
Figure 12 ‐ Wet Set Angle Metal
1
2
3
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-19
8/31/2022
Appendix A
G:\RJK\WORD\32202 Q504 Mattacheese DYIMS Yarmouth FR19 Report 8-30-22.docx Page 9 of 12
Callouts:
1. Coping
2. Concealed plate at laps
3. Angle metal
Comments:
0830 055 R. J. Kenney Associates, Inc.
Figure 13 ‐ Low Roof Coping
Callouts:
1. Prefabricated pipe
flashing
Comments:
0830 058 R. J. Kenney Associates, Inc.
Figure 14 ‐ Compressed and Unsealed Pipe Flashing
1
2
3
1
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-19
8/31/2022
Appendix A
G:\RJK\WORD\32202 Q504 Mattacheese DYIMS Yarmouth FR19 Report 8-30-22.docx Page 10 of 12
Callouts:
1. Pipe penetration
2. Prefabricate pipe flashing
3. Sealant
Comments:
0830 060 R. J. Kenney Associates, Inc.
Figure 15 ‐ No Sealant at Prefabricated Pipe Flashing
Callouts:
1. Damage
2. Unsealed pipe
Comments:
0830 073 R. J. Kenney Associates, Inc.
Figure 16 ‐ Locations of Roof Damage and Unsealed Pipe
1 1
2
1
2
3
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-19
8/31/2022
Appendix A
G:\RJK\WORD\32202 Q504 Mattacheese DYIMS Yarmouth FR19 Report 8-30-22.docx Page 11 of 12
Callouts:
Comments:
0830 077 R. J. Kenney Associates, Inc.
Figure 17 ‐ Roof Damage
Callouts:
Comments:
0830 078 R. J. Kenney Associates, Inc.
Figure 18 ‐ Roof Damage
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number FR-19
8/31/2022
Appendix A
G:\RJK\WORD\32202 Q504 Mattacheese DYIMS Yarmouth FR19 Report 8-30-22.docx Page 12 of 12
Callouts:
1. Open penetration
Comments:
0830 079 R. J. Kenney Associates, Inc.
Figure 19 ‐ Unsealed Pipe Penetration
Callouts:
Comments:
0830 080 R. J. Kenney Associates, Inc.
Figure 20 ‐ Open Area at Penetration
1
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
8/30/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
2.3 Wetted Polyisocyanurate
Insulation
Part D Roof Open
2.4
Upside Down Insulation Part D Roof 05/17/22: Written approval
from the manufacturer that the
orientation is acceptable for the
assembly will close the item,
otherwise correction of
installation methods.
Open
3.4
Wet Polyisocyanurate
Insulation and Cover Board Is
Installed
Part C 05/12/22: Testing will be
necessary to confirm materials
are dry and without organic
growth.
Open
3.5
Incomplete Night Tie-In Part C 05/17/22: Testing should be
conducted at the location to
ensure no moisture intrusion
occurred at the incomplete tie
in.
Open
4.3
Interior Air Barrier Seal at
Windows
Part D 04/28/22: Please provide
approved direction for the issue. Open
4.4
Window Fastening Part D 04/28/22: Please provide
photos of sealant at fasteners. Open
FR-1, 12/15/2021
FR-3, 12/28/2021
FR-2, 12/22/2021
FR-4, 1/6/2022
G:\RJK\WORD\32203 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 8-30-22 1 of 5
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
8/30/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
4.5
Wet Polyisocyanurate
Insulation and Cover Board Is
Installed
Part C and Part
D Roofs
05/12/22: Testing will be
necessary to confirm materials
are dry and without organic
growth.
Open
4.6 Pitch Pocket Detail Part C 04/28/22: No change.Open
4.7
Uncut Clamping Rings Part C 04/07/22: Multiple clamping
rings still left uncut at Part C.
04/28/22: No change.
Open
6.1 Voids in Damproofing From
Damage
Part D and Part
C Open
6.3
Roof Debris Typical 04/28/22: Some large
equipment is on plywood,
although screws, pipes and
other debris are still observed
on the membrane.
Open
6.4
Roof Ponding Part C to Part B 04/28/22: Additional ponding
is observed at the west
breezeway.
05/12/22: Ponding is
continuously observed at both
locations.
Open
FR-6, 4/7/2022
FR-5, 3/21/2022
G:\RJK\WORD\32203 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 8-30-22 2 of 5
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
8/30/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
6.5
PVC In Contact with Asphalt Part B Penthouse 04/28/22: Membrane is still in
contact, and through wall
flashing is installed.
05/12/22: No change observed.
08/08/22: Repairs to the roof
membrane in contact with
asphaltic adhesive were
conducted. The affect
membrane was cut back, and a
new strip of polyvinyl chloride
(PVC) membrane heat welded
to the existing base flashing and
then glued to the wall over the
roofing vapor barrier. A bead
of Sika Sarnafil Sika-Flex is
gun applied to the top edge of
the membrane and struck in. It
is our understanding that this
repair method will be
conducted at similar areas on
the stair tower.
Open
FR-8, 5/12/2022
FR-7, 4/28/2022
No New Issues
G:\RJK\WORD\32203 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 8-30-22 3 of 5
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
8/30/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
8.2
Discontinued AVB at Curtain
Wall Column
Part B, East
Elevation Rising
Wall, Grid Lines
M.9-L
Open
8.4
Roof Discontinuation Between
Vapor Barrier and PVC
Membrane
Part B,
Gymnasium
Roof, Grid Lines
B24 - B25
Open
13.1
End Dams at Through-Wall Part B, East
Elevation, Grid
Line B33
Open
15.1
Glazed in ACM Panels Part B, South
Elevation,
Curtain Wall,
Grid Lines A17-
B21
Open
FR-9, 5/17/2022
No New Issues
FR-10, 6/10/2022
No New Issues
FR-16, 8/8/2022
FR-15, 8/1/2022
FR-12, 6/21/2022
No New Issues
FR-11, 6/16/2022
No New Issues
FR-14, 7/8/2022
FR-13, 7/1/2022
G:\RJK\WORD\32203 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 8-30-22 4 of 5
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
8/30/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
16.1
Metal Panel in Contact with
Roof Membrane
Part C and D,
East and West
Elevations, Stair
Towers
08/18/22: The metal has been
cut back. Closed
17.1
Damaged Metal Panels Part C,
Courtyard East
Elevation,
Parapet Level
Open
17.2
Disconnect Between PVC Roof
Membrane and AVB
Part B, South
Elevation,
Parapet
Open
17.3
Unsealed Prefabricated Pipe
Flashing
Part B Roof,
Grid Lines L,
B16
Open
19.1
Damaged and Unsealed
Prefabricated Pipe Flashing
South B, Low
Roof, Grid Lines
B26.5, N.6 Open
19.2
Roof Membrane Damage Part C, East,
Grid Lines C19,
G
Open
19.3
Open Pipe Penetrations Part C, East,
Grid Lines C20,
F.5
Open
FR-19, 8/30/2022
No New Issues
FR-18, 8/22/2022
FR-17, 8/18/2022
G:\RJK\WORD\32203 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 8-30-22 5 of 5